London East Phase 2 Development Update 4

We’ve been reasonably quiet with the #BuildBlog of late, with focus squarely on the deployment of additional capacity at London East, leaving little room for deep dives into progress (unfortunately!).

But we’re now back with this latest instalment, as we begin tracking progress on Data Halls 3 and 4.

Looking back on our last instalment of the build blog, Data Hall 2 was still very much under construction. This space is now fully fitted out as a private data hall for a single client, and is now under occupancy.

We’ve also got plenty of other updates to report across a range of areas within our London East facility, thanks to an ongoing development programme which extends beyond footprint capacity alone.

Let’s move onto the update photos. This first set were actually taken back in June, however the next instalment of the build blog ended up getting significantly delayed, so here they are:

This was the view across Pod 1 in Data Hall 2, as of June 2024
This was the view across Pod 1 in Data Hall 2, as of June 2024
The view across the Pod 2 footprint area, again in June
The view across Pod 2, again in June 2024
This is the B-side ODF in Data Hall 2 being pre-staged in the summer
This is the A-side ODF in Data Hall 2 being pre-staged in the summer
ODF
The view across to ODF B, as works continued in Data Hall 2 this summer
ODF
The checker plate bash protection was also fitted to the perimeter of Data Hall 2 around this time – this is the view of ODF A being pre-staged
ODF
Pre-staging the ODF enclosures allows for a speedier fit-out once the cabling process begins
ODF
Some of the control system cabling is being run overhead here
ODF
A view across Data Hall 2 as pre-containment works conclude
UPS
This view of LV Room B shows another UPS being rolled into place, ready to support Data Hall 3 in the near future
ODF
Here we see the A-side ODF in Data Hall 2 with some initial flood cabling underway, prior to termination – these are management cables, responsible for things like monitoring systems and CCTV
CREC HMI
This is the internal view of a CREC control system unit, with the front cover and control screen removed, as internal terminations conclude ahead of commissioning
General
Data Hall 2 just prior to having the racks and containment rolled in for assembly
DH2
We jump forwards slightly here, to a view across the now assembled Pods 1 and 2 in Data Hall 2 – this is taken from the rear of the hall, showing the custom layout for this client (the reasons for which will become clear further down in this post)

Now we can catch up in time to where things stand today, with the next run of photos from the past couple of weeks – apologies for any gaps in progress, we’ve been very busy!

DH2
Here we see Pod 1 inside of Data Hall 2, which is now handling live services
DH2
This is a custom, installed-to-request workbench area for the private tenant of Data Hall 2, which sits behind the shortened Pod 2
DH2
Having access to your own private data hall allows for additional deployment options, such as these storage cabinets for spare components
DH2
This view across to Pod 2 in Data Hall 2 shows the inter-pod cable ladder in place, which is now handling active connections for this tenant
DH2
This is a view of both live pods in Data Hall 2, ahead of some final finishing touches, such as the pod door vinyls and some custom lighting options as selected by the client
DH1
Here we see the rear of Row D in Data Hall 1 – the next wave of racks will be deployed as part of Data Halls 3 and 4 in Q1 2024; we now have very limited availability, so get in touch early if you need assistance with space
General
The ground floor is in full development mode, as general non-essential access is now closed
Cabling
As part of the next phase of development, works are now well underway for bringing Data Hall 4 online, with 3 to follow shortly thereafter – here we see one of the many cable drums in Data Hall 4, as it is prepared for installation
Cabling
The ground floor arterial corridor for power cabling is now being filled with the critical power routes required for the next two halls at London East
Cabling
These routes support diverse critical power runs for rack PDUs, as well as supporting power for mechanical systems
Cabling
This is a cable entry aperture into Data Hall 4, which has been skinned to allow for easy fire sealing once all cabling has been finalised
CRECs
Here are the CRECs in place for Data Hall 4, including all of the custom containment and blanking for the additional unit positions, matching the design for Halls 1 and 2
CRECs
The rear-facing air intake louvres have been cut in for both Halls 3 and 4, ahead of system commissioning in due course
UPS
Having additional UPS systems in pre-staging will speed along the deployment time for Halls 3 and 4
UPS
This view inside of LV Room A shows one of the newly arrived UPS systems undergoing some staging works, with internal access granted via removal of a side panel
Exterior
We’ve also undertaken a round of improvement works in the front compound – we now have on-site EV charging via our fast-charger, which will be available for use very soon
Exterior-
We’ve also now marked out parking bays, and installed some Armco to better guide client movements in the front compound, and to protect the sliding vehicle gate more comprehensively
Loading Bay
Our loading bay has had some storage upgrades, including this full-height pallet racking wall, which has been loaded up with components to form part of our future expansion phases
PDUs
We’ve developed a custom storage solution for our APC PDUs, with some of our on-site stock shown here making use of this new hanging system
Roof
We now have direct internal roof access, via this custom hatch, which has a detachable ladder system, for easy and quick personnel access to the roof for inspection of our hot air escape routes

Recycling
Each floor now has a dedicated waste handling area, allowing clients to dispose of both general waste and recyclables with greater ease
Dyson
All toilets within the facility now have Dyson hand dryers, something we have carried across from our London Central facility – these are on backlit standoffs for an added luxury finish
Check In
Our custom check in system has now been live across both of our facilities for a little while, with the introduction of our new QR code system – this has been performing well for clients, representing a massive improvement over the previous system
Reception
Our reception area now has the same Naturewall cladding as our Build and Break Area, and as found in some other common areas, to continue through this visual motif
Reception
This also effectively boxes in some major cabling routes, which is always welcomed over having such things on display in reception

As you can see, despite the delay in getting this build blog instalment posted, we’ve been rather busy.

We’ll continue to get our head down with development work on the run up to the new year, as demand for our services remains exceptionally high. We hope to have another update prepared for our avid readers in the next couple of months.

We also have some further news on the horizon with regards to continued expansion, which we hope to be releasing early next year. Needless to say, we’re very excited for what 2024 will bring.

London East Phase 2 Development Update 3

Progress continues with Phase 2 development works at Netwise London East (NLE), as we head into the warmer summer months.

Data Hall 2 is approaching completion, which will be another fantastic milestone to reach in the total development journey of our newest facility. There have been solid advancements made in all aspects of the Data Hall 2 roll-out, with the most notable being the progress made on power and cooling infrastructure.

As before, we’ll keep things brief, and move straight onto the progress shots:

Containment
Here we see the underfloor electrical containment starting in Data Hall 2
Containment
The island area seen in the centre here is the eventual position of Pod 1 within this space
Containment
The containment provides direct pathways to every possible rack footprint within a data hall, and provides safe routes for all other supporting infrastructure cabling
Containment
Seeing the containment routes come together is always a pleasing visual change in the sub-floor area of each hall
Cabing
As with Data Hall 1, the underfloor power for racks in this space is deployed using several kilometres of cabling, to mounted underfloor commando sockets
Cabing
Great care is taken to ensure that A and B power feeds to each client rack do not cross over, only meeting at the point of use / rack
Cabing
Here we see some of the immaculately laid cabling for the A-side feeds reaching Pod 2
Cabing
Each cable runs between a given rack position and the relevant power distribution board for that side of the power delivery system
Cabing
Here we see the commando sockets at the point of termination, along with the earth bonding flowing in behind, for the racks and for the raised floor system itself
Cabing
The cable runs here ensure no cross-over between A and B feeds on the under-rack containment, which is now more visible at this stage of the installation
Cabing
As always, we’re absolute sticklers for quality and detail, even when it will rarely / never be seen
Cabing
The mains ring which spans the underfloor area and supplies our cleaners sockets is now also in place
Cabing
The cable drums for this part of the build are certainly smaller than those required for the LV room fitouts in Phase 1, but these still clock in at around 400kg per drum
General
Aside to underfloor cabling, the remaining bulk of the termination work is found in each of the four PDUs, and the dual-fed mechanical boards – all finished in striking orange
Cabing
The distribution boards have by far the highest concentration of terminations to be undertaken
Cabing
The in-board terminations are just as carefully handled as everywhere else – a work of art
Cabing
This is one of four power distribution boards in Data Hall 2
Cooling
The cold corridor area of Data Hall 2 has also continued to develop, as the evaporative system is now plumbed in for supply, and has its drainage in place, ready for commissioning
Cooling
The hot air exhaust plenum is ready for the commissioning of the extract fans in due course
Work Room
The first floor store room has been acting as our development side office, providing a space for site meetings, plans, and all other items necessary for a project on this scale to move ahead successfully

Further to the visual updates above, the supplementary / backup air conditioning system is also nearing the point of commissioning, with the pipework installation underway, following the same routes as with the system for Data Hall 1.

Once Data Hall 2 is livened up in terms of the power delivery system(s), the full commissioning works for the primary and secondary cooling systems can begin, which will bring the room to the point of safe occupancy (pending the fitout of the containment Pods, of course!).

We’ve been extremely pleased with progress on-site in the last few weeks. One thing that continues to shine through above all else is the quality of the work, which is something we and our clients alike have come to expect from a Netwise data centre. Every detail is carefully considered, resulting in a truly remarkable facility that we can be proud of for many years to come.

Working Phase 2 around an already active data centre has added additional challenges, not felt during Phase 1 (whereby the site was unoccupied by client deployments). While none of the works undertaken as part of Phase 2 pose any risk to live client services, there are many considerations to bear for enabling continued client access while many areas of the facility are being actively worked on.

London East Phase 2 Development Update 2

We’ve been making steady progress on Phase 2 of our deployment plan at Netwise London East (NLE). This includes the total completion of Pod 2 in Data Hall 1, and large strides towards the onlining of Data Hall 2 in the coming months. This will be followed shortly thereafter with the base infrastructure deployment for Data Halls 3 and 4 later in the year.

We’ve been moving ahead firmly across various areas of general infrastructure, electrical and cooling systems for Data Hall 2, with the primary evaporative cooling system now in place ahead of commissioning. The feeder connections from the LV rooms to the in-hall distribution boards are now also in place, ahead of the main electrical works for the diverse rack feeds beginning in the coming weeks.

We’ll keep things brief this time around, so let’s get straight to the update photos:

Cabling
Here we have some of the additional cabling required to bring the next phase online at NLE
Cabling
Each of our data halls require a significant quantity of cabling to link them back to our diverse LV rooms
Cabling
We’ve certainly worked our way through a healthy number of large cable drums at this stage
Cabling
Pulling in these large armoured cables between floors can certainly be a challenge for the teams involved in this work
Cabling
With the main power cabling route handled under the raised floor at NLE, certain areas are cordoned off while works are underway, however disruption is generally kept to no more than a couple of hours at a time, per area
Cabling
These cable routes are already populated with live service power, as Data Hall 1 is fed via the same risers – here we see some new cabling ahead of being tied and cleated
Cabling
The longer of the two routes for the DH2 power delivery is from LV A – here we see the longer run with some of the cabling loose laid into the underfloor ladder
Cabling
The cabling routes flow down the risers to the diverse LV rooms, once they leave the main corridor(s)
Cabling
Considered placement of the large cable drums is vital in ensuring a smooth run-off of the cabling into the raised floor area – the same can be said for the cable rollers
Cabling
Drum placement must consider disruption, ease of access, and result in the least possible amount of free tail once the cable is fully released
DH2
Data Hall 2 has a range of components ready for installation, including some of the distribution boards, and the custom-made ODFs
Cooling
The primary cooling system for DH2 is now in place, that being our evaporative system which famously delivers our world-leading PUE figures
Cooling
As with DH1, we have space for seven CREC units, however we have deployed four initially – it is not expected that additional coolers will be needed, however installing them later would be a straightforward addition
Cooling
The cold corridor filtration system and overhead extraction loop are now complete for DH2 – this is taken ahead of the lights being installed, hence the low light conditions and temporary insulation panels
Pod 2
Pod 2 now has a range of active client deployments within it – in fact, Row C is now almost entirely accounted for
Pod 2
Pod 2 now also completes the full in-hall ODF to ODF pathway using the overhead ladder and trough system
Pod 2
Here’s a view of the back end of Data Hall 1, with both rear Pod entry door systems in view, and the CREC system for this room
Pod 2
This is the view inside Pod 2, as viewed from the rear entry doors
BuildRoom
Our Build and Break Room is now fully fitted out, and sees great use already by our clients
BuildRoom
The function of this one space is split at our London Central facility, which makes use more tricky, so we decided to consolidate amenities at London East for an improved visitor experience
BuildRoom
The wall features continue here, to tie in with other areas of the facility
BuildRoom
We’re particularly proud of our customer kitchen here, which has been expertly installed by our in-house facilities team, to the highest specification
BuildRoom
Be sure to check out the Build and Break Room on your next visit

We now have a dedicated roof hatch system installed over the storage mezzanine, for easier, direct access to the roof, which is important for speedy access to our heat extraction loop. We’ll update readers with photos of this area next time around.

We’re expecting to see a dramatic uptick in progress on Data Hall 2 in the next few weeks, as we head towards the peak activity period which will enable occupation of the space. This will also provide some additional visual change to enable a more in-depth update, which is something which has been lacking since the completion of Phase 1 – we apologise to our regular Build Blog readers for this!

London East Phase 2 Development Update 1

We’re now a little way into Phase 2 of development here at our London East data centre, with good progress made across a number of areas throughout the facility since our last update.

The deployment of Pod 2 in Data Hall 1 is well underway, with all racks now positioned and bayed, and with the first tenants in the space already deploying live kit. The complete containment system is now being installed, which will bring the capacity expansion project within Data Hall 1 to a close.

Beyond this, further work has been undertaken as part of the Data Hall 2 expansion project, as we prepare for that space to take initial occupancy in the early stages of 2023.

Aside to the data halls, we’ve also seen developments elsewhere, such as the onlining of our new lift, the installation of our new gates and razor wire system to the rear compound fencing, our new Naturewall welcome screen in the speed gate entranceway, and additional development work undertaken on our customer portal.

The Build and Break Room has also seen notable advances towards its completion and full opening, which is something we’re very excited about. We’ll be continuing to keep this under wraps for the time being, and will publish a separate update about this once ready for use.

We’ll get straight to it with the photos:

Pod 2
We began to position racks into place for Pod 2 early to visualise the space, and also to accommodate incoming client systems
Pod 2
The first four racks in Pod 2 were positioned based on client requirement, followed by a further three as part of the same installation
Pod 2
Here we see what the complete back-to-back Pods in Data Hall 1 look like, complete with inter-pod cable ladder at both ends
Pod 2
The full cold aisle containment system is next to be built as part of Pod 2
Pod 2
The deployment of Pod 2 takes Data Hall 1 to maximum available capacity on rack space, giving us a good amount of headroom to grow into ahead of opening Data Hall 2 in 2023
Lift
Our personnel lift had to be delayed due to supply issues, so we’re very pleased to now have this in place (as are many of our customers!)
Lift
We opted for a glass sided shaft, and the lift has been colour-matched to the doors found throughout the data centre, to maintain our visual language throughout all areas of the facility
Lift
Here we see the lift as seen from the first floor atrium, where the platform will arrive for clients visiting Data Halls 1 and 2
Lift
This is the view from the top of the lift, looking out over our main atrium
Lift
The lift sits in the main inter-floor atrium of the building, just along from the speed gates, which visitors will pass through to the technical side of the facility – the speed gates have also had a gate hold function installed, to allow for the glass blades to be held open to assist with any incoming kit via this access route
Speedgates
The speed gate access area has had an upgrade, with a new welcome screen mounted to a Naturewall panel – we’re rolling out these acoustic Naturewall panels throughout the facility, in place of the greenwall accents found at London Central, so expect to see further updates on this as they’re installed
Speedgates
The Naturewall panels are made up of attractive timber slats, mounted to acoustically-treated felt boards, creating a beautiful and tactile cladding surface which wonderfully plays against the industrial metal finishes found throughout London East
Speedgates
We’re still developing our final welcome screen for the speed gate access area, so visitors over the coming few weeks will likely see this evolve with each passing visit
Rear
Here we see the newly installed razor wire to the rear of the building, along with post extensions and upgraded security gate – along with the usual auto-tracking PTZ cameras which encircle the external perimeter of all our facilities
Rear
A view looking in the other direction along the rear of our building, through the fire escape staircase which leads down from the upstairs data halls – the other security gate and tracking camera at the rear can be see here also
Pod 1
Here’s a view of inside Pod 1, which is an indication of exactly how Pod 2 will look on completion of its identical containment system
Pod 1
Here is the view across from Pod 2 towards the entrance to Data Hall 1 and Pod 1
Nespresso
We’ve upgraded to the new Nespresso coffee machine and pod system at London East – this machine will be available to clients in the new Build and Break Room very soon

Progress is expected to pick up as we head towards Christmas, with several weeks of additional activity planned for the back half of November, which will focus on continued work inside of Data Hall 1, along with further preparatory works as part of the Data Hall 2 onlining process.

We’ll also be rolling out some new features on our customer portal and back-end systems, with further news to follow in that regard when suitable.

Phase 2 of development begins at London East

In late August, works began full-force on Phase 2 of our London East data centre build project.

While we won’t be publishing a Build Blog to the same degree as Phase 1 – the forthcoming modular roll-out of additional capacity will be less technically involved (and perhaps interesting) than the front-loaded primary build – we are still going to document this process, and put out updates as things progress.

Phase 2 will predominantly focus on two areas of expansion at London East; the deployment of Pod 2 in Data Hall 1 for an immediate capacity boost, and the full deployment of Data Hall 2, for mid-term growth enablement.

This phase is less time-sensitive than the initial build, and will likely be a split development phase as works continue in other areas, including our Build and Break Room and our new personnel lift, both coming in October.


Updates

We’re now a couple of ‘split weeks’ into Phase 2, and have some initial visual updates to share with our readers.

Roof
The first major works as part of Phase 2 involved the addition of the roof extraction cowls over the top of what will become the cold corridor for Data Hall 2
Roof
This is the view from on top of the roof, with the seven extraction cowls nearest being the new additions for Data Hall 2, and the seven furthest away being the active service cowls for Data Hall 1
Roof
These cowls allow for exhaust air to be extracted to atmosphere, if not required for any recirculation purposes – our new roof fall-arrest system can be seen in the foreground here, installed this summer
Roof
The new cowls are an exact copy of those servicing active loads in Data Hall 1, allowing for the weatherproof venting of hot exhaust air
Materials
There are a lot of materials and components which go into each data hall – the duct sleeves seen here are for the eventual 28 intake louvres to be cut into the rear of the building for the forthcoming second data hall (of four in this building)
Shipment
The components to make up another three of our containment pods arrived to site this week, allowing for the deployment of another 84 racks across halls 1 and 2
Floor
We’ve also added a couple of other niceties to the facility as part of this phase – here we can see our custom engineered glass floor tiles, which we’re placing in strategic locations to show off the quality of our sub-floor fit-out
Floor
Here are another set of these tiles in the main stairway atrium, showing the large trefoil runs between LV rooms – these will all be lit in due course, to make this even more of a feature

We’re extremely pleased with developments so far, despite being early into Phase 2. It is a phase of work which is expected to take us into next year for full realisation, however it will complete in stages. For example, the deployment of Pod 2 in Data Hall 1 will come first, and will be a relatively fast process, as this simply requires the physical construction of the containment pod and the integration of some monitoring and operating systems. The supporting infrastructure is already in place, with no required additions at this stage.

The deployment of Data Hall 2 is a larger operation, as this still requires lots of work under the raised floor to make the space ready for power and connectivity.

We’ll be posting updates to this process as and when suitable progress is made.