London East Phase 2 Development Update 4

We’ve been reasonably quiet with the #BuildBlog of late, with focus squarely on the deployment of additional capacity at London East, leaving little room for deep dives into progress (unfortunately!).

But we’re now back with this latest instalment, as we begin tracking progress on Data Halls 3 and 4.

Looking back on our last instalment of the build blog, Data Hall 2 was still very much under construction. This space is now fully fitted out as a private data hall for a single client, and is now under occupancy.

We’ve also got plenty of other updates to report across a range of areas within our London East facility, thanks to an ongoing development programme which extends beyond footprint capacity alone.

Let’s move onto the update photos. This first set were actually taken back in June, however the next instalment of the build blog ended up getting significantly delayed, so here they are:

This was the view across Pod 1 in Data Hall 2, as of June 2024
This was the view across Pod 1 in Data Hall 2, as of June 2024
The view across the Pod 2 footprint area, again in June
The view across Pod 2, again in June 2024
This is the B-side ODF in Data Hall 2 being pre-staged in the summer
This is the A-side ODF in Data Hall 2 being pre-staged in the summer
ODF
The view across to ODF B, as works continued in Data Hall 2 this summer
ODF
The checker plate bash protection was also fitted to the perimeter of Data Hall 2 around this time – this is the view of ODF A being pre-staged
ODF
Pre-staging the ODF enclosures allows for a speedier fit-out once the cabling process begins
ODF
Some of the control system cabling is being run overhead here
ODF
A view across Data Hall 2 as pre-containment works conclude
UPS
This view of LV Room B shows another UPS being rolled into place, ready to support Data Hall 3 in the near future
ODF
Here we see the A-side ODF in Data Hall 2 with some initial flood cabling underway, prior to termination – these are management cables, responsible for things like monitoring systems and CCTV
CREC HMI
This is the internal view of a CREC control system unit, with the front cover and control screen removed, as internal terminations conclude ahead of commissioning
General
Data Hall 2 just prior to having the racks and containment rolled in for assembly
DH2
We jump forwards slightly here, to a view across the now assembled Pods 1 and 2 in Data Hall 2 – this is taken from the rear of the hall, showing the custom layout for this client (the reasons for which will become clear further down in this post)

Now we can catch up in time to where things stand today, with the next run of photos from the past couple of weeks – apologies for any gaps in progress, we’ve been very busy!

DH2
Here we see Pod 1 inside of Data Hall 2, which is now handling live services
DH2
This is a custom, installed-to-request workbench area for the private tenant of Data Hall 2, which sits behind the shortened Pod 2
DH2
Having access to your own private data hall allows for additional deployment options, such as these storage cabinets for spare components
DH2
This view across to Pod 2 in Data Hall 2 shows the inter-pod cable ladder in place, which is now handling active connections for this tenant
DH2
This is a view of both live pods in Data Hall 2, ahead of some final finishing touches, such as the pod door vinyls and some custom lighting options as selected by the client
DH1
Here we see the rear of Row D in Data Hall 1 – the next wave of racks will be deployed as part of Data Halls 3 and 4 in Q1 2024; we now have very limited availability, so get in touch early if you need assistance with space
General
The ground floor is in full development mode, as general non-essential access is now closed
Cabling
As part of the next phase of development, works are now well underway for bringing Data Hall 4 online, with 3 to follow shortly thereafter – here we see one of the many cable drums in Data Hall 4, as it is prepared for installation
Cabling
The ground floor arterial corridor for power cabling is now being filled with the critical power routes required for the next two halls at London East
Cabling
These routes support diverse critical power runs for rack PDUs, as well as supporting power for mechanical systems
Cabling
This is a cable entry aperture into Data Hall 4, which has been skinned to allow for easy fire sealing once all cabling has been finalised
CRECs
Here are the CRECs in place for Data Hall 4, including all of the custom containment and blanking for the additional unit positions, matching the design for Halls 1 and 2
CRECs
The rear-facing air intake louvres have been cut in for both Halls 3 and 4, ahead of system commissioning in due course
UPS
Having additional UPS systems in pre-staging will speed along the deployment time for Halls 3 and 4
UPS
This view inside of LV Room A shows one of the newly arrived UPS systems undergoing some staging works, with internal access granted via removal of a side panel
Exterior
We’ve also undertaken a round of improvement works in the front compound – we now have on-site EV charging via our fast-charger, which will be available for use very soon
Exterior-
We’ve also now marked out parking bays, and installed some Armco to better guide client movements in the front compound, and to protect the sliding vehicle gate more comprehensively
Loading Bay
Our loading bay has had some storage upgrades, including this full-height pallet racking wall, which has been loaded up with components to form part of our future expansion phases
PDUs
We’ve developed a custom storage solution for our APC PDUs, with some of our on-site stock shown here making use of this new hanging system
Roof
We now have direct internal roof access, via this custom hatch, which has a detachable ladder system, for easy and quick personnel access to the roof for inspection of our hot air escape routes

Recycling
Each floor now has a dedicated waste handling area, allowing clients to dispose of both general waste and recyclables with greater ease
Dyson
All toilets within the facility now have Dyson hand dryers, something we have carried across from our London Central facility – these are on backlit standoffs for an added luxury finish
Check In
Our custom check in system has now been live across both of our facilities for a little while, with the introduction of our new QR code system – this has been performing well for clients, representing a massive improvement over the previous system
Reception
Our reception area now has the same Naturewall cladding as our Build and Break Area, and as found in some other common areas, to continue through this visual motif
Reception
This also effectively boxes in some major cabling routes, which is always welcomed over having such things on display in reception

As you can see, despite the delay in getting this build blog instalment posted, we’ve been rather busy.

We’ll continue to get our head down with development work on the run up to the new year, as demand for our services remains exceptionally high. We hope to have another update prepared for our avid readers in the next couple of months.

We also have some further news on the horizon with regards to continued expansion, which we hope to be releasing early next year. Needless to say, we’re very excited for what 2024 will bring.

Netwise sponsors South Berkshire Hockey Club

We’re very excited to announce our position as the main shirt sponsor for the South Berkshire Hockey Club this year, as the new season begins in earnest.

It’s already been a competitive start to the year on pitch, with some solid results posted in just the first month of action; the Ladies’ 1st team is now already sitting in the top half of the league, having been promoted to the South Central Women’s Premier Division 2.

The Ladies’ 1st Team

The Men’s 1st team has had a slightly more difficult start to the season. The opening schedule has not been quite so kind to them and to date it’s been three competitive but fruitless games. However this is expected to put them in extremely good stead for their next set of fixtures, at which point the team is anticipating traction for the rest of the season.

The Men’s 1st Team

Our support of the SBHC has enabled an additional weekly Monday night training session, allowing their performance teams to push on in their new leagues, while keeping costs accessible to players in what has traditionally been known as an expensive/classist sport.

The Men’s 1st Team

Our Technical Manager, Nathan, is a long-standing member of the SBHC, which makes supporting them this year even more special for Netwise.

The club is renowned for its unwavering dedication to the sport, its inclusivity, and its exceptional track record in nurturing both youth and senior teams.

This new union between the South Berkshire Hockey Club and Netwise is a testament to our shared values and common goals, such as supporting local talent, enhancing community spirit, and aiming for success in everything we do, making for a perfectly aligned partnership.

Some of the Men’s 1st Team in action

With Netwise’s support, the South Berkshire Hockey Club is poised for a remarkable season. We are dedicated to upholding the club’s time-honored values of teamwork, sportsmanship, and dedication, and we very much look forward to sharing in their successes.

London East Phase 2 Development Update 3

Progress continues with Phase 2 development works at Netwise London East (NLE), as we head into the warmer summer months.

Data Hall 2 is approaching completion, which will be another fantastic milestone to reach in the total development journey of our newest facility. There have been solid advancements made in all aspects of the Data Hall 2 roll-out, with the most notable being the progress made on power and cooling infrastructure.

As before, we’ll keep things brief, and move straight onto the progress shots:

Containment
Here we see the underfloor electrical containment starting in Data Hall 2
Containment
The island area seen in the centre here is the eventual position of Pod 1 within this space
Containment
The containment provides direct pathways to every possible rack footprint within a data hall, and provides safe routes for all other supporting infrastructure cabling
Containment
Seeing the containment routes come together is always a pleasing visual change in the sub-floor area of each hall
Cabing
As with Data Hall 1, the underfloor power for racks in this space is deployed using several kilometres of cabling, to mounted underfloor commando sockets
Cabing
Great care is taken to ensure that A and B power feeds to each client rack do not cross over, only meeting at the point of use / rack
Cabing
Here we see some of the immaculately laid cabling for the A-side feeds reaching Pod 2
Cabing
Each cable runs between a given rack position and the relevant power distribution board for that side of the power delivery system
Cabing
Here we see the commando sockets at the point of termination, along with the earth bonding flowing in behind, for the racks and for the raised floor system itself
Cabing
The cable runs here ensure no cross-over between A and B feeds on the under-rack containment, which is now more visible at this stage of the installation
Cabing
As always, we’re absolute sticklers for quality and detail, even when it will rarely / never be seen
Cabing
The mains ring which spans the underfloor area and supplies our cleaners sockets is now also in place
Cabing
The cable drums for this part of the build are certainly smaller than those required for the LV room fitouts in Phase 1, but these still clock in at around 400kg per drum
General
Aside to underfloor cabling, the remaining bulk of the termination work is found in each of the four PDUs, and the dual-fed mechanical boards – all finished in striking orange
Cabing
The distribution boards have by far the highest concentration of terminations to be undertaken
Cabing
The in-board terminations are just as carefully handled as everywhere else – a work of art
Cabing
This is one of four power distribution boards in Data Hall 2
Cooling
The cold corridor area of Data Hall 2 has also continued to develop, as the evaporative system is now plumbed in for supply, and has its drainage in place, ready for commissioning
Cooling
The hot air exhaust plenum is ready for the commissioning of the extract fans in due course
Work Room
The first floor store room has been acting as our development side office, providing a space for site meetings, plans, and all other items necessary for a project on this scale to move ahead successfully

Further to the visual updates above, the supplementary / backup air conditioning system is also nearing the point of commissioning, with the pipework installation underway, following the same routes as with the system for Data Hall 1.

Once Data Hall 2 is livened up in terms of the power delivery system(s), the full commissioning works for the primary and secondary cooling systems can begin, which will bring the room to the point of safe occupancy (pending the fitout of the containment Pods, of course!).

We’ve been extremely pleased with progress on-site in the last few weeks. One thing that continues to shine through above all else is the quality of the work, which is something we and our clients alike have come to expect from a Netwise data centre. Every detail is carefully considered, resulting in a truly remarkable facility that we can be proud of for many years to come.

Working Phase 2 around an already active data centre has added additional challenges, not felt during Phase 1 (whereby the site was unoccupied by client deployments). While none of the works undertaken as part of Phase 2 pose any risk to live client services, there are many considerations to bear for enabling continued client access while many areas of the facility are being actively worked on.

London East Phase 2 Development Update 2

We’ve been making steady progress on Phase 2 of our deployment plan at Netwise London East (NLE). This includes the total completion of Pod 2 in Data Hall 1, and large strides towards the onlining of Data Hall 2 in the coming months. This will be followed shortly thereafter with the base infrastructure deployment for Data Halls 3 and 4 later in the year.

We’ve been moving ahead firmly across various areas of general infrastructure, electrical and cooling systems for Data Hall 2, with the primary evaporative cooling system now in place ahead of commissioning. The feeder connections from the LV rooms to the in-hall distribution boards are now also in place, ahead of the main electrical works for the diverse rack feeds beginning in the coming weeks.

We’ll keep things brief this time around, so let’s get straight to the update photos:

Cabling
Here we have some of the additional cabling required to bring the next phase online at NLE
Cabling
Each of our data halls require a significant quantity of cabling to link them back to our diverse LV rooms
Cabling
We’ve certainly worked our way through a healthy number of large cable drums at this stage
Cabling
Pulling in these large armoured cables between floors can certainly be a challenge for the teams involved in this work
Cabling
With the main power cabling route handled under the raised floor at NLE, certain areas are cordoned off while works are underway, however disruption is generally kept to no more than a couple of hours at a time, per area
Cabling
These cable routes are already populated with live service power, as Data Hall 1 is fed via the same risers – here we see some new cabling ahead of being tied and cleated
Cabling
The longer of the two routes for the DH2 power delivery is from LV A – here we see the longer run with some of the cabling loose laid into the underfloor ladder
Cabling
The cabling routes flow down the risers to the diverse LV rooms, once they leave the main corridor(s)
Cabling
Considered placement of the large cable drums is vital in ensuring a smooth run-off of the cabling into the raised floor area – the same can be said for the cable rollers
Cabling
Drum placement must consider disruption, ease of access, and result in the least possible amount of free tail once the cable is fully released
DH2
Data Hall 2 has a range of components ready for installation, including some of the distribution boards, and the custom-made ODFs
Cooling
The primary cooling system for DH2 is now in place, that being our evaporative system which famously delivers our world-leading PUE figures
Cooling
As with DH1, we have space for seven CREC units, however we have deployed four initially – it is not expected that additional coolers will be needed, however installing them later would be a straightforward addition
Cooling
The cold corridor filtration system and overhead extraction loop are now complete for DH2 – this is taken ahead of the lights being installed, hence the low light conditions and temporary insulation panels
Pod 2
Pod 2 now has a range of active client deployments within it – in fact, Row C is now almost entirely accounted for
Pod 2
Pod 2 now also completes the full in-hall ODF to ODF pathway using the overhead ladder and trough system
Pod 2
Here’s a view of the back end of Data Hall 1, with both rear Pod entry door systems in view, and the CREC system for this room
Pod 2
This is the view inside Pod 2, as viewed from the rear entry doors
BuildRoom
Our Build and Break Room is now fully fitted out, and sees great use already by our clients
BuildRoom
The function of this one space is split at our London Central facility, which makes use more tricky, so we decided to consolidate amenities at London East for an improved visitor experience
BuildRoom
The wall features continue here, to tie in with other areas of the facility
BuildRoom
We’re particularly proud of our customer kitchen here, which has been expertly installed by our in-house facilities team, to the highest specification
BuildRoom
Be sure to check out the Build and Break Room on your next visit

We now have a dedicated roof hatch system installed over the storage mezzanine, for easier, direct access to the roof, which is important for speedy access to our heat extraction loop. We’ll update readers with photos of this area next time around.

We’re expecting to see a dramatic uptick in progress on Data Hall 2 in the next few weeks, as we head towards the peak activity period which will enable occupation of the space. This will also provide some additional visual change to enable a more in-depth update, which is something which has been lacking since the completion of Phase 1 – we apologise to our regular Build Blog readers for this!

Sustainability in-focus: beating our design PUE figures for a second year running

We are very excited to announce that our London Central (NLC) facility has once again exceeded expectations in terms of energy efficiency. NLC’s design PUE (Power Usage Effectiveness) is an impressive 1.12, but the annualised real-world PUE for the last 12 months was a staggering 1.09 – an improvement over the already remarkable 1.11 achieved the year prior.

NLC is our facility in Bermondsey, London, which we opened in 2015

For those unfamiliar with the concept of PUE, it is a measure of how much energy a data centre uses for computing compared to how much energy it uses for supporting load, such as cooling, UPS losses, fire systems etc. The goal for data centres is to have the lowest possible PUE, as this indicates the highest level of energy efficiency.

Even just meeting our design PUE would be impressive for a London data centre, but to exceed this by such a significant margin is something we’re hugely proud of.

We have consistently demonstrated our commitment to sustainability and energy efficiency across all aspects of our operation. This latest achievement is a testament to our ongoing efforts to reduce our carbon footprint and promote sustainable practices in the industry.

A real-world PUE of 1.09 ranks among the lowest PUEs reported by data centres worldwide, indicating that the facility is operating with a high level of energy efficiency and with minimal energy waste.

We believe that data centres have a significant role to play in mitigating the impacts of climate change, and we are proud to be leading the way in this effort. Our innovative approach to energy management, combined with our state-of-the-art technology and cutting-edge infrastructure, has enabled us to achieve these outstanding results.

Furthermore, the design PUE of our latest data centre, Netwise London East (NLE), is just 1.05. Reaching a facility’s design PUE target does require a high level of capacity utilisation, which takes time following launch (though helped by our modular design and deployment philosophy), however we couldn’t be more excited to see where our real-world figures lands at NLE in the coming months and years.

NLE opened in 2022, in Canning Town, and is on-track to be one of the most efficient data centres in the world

We would like to take this opportunity to thank our team and our customers for their continued support. We remain committed to driving innovation and sustainability in the data centre industry and look forward to continuing to push the boundaries of what is possible.