London East Phase 2 Development Update 2

We’ve been making steady progress on Phase 2 of our deployment plan at Netwise London East (NLE). This includes the total completion of Pod 2 in Data Hall 1, and large strides towards the onlining of Data Hall 2 in the coming months. This will be followed shortly thereafter with the base infrastructure deployment for Data Halls 3 and 4 later in the year.

We’ve been moving ahead firmly across various areas of general infrastructure, electrical and cooling systems for Data Hall 2, with the primary evaporative cooling system now in place ahead of commissioning. The feeder connections from the LV rooms to the in-hall distribution boards are now also in place, ahead of the main electrical works for the diverse rack feeds beginning in the coming weeks.

We’ll keep things brief this time around, so let’s get straight to the update photos:

Cabling
Here we have some of the additional cabling required to bring the next phase online at NLE
Cabling
Each of our data halls require a significant quantity of cabling to link them back to our diverse LV rooms
Cabling
We’ve certainly worked our way through a healthy number of large cable drums at this stage
Cabling
Pulling in these large armoured cables between floors can certainly be a challenge for the teams involved in this work
Cabling
With the main power cabling route handled under the raised floor at NLE, certain areas are cordoned off while works are underway, however disruption is generally kept to no more than a couple of hours at a time, per area
Cabling
These cable routes are already populated with live service power, as Data Hall 1 is fed via the same risers – here we see some new cabling ahead of being tied and cleated
Cabling
The longer of the two routes for the DH2 power delivery is from LV A – here we see the longer run with some of the cabling loose laid into the underfloor ladder
Cabling
The cabling routes flow down the risers to the diverse LV rooms, once they leave the main corridor(s)
Cabling
Considered placement of the large cable drums is vital in ensuring a smooth run-off of the cabling into the raised floor area – the same can be said for the cable rollers
Cabling
Drum placement must consider disruption, ease of access, and result in the least possible amount of free tail once the cable is fully released
DH2
Data Hall 2 has a range of components ready for installation, including some of the distribution boards, and the custom-made ODFs
Cooling
The primary cooling system for DH2 is now in place, that being our evaporative system which famously delivers our world-leading PUE figures
Cooling
As with DH1, we have space for seven CREC units, however we have deployed four initially – it is not expected that additional coolers will be needed, however installing them later would be a straightforward addition
Cooling
The cold corridor filtration system and overhead extraction loop are now complete for DH2 – this is taken ahead of the lights being installed, hence the low light conditions and temporary insulation panels
Pod 2
Pod 2 now has a range of active client deployments within it – in fact, Row C is now almost entirely accounted for
Pod 2
Pod 2 now also completes the full in-hall ODF to ODF pathway using the overhead ladder and trough system
Pod 2
Here’s a view of the back end of Data Hall 1, with both rear Pod entry door systems in view, and the CREC system for this room
Pod 2
This is the view inside Pod 2, as viewed from the rear entry doors
BuildRoom
Our Build and Break Room is now fully fitted out, and sees great use already by our clients
BuildRoom
The function of this one space is split at our London Central facility, which makes use more tricky, so we decided to consolidate amenities at London East for an improved visitor experience
BuildRoom
The wall features continue here, to tie in with other areas of the facility
BuildRoom
We’re particularly proud of our customer kitchen here, which has been expertly installed by our in-house facilities team, to the highest specification
BuildRoom
Be sure to check out the Build and Break Room on your next visit

We now have a dedicated roof hatch system installed over the storage mezzanine, for easier, direct access to the roof, which is important for speedy access to our heat extraction loop. We’ll update readers with photos of this area next time around.

We’re expecting to see a dramatic uptick in progress on Data Hall 2 in the next few weeks, as we head towards the peak activity period which will enable occupation of the space. This will also provide some additional visual change to enable a more in-depth update, which is something which has been lacking since the completion of Phase 1 – we apologise to our regular Build Blog readers for this!

Sustainability in-focus: beating our design PUE figures for a second year running

We are very excited to announce that our London Central (NLC) facility has once again exceeded expectations in terms of energy efficiency. NLC’s design PUE (Power Usage Effectiveness) is an impressive 1.12, but the annualised real-world PUE for the last 12 months was a staggering 1.09 – an improvement over the already remarkable 1.11 achieved the year prior.

NLC is our facility in Bermondsey, London, which we opened in 2015

For those unfamiliar with the concept of PUE, it is a measure of how much energy a data centre uses for computing compared to how much energy it uses for supporting load, such as cooling, UPS losses, fire systems etc. The goal for data centres is to have the lowest possible PUE, as this indicates the highest level of energy efficiency.

Even just meeting our design PUE would be impressive for a London data centre, but to exceed this by such a significant margin is something we’re hugely proud of.

We have consistently demonstrated our commitment to sustainability and energy efficiency across all aspects of our operation. This latest achievement is a testament to our ongoing efforts to reduce our carbon footprint and promote sustainable practices in the industry.

A real-world PUE of 1.09 ranks among the lowest PUEs reported by data centres worldwide, indicating that the facility is operating with a high level of energy efficiency and with minimal energy waste.

We believe that data centres have a significant role to play in mitigating the impacts of climate change, and we are proud to be leading the way in this effort. Our innovative approach to energy management, combined with our state-of-the-art technology and cutting-edge infrastructure, has enabled us to achieve these outstanding results.

Furthermore, the design PUE of our latest data centre, Netwise London East (NLE), is just 1.05. Reaching a facility’s design PUE target does require a high level of capacity utilisation, which takes time following launch (though helped by our modular design and deployment philosophy), however we couldn’t be more excited to see where our real-world figures lands at NLE in the coming months and years.

NLE opened in 2022, in Canning Town, and is on-track to be one of the most efficient data centres in the world

We would like to take this opportunity to thank our team and our customers for their continued support. We remain committed to driving innovation and sustainability in the data centre industry and look forward to continuing to push the boundaries of what is possible.

A look back at 2022

As we head into another exciting year here at Netwise, we would again like to take pause in January to appreciate the year gone by. 2022 was another important year for Netwise, most notably for seeing live client services deployed inside of our new Netwise London East (NLE) data centre for the first time.

We also began development on Phase Two of the London East development cycle in the very same year, just six months after our first anchor tenant entered Data Hall 1.

Pod 2
Since launching with Pod 1 back in early 2022, a further 28 racks have since joined total capacity in Data Hall 1, taking the space to its 56 enclosure capacity

As seems to be the recurring theme for all Netwise annual retrospectives, 2022 again represents a huge year for us in terms of investments. We’ve continued with our build-out of NLE, following on from Phase One completion earlier in the year.

We’ve seen a fantastic range of new client installations across our entire estate, along with the continued expansion of existing client systems, as our roster of exemplary customers leverage their critical deployments to grow and thrive.

Notable projects from 2022 include:

  • We soft-opened NLE to client installations – without question, our largest single project achievement in 2022 has been the introduction of live client systems to Data Hall 1 for the first time. You can catch up with the build, from start to finish, on our Build Blog.
  • We deployed Pod 2, Data Hall 1 at NLE – almost as quickly as we got Pod 1 online, it was time to get Pod 2 deployed to keep pace with new installations at NLE. The containment system for Pod 2 landed with us in the summer, and saw the first new system installed in September, across seven of the 28 new enclosures.
  • Phase Two of development at NLE began – in the closing stages of the year, we made great strides towards the next stage of development at London East. Data Hall 2 will form the first part of this next phase, with the cooling and extraction pathways now cut into the fabric of the building.
  • Nathan Desmond joined as Technical Manager – in November, we expanded our team with the joining of Nathan, our new Technical Manager. Expect a full introductory post very soon, to do full justice to this very important milestone.
  • We expanded our European locations in Marseille and Amsterdam – we’ve deployed new systems in both Marseille, FR and Amsterdam, NL, as we continue to support international clients with their pan-European installations. This takes our global spread of live deployments to 15 locations around the world, from our five PoPs in London, to as far away as Kuwait and Singapore.
  • NLC exceeded its design PUE, reaching an impressive 1.11 – our London Central facility officially beat its design PUE of 1.12 in early 2022, achieving a real-world annualised PUE of just 1.11 across 12 months. That makes NLC one of the most efficient data centres in the UK (and the world), particularly when coupled with our wider sustainability measures, such as our exclusive purchase of 100% renewable energy. In fact, our own London East facility will likely be the only data centre in the UK to beat this, with a design PUE of just 1.05 – a truly impressive figure.

As is clear to see, 2022 has certainly been dominated with all things NLE, following the soft-opening in May, and the continued investment in the space as we expand into our newest facility.

This doesn’t mean that our London Central facility (NLC) hasn’t seen its fair share of developments alongside, with some key monitoring upgrades deployed onto our generator system, amongst other minor upgrades and improvement works. With NLC running at near-capacity, it’s fantastic to see the natural efficiencies that come with taking a facility to its true design capabilities, a position many data centres rarely reach.

From a wider perspective, we’ve enjoyed another brilliant year in terms of growth, which is driving our rapid expansion into all corners of the new data centre. We pride ourselves on our stable, predictable growth trajectory, which is how we maintain our rock-solid reliability for clients around the world.

2022 also saw unprecedented changes in the global energy market, resulting in a noteworthy upswing in wholesale rates. This has been felt across both domestic and commercial sectors of the market, and has certainly been the most difficult aspect of the year to deal with. The future is still uncertain, however we are seeing positive indicators in the wholesale market which point towards more stability in 2023, which we’re very much hopeful for.

We’re looking ahead to a very exciting year in 2023, as we continue to develop NLE (with be the deployment of Data Halls 2, 3 and 4), and even begin exploring options for campus-level lateral expansion to maintain our ever-important growth ambitions.

Pod 1
We look forward to sharing more exciting news with you as we head into 2023.

London East Phase 2 Development Update 1

We’re now a little way into Phase 2 of development here at our London East data centre, with good progress made across a number of areas throughout the facility since our last update.

The deployment of Pod 2 in Data Hall 1 is well underway, with all racks now positioned and bayed, and with the first tenants in the space already deploying live kit. The complete containment system is now being installed, which will bring the capacity expansion project within Data Hall 1 to a close.

Beyond this, further work has been undertaken as part of the Data Hall 2 expansion project, as we prepare for that space to take initial occupancy in the early stages of 2023.

Aside to the data halls, we’ve also seen developments elsewhere, such as the onlining of our new lift, the installation of our new gates and razor wire system to the rear compound fencing, our new Naturewall welcome screen in the speed gate entranceway, and additional development work undertaken on our customer portal.

The Build and Break Room has also seen notable advances towards its completion and full opening, which is something we’re very excited about. We’ll be continuing to keep this under wraps for the time being, and will publish a separate update about this once ready for use.

We’ll get straight to it with the photos:

Pod 2
We began to position racks into place for Pod 2 early to visualise the space, and also to accommodate incoming client systems
Pod 2
The first four racks in Pod 2 were positioned based on client requirement, followed by a further three as part of the same installation
Pod 2
Here we see what the complete back-to-back Pods in Data Hall 1 look like, complete with inter-pod cable ladder at both ends
Pod 2
The full cold aisle containment system is next to be built as part of Pod 2
Pod 2
The deployment of Pod 2 takes Data Hall 1 to maximum available capacity on rack space, giving us a good amount of headroom to grow into ahead of opening Data Hall 2 in 2023
Lift
Our personnel lift had to be delayed due to supply issues, so we’re very pleased to now have this in place (as are many of our customers!)
Lift
We opted for a glass sided shaft, and the lift has been colour-matched to the doors found throughout the data centre, to maintain our visual language throughout all areas of the facility
Lift
Here we see the lift as seen from the first floor atrium, where the platform will arrive for clients visiting Data Halls 1 and 2
Lift
This is the view from the top of the lift, looking out over our main atrium
Lift
The lift sits in the main inter-floor atrium of the building, just along from the speed gates, which visitors will pass through to the technical side of the facility – the speed gates have also had a gate hold function installed, to allow for the glass blades to be held open to assist with any incoming kit via this access route
Speedgates
The speed gate access area has had an upgrade, with a new welcome screen mounted to a Naturewall panel – we’re rolling out these acoustic Naturewall panels throughout the facility, in place of the greenwall accents found at London Central, so expect to see further updates on this as they’re installed
Speedgates
The Naturewall panels are made up of attractive timber slats, mounted to acoustically-treated felt boards, creating a beautiful and tactile cladding surface which wonderfully plays against the industrial metal finishes found throughout London East
Speedgates
We’re still developing our final welcome screen for the speed gate access area, so visitors over the coming few weeks will likely see this evolve with each passing visit
Rear
Here we see the newly installed razor wire to the rear of the building, along with post extensions and upgraded security gate – along with the usual auto-tracking PTZ cameras which encircle the external perimeter of all our facilities
Rear
A view looking in the other direction along the rear of our building, through the fire escape staircase which leads down from the upstairs data halls – the other security gate and tracking camera at the rear can be see here also
Pod 1
Here’s a view of inside Pod 1, which is an indication of exactly how Pod 2 will look on completion of its identical containment system
Pod 1
Here is the view across from Pod 2 towards the entrance to Data Hall 1 and Pod 1
Nespresso
We’ve upgraded to the new Nespresso coffee machine and pod system at London East – this machine will be available to clients in the new Build and Break Room very soon

Progress is expected to pick up as we head towards Christmas, with several weeks of additional activity planned for the back half of November, which will focus on continued work inside of Data Hall 1, along with further preparatory works as part of the Data Hall 2 onlining process.

We’ll also be rolling out some new features on our customer portal and back-end systems, with further news to follow in that regard when suitable.

Phase 2 of development begins at London East

In late August, works began full-force on Phase 2 of our London East data centre build project.

While we won’t be publishing a Build Blog to the same degree as Phase 1 – the forthcoming modular roll-out of additional capacity will be less technically involved (and perhaps interesting) than the front-loaded primary build – we are still going to document this process, and put out updates as things progress.

Phase 2 will predominantly focus on two areas of expansion at London East; the deployment of Pod 2 in Data Hall 1 for an immediate capacity boost, and the full deployment of Data Hall 2, for mid-term growth enablement.

This phase is less time-sensitive than the initial build, and will likely be a split development phase as works continue in other areas, including our Build and Break Room and our new personnel lift, both coming in October.


Updates

We’re now a couple of ‘split weeks’ into Phase 2, and have some initial visual updates to share with our readers.

Roof
The first major works as part of Phase 2 involved the addition of the roof extraction cowls over the top of what will become the cold corridor for Data Hall 2
Roof
This is the view from on top of the roof, with the seven extraction cowls nearest being the new additions for Data Hall 2, and the seven furthest away being the active service cowls for Data Hall 1
Roof
These cowls allow for exhaust air to be extracted to atmosphere, if not required for any recirculation purposes – our new roof fall-arrest system can be seen in the foreground here, installed this summer
Roof
The new cowls are an exact copy of those servicing active loads in Data Hall 1, allowing for the weatherproof venting of hot exhaust air
Materials
There are a lot of materials and components which go into each data hall – the duct sleeves seen here are for the eventual 28 intake louvres to be cut into the rear of the building for the forthcoming second data hall (of four in this building)
Shipment
The components to make up another three of our containment pods arrived to site this week, allowing for the deployment of another 84 racks across halls 1 and 2
Floor
We’ve also added a couple of other niceties to the facility as part of this phase – here we can see our custom engineered glass floor tiles, which we’re placing in strategic locations to show off the quality of our sub-floor fit-out
Floor
Here are another set of these tiles in the main stairway atrium, showing the large trefoil runs between LV rooms – these will all be lit in due course, to make this even more of a feature

We’re extremely pleased with developments so far, despite being early into Phase 2. It is a phase of work which is expected to take us into next year for full realisation, however it will complete in stages. For example, the deployment of Pod 2 in Data Hall 1 will come first, and will be a relatively fast process, as this simply requires the physical construction of the containment pod and the integration of some monitoring and operating systems. The supporting infrastructure is already in place, with no required additions at this stage.

The deployment of Data Hall 2 is a larger operation, as this still requires lots of work under the raised floor to make the space ready for power and connectivity.

We’ll be posting updates to this process as and when suitable progress is made.