London East Build Blog – Weeks 93 to 97

With the final utility connections now upon us, and the last elements of our stage one internal fit-out now reaching completion, we’re now tantalisingly close to welcoming our first clients into NLE.

A large portion of the facility has in fact been ready to receive client systems for some time now, however as is always the way with projects of this scale and complexity, a number of tasks did run into delays for various reasons as we headed into the back quarter of last year.


Weekly overview

As much as this is a five week update – one of the longest spanning periods to date on the NLE Build Blog – it is somewhat light in visual change, as we’ve been focusing most of our attention on systems integration. Naturally, this is an incredibly important and complex part of onlining any new data centre, however it does prove a tricky side of the project to relay visually.

Regardless, we do have some photo updates to relay this time around.

Monitoring
We’re now finalising some of the last monitoring and control system integrations, including the monitoring system seen here forming part of our supplementary cooling infrastructure in Data Hall 1
Network
Here we see one of the many MUXs we have across all of our POPs, which we now have branded for us
Network
Our core network has been building up to the point of full commissioning in layers, as various devices across the facility come online for the first time – here we see the first phase fibre layer landing in place on the B-side
Network
We have now fully deployed the internal network at London East, from core to edge
Network
This is the same across both the A and B sides of the core network and distribution network – there will of course be further internal connections made across this platform as the first client systems land on-site
ODF
The A and B ODFs in Data Hall 1 are now also fully online, supporting our own infrastructure requirements, and ready to handle cross-connects and transit for clients as they begin to deploy live systems
ODF
ODF B in Data Hall 1 is presently more busy than ODF A, as this is where a larger quantity of our own management links come back to, due to the positioning of this ODF within the room and wider building
Private Pod
The private pod we have ready for one of our clients is fully commissioned, including custom access control, and the now fully-trimmed security panel which segments this secure space for the client
Reception
We’ve begun the installation of the new security glass system in reception, which will place the on-duty guard in a segmented area, which also secures the route to the on-site NOC
Reception
The track system for the glass is being fitted here, which will house the large, custom-cut 10mm thick security glass
Reception
The system will be comprised of a large sheet with slim opening over the desk, and a large floor-to-ceiling door and glass infills to the side, with access control
Reception
Various supplementary signage and notices have also been distributed throughout the facility, including the custom fire zone map which sits alongside the main building alarm system
DH2
We’ve pre-emptively started rolling out some more infrastructure in Data Hall 2, which remains in a partially fitted out state – this is the Honeywell PSU and control interface as part of the monitoring / BMS for this space
HV
The final piece of the puzzle for our HV connection arrived on-site, and has now been pulled in and jointed – this is the largest diameter cable drum to arrive at NLE to date
HV
This is specialist HV cable for connecting into our transformer, and comes on the drum as a pre-cut triplex length to be pulled in as a single piece
HV
We had further civils underway as part of this final connection, which required a small amount of additional excavation in our demise, and another dig in the road nearby
HV
In addition, we have two other digs happening simultaneously in the nearby area as further services arrive to site ready for opening
LV
We’ve also completed a fully custom installation of Intelimonitor SCADA screens in each LV room, which show live status information on our generator system, which read from the sets and breakers in real-time
LV
Here’s a closer look at the SCADA screen in LV Room B – this is a custom mounted Surface Pro, running the custom software and screen output for our particular setup

Much of the work in this period has been happening in less visual areas, including the onlining of systems and bringing them into our centralised control and monitoring platforms. This has been an ongoing part of the commissioning process for some time now, and is nearing completion.

The facility is in a position to accept client systems on a pre-staging basis, with all internal power systems online.

As we head into the final month of Q1, we’re extremely excited to be as close as we are to full readiness. We’re expecting the first client systems to begin rolling into the facility in March, which will of course be the most major milestone of this project to date.


What’s next?

We are continuing with our extensive commissioning works, which span all areas of the facility and its various systems.

All the while this is happening, the final elements relating to our core utilities are being finalised, which will bring phase one of our build to a conclusive state. There will be a certain amount of post-onlining works, which could be dubbed ‘phase one-point-five’, ahead of the later technical space expansion into Data Hall 2, which will be phase two.

We even have some early interest in our ground floor data halls for singular client project use, so it could be that plans for internal expansion are indeed brought forwards, depending on how these things come together in the coming months.

London East Build Blog – Weeks 87 to 92

We’ve had a busy start to the year as final stage works continue, taking us towards close-out on phase one at London East.

Our core team got to enjoy some much-deserved time off over the holiday season, ready for action as usual in the new year – one which is set to hold a wide range of milestones for Netwise.


Weekly overview

We’ll get straight to it with the photos this time, as we’ve got lots of changes to show our readers, which have materialised in both the run up to and exit from the holiday season.

General
We added a nice wide angle lens to our photography arsenal over Christmas, which will help us properly capture the scale of our new facility
General
Here we see Data Hall 1 in its completed state, ready to receive customer deployments in due course – Phase 1 will see the onlining of Pod 1, with the position for Pod 2 (assuming the standard full-length application) seen in the foreground
General
A look across Data Hall 1 to Pod 1, containing Row A and Row B
General
Our new wide angle lens helps us get in close to areas that would otherwise be difficult to properly show on-screen
General
This end of the first pod, seen held open while final work is undertaken, will be a private entrance for a client who has elected to take segregated space
General
The stylised vision panel privacy etching has now also been applied to Data Halls 3 and 4, until the rooms go live
General
A more visible view of these on the doors to Data Hall 3, which will be removed when the room goes live
Core
The staging of our own resilient core is now well underway, with all hardware in position, and cabling now approaching completion (more visibility on this next time)
Core
We’re now also able to begin fully integrating the new site, as systems come online and mix with our live operation
Core
The core racks again follow our colour coding from London Central, with the A-side being yellow, and the B-side being blue
Core
The core racks now also have customised overhead troughs to enable easier and safer cable routing between the rack and ODF
Reception
Our reception is really taking shape now, with our custom reception / security desk now in place, ahead of the glass enclosure installation coming soon – the site is already manned 24×7 in preparation for launch
Ramp
Our new brushed welcome sign is now in place at the main customer entry way, leading to the data halls and technical spaces
Ramp
This sign follows the same design as the NOC signage we have at both of our data centres
Noc
The NOC screens at London East are now online, and pending final completion in terms of display configuration
LV
The LV rooms now each contain folders documenting the LV designs, for easy engineer access, and are soon to be fitted with additional smart screens for generator status readouts, in addition to the already very detailed ComAp controllers – you can also see one of the first aid kits located here, which have now been fitted throughout the facility
LV
Our new wide angle lens has allowed us to capture the scale of our main switchgear more completely, with the full seven metre span visible here in LV Room B
LV
The same full-view of the board in LV Room A
LV
The view across to the UPS and distribution in LV Room A
Noc
Our small acoustic rack in the NOC, which handles local NOC communications, has now been cabled in its final configuration
Loadbank
One of the major tasks undertaken on our arrival back after Christmas was the final load bank test of our newly deployed backup generator system
Loadbank
This load bank test enabled our generator engineers to run the system up to significant levels during the configuration stage, to simulate the building load as it will be once client deployments begin landing on-site
Loadbank
We were able to simulate a load of 780kW across the whole system, before running generator each up to around 500kW to soak test on a per set level
Loadbank
Having use of this unit for the week of commissioning ensures that our backup power systems have been tested sufficiently up to suitable load figures, which is not possible using building load at this point in time
Loadbank
With the unit running, a large amount of heat is produced (top exit), which is how the energy requirement is created
Fire
This is a view of the fire control and extinguishant panel outside of LV Room B, which shows the custom badges we’ve had made for these units throughout the building – details, details, details!
Metering
Here we see pre-staging for our in-house assembly line for producing the circuit monitors, which will sit under each live client rack, and enable power metering which is PDU-agnostic

It’s an exciting time, as we begin to see many aspects of the new site ‘go live’ for the first time. Aside from some final elements due to close off in the coming few weeks, the site is now essentially service-ready, with some early deployment options for particular clients taking shape.

One system that we’ve been excited to see take shape is our new fully-integrated CCTV and access control platform. While we still have our long-retention continuous recording setup on all cameras, we now also have AI-driven motion tracking and sensing, which means that our system is able to follow visitors around the site automatically, generating points of interest as event triggers. This is also tied into the door entry system, which can actively track activity in the facility and record contextualised snapshots from nearby angles, to create journey data for future reference (if ever required). This level of automation is fantastic for enhancing our security.


What’s next?

Next up, we’ll be continuing with commissioning works across the board, as we liven up all areas of the site.

London East Build Blog – Weeks 83 to 86

The final stages of phase one are progressing nicely, with a wide range of commissioning and integration works now underway across the site.

It’s very exciting to see critical systems that will soon be delivering service to end users begin to come online, with hardware now starting to land in core and distribution racks for the first time.


Weekly overview

It’s been another busy few weeks on-site at London East, with the bulk of our time and effort now spent on technical commissioning work, and on the completion of outstanding finer details, as we head towards the end of the year.

Our heads are very much down as we approach the holiday period, to ensure that we reach our status targets before the new year. As such, we’ll keep this post brief, and move straight onto the photographic updates.

Compound
Our compound security fence has had its signage applied, which includes warnings about CCTV, razor wire, and other important informational signs – these span the full length, and all faces
Compound
The main visitor entry point to the facility has now been completed, including full privacy / security panelling, and our site name vinyls – London Central is having brand new panels and updated vinyls installed to match very soon
AC Plant
The CRAC and comfort cooling condenser plant is now fully installed and commissioned, and sits in a corner of the main compound – this will have its own small sub-fence installed as part of phase two
Gens
A look across the front compound to our generators, which have now had their identifier vinyls applied
Gens
The simple yet bold branding found throughout NLE continues outside, with the large format numbering now in place on our four generators
Signage
All interior signage is now complete, with this view showing the first floor directional signage in the main corridor, to direct visitors as they leave the lift and staircase atrium
Riser
All four of our riser access areas have had custom grills installed, to allow for safe and easy engineer access at any level – these are custom-cut GRP grills, installed on a custom steel frame, unique to each riser and their various penetrations
Cooling
The data hall cooling control systems are now full commissioned, and the area is now being actively controlled by the new system – here we see the main status screen for Data Hall 1, which has had a fully custom holding display built to show real-time information from within the space
Power
The final stages of the power system commissioning works are underway, which includes all integration settings on our main switchboards – this is a view of the main status screen in LV B
ODF
The network rollout has begun at the core, which will be followed shortly thereafter by aggregation and management roll-out in the data halls – here we see ODF B in Data Hall 1 being prepared for fit-out
ODF
This is the temporary setup in ODF B, which enabled some of the commissioning works to proceed ahead of having the main network in place – this also shows the custom vertical mounting arrangement we’ve deployed in these cabinets, to house switches
UPS
Here we see the UPSs in LV B at around 75% completion, pending the final UPS being rolled into place in the empty position on the left, which is as far as this room will see deployment during phase one
UPS
This is the front view in LV A, showing the fully completed UPS setup
UPS
The rear view of the UPS arrangement in LV A, with this space now phase one complete (aside from finishing touches to come post-commissioning)
Comms
The staging of our own core has now begun for both A and B sides – here we see the A side, with the main comms rack now staged ahead of cabling, which will happen once the ODF is also fitted out in the coming days, at which point the side panels will be fitted back onto the main rack
Comms
Here we see the B side, which again has the ODF fit-out to follow – this side contains some of the BT infrastructure delivered to site, so is further along in terms of deployment

We’re very pleased with progress, and we are very much enjoying the sight of things coming together. Being at the point whereby hardware is being installed into racks is another major milestone in this project, and an aspect of the build that our team tend to enjoy most as data centre professionals. This is when the facility begins to truly come to life, and systems are interconnected and brought into the Netwise ecosystem for the first time.

While there’s still plenty to be done in the weeks leading up to Christmas, we’re also all looking forward to our company Christmas party, which is now only a week or so away. We’ve got plenty to look back on this year, so we’re thrilled to get everyone together and celebrate our achievements.


What’s next?

Commissioning and integration will consume the bulk of our time on-site at NLE, ahead of the holidays. This will prepare the space for occupation in January. We’re extremely excited to see the new site integrated into our existing architecture in the coming weeks, becoming the fifth major POP on our metro network.

We’re also getting into the Christmas sprit on-site, which is always nice!

London East Build Blog – Weeks 79 to 82

We breathed life into many of the main power systems for the first time in this instalment, with commissioning actions underway on our primary switchboards and our backup generator systems.

The push towards phase one completion has seen many exciting milestone events reached in a short space of time, which is always great to see. We’ve energised the main switchboards, integrated and tested the generator failover, and removed the temporary site power, amongst a range of other system commissioning tasks.


Weekly overview

Things are sharpening up quickly on-site, as a wide range of systems begin to spin to life for testing and commissioning, ready to begin serving client kit in due course.

We’ve hit a number of milestones this time around, including the testing and commissioning of our cooling systems throughout the building (both critical and comfort), and the same point reached on our fire detection and extinguishant panels, both building-wide and the enhanced systems in critical spaces.

Speedgates
The speedgate area has been carpeted through from the main entrance and reception, to finish off the space ready for client arrivals
LV
The cooling systems throughout the building have now been commissioned and tested, with cold and warm air now available in all critical spaces
LV
Our UPS commissioning is well underway, with the main units now interconnected with the UPS output boards
LV
The building is now powered through the primary switchgear and distribution boards, with all temporary site power now fully decommissioned and removed
DH1
A look across Data Hall 1 after it’s had its initial post-work clean, with one of the supplementary AC units open for commissioning
DH1
A look across Data Hall 1, towards the first pod of racks
DH1
The four CREC units have now been brought to life, with cooling, recirculation and extraction now tested and proven
DH1
Both the primary CREC and supplementary CRAC systems feed into the shared underfloor plenum, which will distribute closely controlled air to all footprints in DH1
DH1
The entrance into the cold corridor in Data Hall 1 is the first view of our new signage design language (just visible here!)
DH1
The view towards the A-side power distribution in Data Hall 1, with ODF A visible on the right hand side
DH1
The primary CREC system has now had all filters installed – here we see the 28x quad-fin air intake filters, this being the first layer of filtration before hitting the multi-stage filtration inside each cooler
DH1
It’s been very exciting to see the cooling system spun up for the first time, and fantastic to see the real-world culmination of all our design and simulation work
DH1
Here we see some of the detail as you enter the cold corridor from Data Hall 1, showing the lighting system and the access hatch for the otherwise-sealed extraction loop
Loading
Our warehouse and loading bay now has large floor lettering / numbering on each receiving dock door for quick and easy identification while loading and/or unloading
Loading
These large format letters / numbers all form part of our new design language, which has now begun to roll out throughout the facility
Signage
We’ve opted for a more modern approach to our signage at London East, an evolution of the design at London Central – simplicity and clarity is the main order of the day here
Signage
All internal signage is now direct-application vinyl, in our custom font to match all digital and print assets – aside from a few 3D logo and type elements
Signage
Here we see one of the larger multi-directional signs to guide visitors around the facility
Signage
Each corridor and main customer route has multi-directional signage in place to guide visitors through the building
Signage
The frosted / etch effect pod door vinyls have returned, as found at NLC as part of our rebrand in 2019
Wifi
Visitors will now see wifi access points and access control beacons in various places throughout the facility – the wifi is an extension of the mesh deployed at London Central, meaning you’ll automatically connect at East if you’ve already done so at Central

As you can imagine, with much of the work on-site now commissioning actions, presenting this visually for the build blog is tricky. We’re hoping to put together another fly-through video soon, to show phase one completion.

Another unseen but extremely critical area which reached completion this time around is our fire stopping, which has now seen all additional wall apertures cut in since initial construction fully sealed and certified. This ensures that the building fully complies with our extremely strict fire design and operation policies.

With all of the broad strokes of the project now complete, we’re able to begin working through the more detailed finishing work, while system commissioning actions continue.


What’s next?

As is to be expected at this point in the project, more of the same.

We’re quickly moving towards welcoming in our first client systems, with the final set of work ahead of this to focus on UPS systems, network integration, and general facility commissioning (things like onlining our NOC for CCTV and systems monitoring).

London East Build Blog – Weeks 75 to 78

The pace has certainly picked up now, as we push towards phase one completion at London East.

This acute focus has left little time for the blog, and as broad strokes visual change has slowed down at this point, we’ve put together a four week short summary of the last month on-site at NLE.


Weekly overview

Phase one completion will see the facility ready to take its first clients, which is an enormous milestone for us here at Netwise.

There will still be some ongoing works beyond phase one, which will include things like our customer lounge and some other secondary niceties, as primary focus at this point is getting the technical spaces completed and ready to receive live client systems.

Looking slightly further ahead still, phase two will involve the preparation and roll-out of further technical space, making use of the other data halls, which given the amount of work put in ahead of time for this will certainly come to fruition much more quickly. This is expected in 2022, and will be based on a dynamic roll-out schedule, driven largely by demand.

The largest area of progress in this instalment of the build blog has been centred around air conditioning. This is not our primary cooling source in the technical spaces at NLE, with that role falling to our extremely efficient adiabatic systems, however traditional AC does still play a crucial role in both supplementary cooling in critical spaces, and comfort cooling in customer and staff areas.

Cooling
This is a view inside the cooling control system unit for Data Hall 1, as the internal termination reaches completion
Cooling
The pipework for both the supplementary CRAC systems and the comfort cooling throughout the building are comprised of some very long pipe runs, depending on the location of the internal equipment
Cooling
Some of the pipe runs for the AC systems have been fairly complex, because of their routes, and because of how split systems have their pipework distributed between endpoints
Cooling
One of the main convergent runs of AC pipework can be found on our storage mezzanine, as the runs cross towards the exterior condenser area
Cooling
Here we see one of the main runs coming together, which traverses the storage mezzanine before reaching the exterior skin and turning down towards the point of exit
Cooling
Power cabling also joins the pipework runs, with drainage to follow
Cooling
Here’s a snapshot of the complex manifold work happening in one of the ceilings, as the split systems are evenly distributed to ensure even pressure
Cooling
This is the AC unit in the build room and customer breakout area, as the cabling begins to be terminated internally
Cooling
All comfort cooling systems have in-room control panels
Cooling
This is the control panel for the system in another customer amenity space, which also allows for remote operation and monitoring
Cooling
Here we see some of the external condensers being worked on by our AC engineers
Cooling
The external condensers are laid out in a grid which enables plenty of future growth
Cooling
The larger condensers here are for the supplementary downflow units in the data halls, temporarily stood on their rubber feet ahead of permanent fixture
Lighting
Here we see the overhead lighting system installation underway in the cold corridor area for Data Hall 1 – this is where external air is filtered and processed for our primary CRAC system
Power
The UPSs and UPS switchboards are now in place and terminated in LV B, to match the state in LV A
Power
Our main LV switchboards in both LV rooms have now had their line diagram vinyls fitted, taking both boards to completion ahead of energisation for commissioning and setup
Power
The line diagrams are fitted to all switchboards, including the smaller sub-boards for the UPS systems
Racks
Here we see one of our custom designed security panels fitted to Pod 1 in Data Hall 1, for the privatisation of racks within said containment system
Razor
We’ve now fitted the razor wire to the top of our compound fencing, which aside from adding electric motor controls to the main gate, takes this area to completion
Razor
The razor wire now runs the entire perimeter of the facility
Razor
We designed a custom implementation of the razor wire retention system to allow for the retraction of our large vehicle access gate
Spraying
As part of the final stage of work, we’ve had any construction marks and / or damage on our metal clad panel walls repaired, which included full panel respraying where necessary
Spraying
Any panels with damage incurred during the build have been returned to factory condition
Spraying
The spray team were able to achieve a truly flawless finish
Spraying
We’re very pleased with the outcome of the retouch and repair works undertaken throughout the facility
VESDA
The VESDA pipework has now been installed in both LV rooms

As you can see, NLE is still an extremely busy site, with lots of finishing stage work underway. Yet so much more of the work being undertaken at this point is not of a visual nature; commissioning of power systems, access control, network setup, CCTV etc, these are all tasks with little to photograph. However progress across all of these areas will be relayed when suitable.

We’re certainly entering into an exciting period of the build, as major systems begin to see energisation for the first time.


What’s next?

More of the same as we head towards phase one end-out. Keep your eyes peeled for the next instalment of the blog, which will show much of the major infrastructure being onlined for the first time!