London East Build Blog – Weeks 52 to 55

A slightly later-than-planned update to the build blog this time around, thanks to time spent on more critical development works, as we head into a period of extended activity on-site at NLE.

The last four weeks have seen excellent progress across a varied range of areas, bringing a number of outstanding side-projects to a close, and solid advancements made on some of the remaining primary tasks.


Weekly overview

We’ll be keeping the update this week brief, so as to retain focus on real-world progress, however this post will serve as a general visual update to our readers, showing advancements across the various areas which have seen the most apparent change.

Front Gates
As seen at NLC, we’re blanking off the gate and turnstile sections of the front compound fencing, for added visuals and security – the turnstile sections are to follow
Checkerplate
The final outstanding checkerplate has now been installed, seen here in the ground floor level loading bay
Loading Bay Guard
Both the ground and first floor level loading bays have had checkerplate and bash protection installed, allowing the forklift to bump into the stops here for accurate, guess-free loading
Louvres
The intake louvres are now complete, pending their filter frames being installed in due course – here you can now see both top and bottom runs in place
Louvres
Here is an external view of the two intake louvre runs for Data Hall 1
Louvres
This is the continuation of the intake louvres beyond the first floor data hall fire escape route
Roof Sheets
This is our shipment of soaker sheets for the roof aperture profiles, which will take the extraction cowls
Roof Louvres
A view of some of our newly installed extraction cowls, as fitted to the roof of the cold corridor for Data Hall 1 – these will take warm exhaust air out to atmosphere when not required for recirculation, and are in this position to avoid any possible heat loops with the intake side of the primary cooling system
LV Plinths
Our LV rooms have preparations well underway to receive the main switchboards – the first part of this is preparing the open floor apertures for the incoming custom equipment plinths
LV Plinths
This is the main open trench for the primary switchgear in LV Room B – the custom plinths will sit inside this opening, with the floor finished to the front and back side of the frames
Boards
Here we see our custom PDU expansion boards which will affix to the bottom of our Mardix PDUs in the data halls, allowing for our circuit monitoring to be installed on each rack feed
Ceiling
We’ve now started installing the ceiling tiles, as overhead works on the fire detection and lighting systems reach their conclusion – this has really started to finish off each room, giving a better indication of the finished surfaces
Ceiling
Here we see the tiles installed in position above the eventual location of Pod 2, inside Data Hall 1

The most keen focus has been spent on the cooling system, in terms of the handling of air in and out of the building.

Beyond the visible updates as presented above, we’ve also been able to continue with underlying developmental plans for the remaining work phase, including aspects of power and connectivity.

Our fire contractors are now close to completion, which will be another major system milestone checked off very soon, as we march towards client deployment readiness.


What else has been happening?

It’s been a bumper start to Q2 here at Netwise, as we help a wide range of new and existing clients grow and deploy in our London Central facility. We’ve also started showing new prospects around London East as it moves nearer to completion, with a range of racks in the first pod now allocated to incoming clients.

We’re also close to pushing out a press release announcing our first major on-site carrier, so keep an eye out for that in the coming weeks.


What’s next?

Works are continuing on power, fire and connectivity. These are the main focus as we move towards the summer months, and to our forthcoming launch – watch this space for updates on when our first on-site events will be held.

London East Build Blog – Weeks 49 to 51

Things are really heating up now in terms of progress on-site at NLE, as we document another three weeks of work at our forthcoming data centre.

We’re almost at the one year mark in terms of when we first gained access to the new building, and despite some setbacks early on due to the Coronavirus pandemic, we’ve been extremely pleased with how quickly we’ve transformed the site from shell to data centre.

We’re not quite there yet, but we’re getting ever closer!


Weekly overview

The last three weeks have seen tremendous progress across a wide range of project areas. The most notable changes have centred around the physical adjustments to the rear of the facility, as the first set of louvred intake panels are cut into the exterior walls for Data Hall 1.

Speedgates
Our custom cable cover ramps have been installed as part of our client flow speed gates
Cooling
The coolers for Data Hall 1 now have their water supply and drains plumbed in
Cooling
The cooling controller for Data Hall 1 has now had its trunking installed, which connects through to the routes in the data hall itself
Fire Panels
The fire panels have started to have their containment installed, with cables now run in to them for future commissioning
Fire Panels
Here we see some more fire panel containment and cabling, along with the route being taken by our single run of MDPE pipework for the cooling supply
Fire Panels
The containment during installation inside Data Hall 1 for fire systems, including the main panels and VESDA system
Fire Panels
This shows a near-complete containment assembly for the VESDA system in Data Hall 2, which allows for multiple route options between equipment
Louvres
The first set of louvres being cut into the rear elevation of Data Hall 1’s cold corridor, with frames being installed
Louvres
The first set of louvres installed ahead of having their rear bag filter frames fitted – there will be a second run of these louvres installed underneath these, giving 28 external intake louvres per hall in total
Louvres
Another view of the first set of louvres installed for Data Hall 1
Louvres
An exterior view of the louvres as installed, ahead of the second run below this set, and some finishing flashings that will be install on completion
Louvres
The louvres for Data Hall 1 are split across the fire escape door
NOC
The black textured wall in the meeting room at the NLE NOC also doubles as a handy pin board, which is ideal for displaying various technical drawings during the build process
Pod 1
Pod 1 in Data Hall 1 is now fully assembled, with both automatic doors now installed and powered
Pod 1
A view across Data Hall 1, at the now fully assembled containment pod, housing the first 28 racks
Pod 1
We’ve carried over our use of APC hardware for all racking and containment, which will mean a familiar service presentation for clients with services in London Central, and elsewhere in our partner sites
Pod 1
A look at the contact-free entry and exit sensors for the shared Pod 1 colocation space, which can be opened even with hands full with equipment
Pod 1
Another view down the length of Pod 1 – you can just make out our custom rack unit blanks in the top quarter rack, which have our logomark on them

As we hope is self-evident, the visual and functional change on-site has been noteworthy, to say the least.

Big advances have been made in containment, which helps move the project along in many areas. Our fire contractors are now able to bring all systems together, and complete the VESDA and extinguishant panel integrations with the main building system.

Having Pod 1 reach point of completion from an assembly perspective is also a major project milestone, and gives a tangible focus point for any tours of the site ahead of it opening.


What’s next?

Next week we will reach 12 months on-site at NLE, although due to COVID-19 restrictions early on, we’re probably more like 9 months of true work into the project.

The next set of louvres will be installed in the next week or so, along with further works on various open projects. This all falls alongside larger project work, which will see broader stroke progress as the build continues towards full onlining in the next few months.

London East Build Blog – Weeks 47 and 48

We have another two weeks in the books on-site at London East, as things continue to develop as we head towards energisation.

The last couple of weeks have seen a good amount of change across a number of areas, including dramatic visual changes in Data Hall 1, and to the generator canopies.


Weekly overview

The containment system in Data Hall 1 has now been partially assembled, scheduled for completion next week. Most importantly, the two pod entry / exit doors have been installed, and had their electric opening and closing mechanisms setup.

Containment
Here we see one of the pod entry and exit doors partially assembled, with the cabling strung out for testing
Containment
This angle is from inside the pod, looking towards the front of the room, as the containment roof panels begin to find their place atop the rows of cabinets
Containment
A look at the rear of the racks, as the system continues to be assembled, including baying, roofing, cable trough installation etc
Containment
This view is of the second pod entry and exit door, found at the rear of the hall, as it is assembled
Containment
The front-side pod access door now fully assembled – it will receive vinyl signage similar to that found at London Central later in the project
Speedgates
The speed gates for access to the technical spaces at London East are now fully integrated and assembled, pending their walk plates (as seem temporarily placed here) and carpeting
Mountings
The first round of panel mountings have begun, with the fire alarm / extinguishant panel and cooling system control and status screen for Data Hall 1 shown here
Mountings
A closer look at the fire system panels, which are now in place for all data halls and LV rooms
Mountings
A closer look at the Weinview screen panel, which will show cooling status and master controls for Data Hall 1
Mountings
The data halls and LV rooms at East have latest-generation VESDA-E units installed, pending air sample pipe work installation shortly – the data hall models, as seen here, are the full visual output models
Mountings
Here we see the VESDA-E units as mounted in the LV rooms
Gens
The generator canopies have now been refinished in the same anthracite grey as found across this new site, pending ID vinyls in due course
Gens
The generators, alongside being fully commissioned from an electrical connection and control standpoint, will also have a final clearcoat applied in the next few weeks, and some removable security access panels fitting in the gaps between them (effectively zoning them off from the compound)
Extraction
These are the extraction cowls destined for installation on the roof, over the top of the rear cold corridors
Inlets
These are the various components that will make up the intake louvres, destined for installation on the rear face of the building, allowing our evaporative cooling plant to intake external air, through our forthcoming bag filter wall

The containment pods are extremely impressive in person, and will provide a dominant focal point for the first hall. The contact-free entry system, which makes use of a proximity sensor, is particularly impressive to see and use.

The walls – as seen above – have begun to see more tech installed upon them, in the form of various panel boards for various systems. These will have their feeds installed as the main electrical works are underway. In particular, the newest generation VESDA-E panels are very striking, and work much better with the colour pallet at East (compared to their previous generation white / white and green panels). It’s the little details that we really love, and which come together in making a truly beautiful facility.

We think that the refinished generator canopies are a real show-stopper. These sit in a rather dominant position in the front compound, and as such we wanted to ensure they remained in-keeping with the visual language of the site. They’ll be having their ID and branding vinyls applied soon, which again will add to their commanding presence.

The adjustments to the skin of the building are scheduled to begin in the coming two to three weeks, in line with the commissioning of the water supply and drainage to the evaporative coolers, which began this week.


What’s next?

The open set of works as seen above will be brought to a close, as the main electrical contractors begin. Works will continue across the board, most intently focusing on cooling and fire system works, which are now underway throughout the building.

Ralph Wall joins Netwise

We’re extremely excited to introduce you to the latest member of our ever-growing team. Meet Ralph Wall, our new Sales Manager.

Ralph Wall

Ralph has enjoyed a long and successful career in the data centre industry, heading up the sales function at a number of very notable organisations within the sector over the years. His wealth of knowledge, experience and contacts are second-to-none, and will be a much-welcomed addition to the in-house skill set at Netwise.

The ongoing Coronavirus pandemic delayed the official announcement of Ralph’s joining, having actually started with us back in mid-January. We’re now very pleased to be able to fully announce Ralph’s new position with us, and we’re looking forward to seeing the improvements he will bring to the table as we enter another new phase in our development cycle.

It’s no secret that Ralph’s addition to the team comes at a time of major growth and investment for Netwise, with the forthcoming launch of our brand new London East data centre later this year. He will be overseeing the growth and development side of the business as we launch London East, and continue to welcome new clients (and service existing client growth) at London Central.

This new level of representation couldn’t have come at a better time for us, as we enter the end-out phase of construction on what will be our biggest and highest specification data centre to date; the third in our build history. Hard hat tours of the new site will begin shortly, and will be orchestrated by Ralph and the engineering team at Netwise. You can check out our Build Blog here to keep tabs on progress.

You can expect to meet Ralph at our forthcoming launch event(s) later this year, and at all of our social events, once they’re allowed to resume without restriction, of course.

We can’t wait for you to meet Ralph, and he’s certainly excited to meet you too. Get in touch if you’re interested in speaking, or to organise a tour of our facilities.

London East Build Blog – Weeks 45 and 46

We’ve enjoyed an exciting fortnight of changes at NLE for this instalment of the Build Blog, with a large number of big ticket items landing on-site.

This has resulted in notable change throughout the facility over the past two weeks, across a number of key areas. The most striking of these has been the siting of our new generators, which now sit in their final positions in our front compound.


Weekly overview

Alongside the generators arriving – which are having a full canopy refinish in anthracite grey next week – we’ve also taken delivery of our first containment pod, including racks and the cold aisle system. This has resulted in major visual change in Data Hall 1.

We have a time lapse of the generators arriving and landing in place coming very soon, so watch out for this on our socials.

The first containment pod can now be assembled in Data Hall 1, which will be another major milestone in the deployment of our new facility.

Containment
Here we see our container arriving with the first containment pod setup for Data Hall 1
Containment
Part of the shipment was comprised of 14 fully built racks, alongside another 10 flat packed
Containment
The racks were unpackaged to the point of having a single retention bracket remain fixed to the custom pallet, before being lifted up to the first floor – in shot here we see one of our custom quarter cabinets
Containment
Empty racks are lifted up to the first floor loading dock, before being rolled off their custom pallets
Containment
A view from inside Data Hall 1, as the racks that will make up the first containment pod begin to roll into place
Containment
Another view from inside Data Hall 1, as the racks that will make up the first containment pod begin to roll into place
Containment
Some of the containment materials as they begin to be unpacked ahead of installation
Fence
We’ve now completed the physical installation of the turnstile and return-angle fencing that make up the main personnel entrance of the compound – the anti-climb rotating arms match those found at London Central
Fence
A wider view of the now completed entrance area of the compound fencing, pending full razor wire installation to the perimeter in the coming weeks
Generators
Here we see our new generators arriving to site, on two articulated trailers with lifting equipment
Generators
The first of four generators being lifted into place, each of which weigh around five tons dry
Generators
The final two generator sets ready for offloading, to join sets one and two which are now in place
Generators
All four sets in place, which will be securely sub-fenced off after commissioning – they’re also having a full canopy refresh in the coming weeks, taking them from white to anthracite grey
Sign
The backing board of our new sign being installed, with the protective film still in place
Sign
A look at the installed sign, which is an exact replica of the one at London Central, just on a slightly smaller scale to better suit the installation location at London East
Sign
A wider view of the new sign, in context with the main entrance door
Cabling
A look at the first delivery of fire cabling, ready for installation to begin next week
Van
We installed our new lightbar to the van this week, which brings the vehicle to completion
Van
The van enjoyed a deep clean on-site this week, which was overdue in terms of removing the winter road salt that’d slowly been building up in the colder weather

The installation of our exterior building sign was quite a momentous occasion, as it’s the first time this facility has been properly branded with our logomark. This is the exact same style of sign as seen on the side of our London Central facility, with the diffused backlighting that really makes the sign pop at night.

The first instalment of armoured cabling to arrive, which will make up the bulk of the main underfloor power routes, will total somewhere in the region of eleven tons. The fire cabling within the building, which covers all detection and alarm systems, will total 2.5km in length.

We’ve had lots of custom made parts arrive over the past few weeks, destined for installation and / or use throughout the facility. One such item is a custom fork lift plate, which has been designed to take racks from the loading bay up to either floor level. This is a heavy duty steel plate welded to fork sleeves, which is low profile enough to drop straight into each loading dock.


What’s next?

The on-site schedule really picks up in the next week or two, as things begin to move on the end-out works. The site has a large number of trades beginning work, including the fire team, generator canopy refresh team, lift engineers, and a team who will be heading up adjustments to the skin of the building as part of our cooling system(s). This is all happening alongside the main power contractors beginning work, following completion of all design and design testing.

We’re very excited to share the progress!