London East Build Blog – Weeks 71 to 74

Now that raised floors have started to go back down, and termination of cabling is essentially complete, impactful visual change has slowed down slightly, however progress is still pushing forwards at great pace.

We’ve been preparing for some of the final trades to land on site to end-out phase one, which will include the CRAC pipework team and the wall fabrication team from earlier in the project, who will be finishing off some of the final cooling system segregation now that the fans are installed.


Weekly overview

Much of the change this time centres around supplementary cooling, VESDA / fire panels, and data cabling for things such as CCTV, access control and monitoring / system control.

We’re now very much in the end-out phase of the project at this point, which means that various elements that until now were operating separately are coming together quickly.

For example, our evaporative cooling units are now connected back to both their power delivery and control systems, meaning that they will soon be ready for their first spin up and test. This is the same for a number of the core systems which make up the infrastructure of the facility.

AC
We now have most of the building-wide comfort cooling in place for client and staff areas, including here in the build room and customer lounge
AC
Here we see the ceiling mounted AC unit mirrored on the other side of the building, and the same units are now also present in the NOC / office
AC
We’ve also got three high performance models installed in each of the LV rooms, with room for a fourth in due course as and when required based on UPS expansion
AC
Our VESDA pipework is now installed in Data Hall 1 and pre-emptively in Data Hall 2
VESDA
This is the view of the installation in Data Hall 2, which we are pre-staging for future use, along with all other baseline infrastructure – this will speed up the commissioning process for this hall dramatically once it’s needed
VESDA
This is the view of the VESDA installation in Data Hall 1
VESDA
This is a slightly wider view of the VESDA installation in Data Hall 1, showing the various sampling pathways as they leave the main unit, and also showing the B-side PDUs for distribution to client racks, and the earthing bar for the hall
VESDA
Here we see the VESDA pipework installed in Data Hall 2, along the blanking system at the rear which will eventually house the CRECs for this hall
CREC
The CREC units in Data Hall 1 have now had their power and control system cables installed, which brings them up to readiness for commissioning in due course
ODF
The ODFs in Data Hall 1 are starting to take shape, with containment now run in from both high and low levels – here, one of the newly installed cleaner sockets is also visible, as part of a wider ring installed throughout the building to support such requirements
ODF
This is the B-side ODF, with a range of cabling now run back to it to support various functions in Data Hall 1, such as CCTV, monitoring and system controls
Pod
Here we see the entrance to the first committed private pod in Data Hall 1, which after some forthcoming adjustments to access control and visual identity, will be handed over to the client in Q4
Pod
Another view of the pod entry door systems that we use with our APC racking and containment system, which are operated electronically
Power
This floating, conduit-free cleaners socket is achieved by ensuring that it backs onto one of our risers, meaning all containment for the cabling is hidden from view, something we have done wherever possible for a clean installation
Power
This is the cleaners socket as installed alongside ODF B in Data Hall 1, which due to its positioning does require conduit access to under floor containment
Power
The UPS boards are now landing back in place in both LV rooms, having been removed during the flood cabling process
Power
Another view of the PDUs which distribute B-side power in Data Hall 1, with all internals now completely terminated, and ready to hand-off power to client racks
Reception
We now have our new reception desk standing in place, which will be finished with branding and a glass security and visitor flow system in due course
Reception
Another view of the reception desk as placed in an approximation of its final position

We’re getting to the point at which photographing visual change is likely to slow down somewhat, as we move onto more detailed work such as the interconnection of critical systems, and the onlining of various electrical elements including CCTV and door access control.

Excitement is starting to build as the many months of extremely hard work from all those involved begins to show its final fruits, which will become all the more exciting as we start to see systems roar into life.


What’s next?

While build and installation works will continue in a few final areas – such as CRAC pipework, final airflow containment for extraction in Data Hall 1, and the end stages of general system containment – we are now also in a position to begin the early-stage commissioning process.

We are entering an exciting phase of the project, as things finally begin to slot back into place after a good few months of ordered chaos; a necessary evil associated with the extensive electrical work required to take the building from completed shell to functioning data centre.

Over the next few weeks, we expect to see the site visually return to a state of completion (for phase one), at which point the site will be onlined, and commissioning of critical systems will begin in earnest.

London East Build Blog – Weeks 69 and 70

We have more exciting progress to share in this instalment of the Build Blog, as cabling continues to run into the facility at pace.

This progress has been seen across the board, from the largest runs out to external connection points, right down to the smallest termination points inside of the Data Hall PDUs.


Weekly overview

In the last two weeks, we’ve doubled the labour force involved in the electrical side of the project, adding a dedicated cable gang to the on-site trades to help push through the final cable runs, most of which are very substantial armoured cables.

This has seen the vast majority of the on-site cable drums emptied and returned to the vendor, as the cables now lay in place, with termination well underway across the board.

We also have a dedicated jointer on-site, who is heading up much of the largest termination activity, such as inside the generator canopies.

Cabling
The first set of cables that make use of the external ladder runs out to the transformer, seen in place here
Cabling
Another view of the first set of cables on the transformer-to-LV room route
Cabling
This run takes cables all the way out to the transformer enclosure – these are again in a trefoil cleat arrangement, as with the LV Room interlink cables
Cabling
The GRP enclosure for the transformer now in place atop the previously poured base
Cabling
The cables that connect to the transformer take a direct route around the perimeter of the front compound, with rear-mounted security panelling to be installed soon
Cabling
Another view of this particular containment run in the front compound
Cabling
This is the view back towards the building, with the containment and cabling penetrating the skin of the building, pending final capping and fireproofing
Cabling
Some of the newly emptied cable drums, which have since had their contents run into the facility
Cabling
Termination of the main LV boards is now well underway, with a view here inside one of the main enclosures in LV Room A
Cabling
Another of the main enclosures in LV Room A, with the termination now complete
Cabling
This is a view of one of the main enclosures prior to any termination, after glanding
Cabling
Here we see one of the same enclosures mid-way through termination
Cabling
The same enclosure as it reaches completion
Cabling
This view under one of the LV Room floors shows the next layer of containment and cabling going in over the top of the base layer
Cabling
A view of some of the ladder work on the first floor, which now contains the runs which will feed Data Hall 1 with protected, conditioned power
Cabling
A look inside one of the PDUs in Data Hall 1, as the final termination begins
Cabling
This view shows some of the cables as they make use of the riser in LV Room B
Cabling
This is the view of the external containment which heads to the generators, as the cabling nears completion
Cabling
Another view of the generator cables as they enter the building
Cabling
A look across the rear of the generators, where this cabling will soon enter each unit
Cabling
The generator cables enter the building here, and then pass into LV Room A for onward handling – these holes will all be fire stopped and finished with tight-fitting decorated panels
Cabling
The transformer route shown here now contains all cabling as necessary to liven up the site during commissioning
Cabling
Another view of the transformer cabling, with the earthing now in place
Cabling
A view of the transformer cabling as it reaches the enclosure, ready for connection into the transformer once that is installed
ODF
Here we see one of our custom ODFs, of which there are two in Data Hall 1 for diversity – this angle shows the installed overhead cable ladder bridging across to Pod 1
VESDA
The VESDA pipework installation is now underway in Data Hall 1
VESDA
A look at the pipework as it begins to be installed along air pathways, in this case on the supplementary CRAC unit intakes, which now have their automatic dampers fitted
VESDA
The pipework is also installed along the main CREC exhaust and recirculation louvres

This has been a fantastic fortnight for project development, with tremendous progress on the cabling side of things.

We’ve been very excited to see all of the cabling begin to disappear under the floor and into the risers, ready for termination and testing. We’re also very excited to see some additional visual elements installed, such as the bright red VESDA air sampling pipework.


What’s next?

We will continue with progress on all things electrical. As cable pulling nears completion, focus will shift more completely onto termination, along with supplementary power installations, including small scale non-critical power delivery to things like cleaner’s sockets.

Beyond this, the VESDA pipework installations will continue, and with the arrival of additional cabling for things such as the CREC control and monitoring system, this will also begin to take shape.

London East Build Blog – Weeks 66 to 68

Focus on the Build Blog this time around has been firmly on progress with cabling and containment, which continues to develop across the entire site.

A hefty quantity of the largest internal cabling is now all in place, totalling around 8 tonnes. This will now be terminated, along with a host of smaller internal cabling, while additional large external cabling is run in thereafter, as we head ever closer to energisation at London East.


Weekly overview

We’ll get straight into the photos again this time around, as we take a look at cabling and containment developments on-site at NLE.

Containment
Containment has now firmly breached into the exterior areas of the new site, with the runs to the four generators taking shape here
Containment
Another view of the generator containment as it works its way around to the point of entry on each gen set
Containment
A closer view of the twin ladder runs out to the generators, to account for the large quantity of cabling required to connect these units back to the main switchboards and controllers
Containment
What look to be simple drops across to the generators actually required considerable effort, as solid concrete and brickwork edging had to be excavated to allow for the ladder to pass through to the required location
Containment
On the other side of the front compound, the twin ladder runs to the transformer have started to be installed
Containment
Here we see the supporting slotted channel being prepared for installation on this solid block wall, which will house the transformer cable runs as they pass into the building
Containment
The external skin of the building has been modified to allow cabling to enter and pass along this route
Containment
Here’s a view of the uncovered cable ladder which sits under the floor in the ground floor access corridor
Containment
Here we seem a temporary blanking panel in place until the ladder is ready to pass through the building – additional tray is being run in to hold AC pipework for traditional systems that will support supplementary areas of the building
Transformer
The transformer base is now ready for the installation of the GRP enclosure, and the transformer itself
Cabling
This is a view inside of LV Room B, as some of the large ~300kg inter-room cables are run in, which will link the LV boards for various functions / reasons – they are simply laid in loose at this point in time
Cabling
This is the drum of cabling for connecting out to the generators, which clocks in at 2.2 tonnes
Cabling
One of the first drums to be emptied – this was a 1.8 tonne spool, which is now all run in under the floor between the LV rooms – this will be modified and become an outside table for clients to use
Cabling
Another finished drum, slightly smaller this time, equating to around 1.2 tonnes
Cabling
A look into LV Room A, with the cabling being pulled into its trefoil cleats
Cabling
A view into the main LV Room cabling route as they enter LV Room B, showing the cleats as they hold the cables down to the floor mounted channel
Cabling
Another view into LV Room B as the routes continue to take shape, and the tails are fed all the way into the boards
Cabling
Earth cable being pulled into the floor, which again will interconnect the LV Rooms
Cabling
A view into LV Room A, as the earth cables are laid into position ahead of cleating
Cabling
Here we see the earth cabling being pulled into its cleated arrangement, which brings this main route to its full state
Cabling
A look down the main cable route between LV Rooms, showing the multiple trefoils and earthing bundles and they run between the two main boards

As you can see, the main focus here has been on continued progression with cabling and containment, which will continue into the next instalment of the Build Blog.

As always, other works have of course been underway, both in the development of London East, and elsewhere across our ever-growing operation, however we’re keeping this post concise and on topic.


What’s next?

As with the previous ‘what’s next?’ update, we’re looking at more of the same over the next few weeks. We have a vast amount of cabling and termination to undertake, which we hope to see nearing completion by the time we next post to the Build Blog.

We’ll also be moving onto further work on fire and VESDA systems, and will be moving ahead with commissioning on cooling systems, as well as continued work on power, such as the roll out of ‘small power infrastructure’ (supplementary building-wide power sockets for cleaning equipment etc).

London East Build Blog – Weeks 63 to 65

Vast changes again this time, as the electrical works push on at pace both inside and outside of the new facility.

While visually the site now appears a little less finished than before, with masses of flooring taken up to accommodate the newly installed containment and cabling, from a more wholistic view point, things are pushing forwards in a big way at the moment.


Weekly overview

The pace of work and progress on-site has certainly been turned up a gear, as multiple trades now work together on various aspects of the facility’s power systems, alongside work on other related areas to maintain solid progression throughout.

We have a lot of photos to present this time around, so rather than spending too much time on the introduction, we’ll let them do the talking.

LV Boards
Our LV boards have arrived with us, split across two deliveries due to their size
LV Boards
This first batch of boards shown here are destined for LV Room A
LV Boards
We were able to swing the boards right into the loading bay, ready for pre-staging ahead of them being rolled into their final position on their respective plinths
LV Boards
The first couple of sections of the board now coupled together in LV Room A
LV Boards
Here we can see into the gland plate enclosures, where the large armoured cables will soon enter the boards to feed the various breakers seen in the chambers above
LV Boards
Here is another view of LV Room A, with the UPS Boards now also in their final places opposite the main board
LV Boards
The size of these boards makes taking a photo of them tricky – getting them all in view is nearly impossible – a wide angle lens in on our shopping list!
LV Boards
A view from the door of LV Room A, looking towards the boards now full situated, coupled, levelled and locked off
Containment
This is the view down one of the risers, as the containment between floors begins to take shape, and specialist containment for fire cable routes is run in
Containment
A look at some of the containment in place to hold the ladder work under the floor
Containment
Here we see the floor starting to go back down in Data Hall 1, now that the whips are in place – more on that further down in this post
Containment
Another view of the floor back in place at the rear of Row A in Pod 1, with only the termination at the PDU end to go
Containment
Lots of inter-room pathways have been made for cable routes in the past few weeks
Containment
The largest cables will be cleated to the ground, with slotted channel now fixed to the ground along these routes to accommodate this
Containment
Here we see the slotted channel in place under the floor in the LV Rooms
Containment
The main containment runs out to the generators are also starting to take shape
Exterior
Further progress has also been made outside the building, with the trenches dug for the ducting that will carry our HV feeds into our demise
Exterior
The main run of trench to take the ductwork out to the roadside
Exterior
Here’s a look at the poured transformer base, with the shutter forming fully removed
Exterior
A look at some of the machinery on-site to undertake the ground work
Exterior
The trench continues to the road, with steel plates in place to bridge the gap for access while the top remains open
Cabling
Here we see some of the smaller drums of earth cabling for this phase of the project arriving to site
Cabling
Here’s one of the larger drums of earth cable, clocking in at around 750kg
Cabling
Some more of the earth cabling in storage, along with a large quantity of the ladder to be installed around the facility
Cabling
A sizable delivery of the larger armoured cabling that will run between the LV rooms, and to the Data Halls
Cabling
Some of these drums are around 2 metres in diameter, with the delivery clocking in at circa eight tonnes
Cabling
Some more of the drums inside, awaiting their time to land on the large 10 tonne axels we have for pulling them in – each single length of cable can weigh as much as 300kg, and needs to be pulled in using special rollers
Cabling
A view of the cabling as it is laid under the floor, between the LV Rooms
Cabling
Much of the floor has come up to allow for the cabling to be routed, along with the temporary removal of the UPS boards
Cabling
The cabling has been partly stripped here, and installed into the gland plate ready for eventual termination
Cabling
This view shows the cables starting to be cleated together, which run the width of the building between the two LV Rooms – there are 15 more cables to join this first three
Cabling
The first set of cables reaching LV Room B, which will interlink the two boards
Cabling
This view further shows some of the underfloor containment, which is multi-layered in the LV Rooms (top layer removed here)
Cabling
This is a view of the now completed cabinet-side whip cabling in Data Hall 1, which will feed each of the racks with diverse power
Cabling
This room alone has eaten up over 2km of cabling, with well over 3,000 ties holding it all down to the tray
Cabling
Data Hall 1 has been flood cabled with feeds for all eventual rack locations, including the currently vacant spots for Pod 2
Cabling
Diverse cable routes always take pathways which reduce cross-over, in this instance only happening once, where A and B feeds need to move past each other as each pod is cross-fed – a cable bridge has been installed to handle this
Cabling
As always, the devil is in the detail, and we’re very pleased with how the underfloor cabling has come together in Data Hall 1
Cabling
A view down the length of Row B, with all commando sockets in place, and earth bonding for both the racks and the raised floor visible
Cabling
The A and B feeds to each rack only converge at the rack itself, otherwise maintaining fully separated routes throughout
Cabling
Keeping routes so strictly diverse in this way requires far more cabling and containment, which comes with a great deal of additional cost and labour, however it is vital for true client-facing A/B redundancy

As you can see, it’s been a busy few weeks on-site here at NLE.

Things are certainly ramping up as we move into the closing stages of the opening phase of the project, which will allow our first clients to install kit into Data Hall 1.

It’s certainly a rather intense time to be a part of the NLE project, as multiple trades push on with various aspects of the build in tandem, ultimately taking us towards the finish line at pace, and in line with expectations on our phase one launch.


What’s next?

For the time being, much of the same. Progress will continue on electrical over the coming weeks, and we will also be pushing ahead with other areas, including the various cooling systems throughout the facility.

London East Build Blog – Weeks 59 to 62

We have a very exciting instalment of the build blog this time around, as we see masses of containment and cabling begin to roll into position at London East, along with civil works for our HV mains incomers.

This is another major turning point in the development of the new facility, as we head ever closer to energising the site ready for client deployments.


Weekly overview

Massive change has begun in earnest this week, as masses of under floor containment begins to flow into Data Hall 1. This has been flood cabled, and the installation team will then move onto the main containment runs which allow for cabling between the upstairs data halls and the downstairs LV rooms.

We’ve also got major civils happening both on-site and in the local area, as our incomers make their way to us, along with our first dark fibre links.

Containment
The underfloor containment for the commando whips being installed in Data Hall 1
Containment
A closer look at the containment runs which flank Pod 1 in Data Hall 1
Containment
This containment will carry the A and B feed whips from each side of the in-room power distribution units, along with some supplementary supplies for M&E equipment
Containment
A view across Data Hall 1, from the eventual position of Pod 2, looking at Pod 1 as it floats above the containment being installed underneath
Containment
Here we see the containment being installed around the central supporting platform for Pod 2, or whichever additional pod layouts are required in Data Hall 1
Containment
Containment beyond Data Hall 1 spans the entire building, including the risers, one of which is pictured here with preparative works underway for cable ladder installation
Electrical
The electrical boards have been installed on their custom plinths in Data Hall 1, on both A and B sides – the A side boards are pictured here, along with the M&E board which has an integral ATS to handle twin incomers from the LV rooms
Electrical
A closer look at the underside of the A-side boards, with the cable entry and exit pathway for A incomers and A-side whips
Electrical
These are the B-side power distribution units, which are installed on the opposite side of Data Hall 1
Electrical
While Data Hall 2 will likely remain as empty white space for a little while, we’re pre-installing the electrical infrastructure, including the in-room PDUs as seen here
Electrical
The plinths and bases are installed on the other side of Data Hall 2 here, with the PDUs being prepared for installation atop these shortly
Electrical
The Data Hall 2 PDUs being prepared ahead of installation on the associated plinths and expansion enclosures
Electrical
The first drum of cable on axle stands in Data Hall 1 for commando whips – this is the first run of over 2km of power cabling for this room alone
Electrical
The first rack commando feeds being loose laid onto the basket
Electrical
Some of the whips, because of the careful consideration of runs to avoid parallel runs and cross-over, are extremely long, and as such our corridors have proven helpful for preparation ahead of pulling in
HV Roadworks
Our HV supply is making its way to us from the relevant substations, with a view of the route works on the surrounding roads on the trading estate
HV Roadworks
Another view of the road works, which have spanned the entire length of Cody Road for delivery to us
HV Roadworks
The works have required careful closure control across considerable distances, as have the civil works for our fibre routes
LV
Our LV rooms are prepped and ready for the boards to arrive, which are landing with us early next week – an exciting milestone
Trades Canteen
Data Hall 4 has been doubling up as a trades canteen and plans overview space while various contractors are on-site
Transformer
The first of the ground works equipment arriving on-site, ready to begin digging in our transformer base
Transformer
During the dig, we had a daily collection of outcoming ground materials to keep the working area clear
Transformer
The shutter forms in place for the pour of the highly complex, reinforced transformer base
Transformer
The pour of the base will be undertaken early next week, ahead of the transformer enclosure arriving shortly thereafter
VESDA
Additional works have been underway in other areas, including final containment runs for the LV room VESDA and fire systems – these continue on into the risers, which are having twin-run trunking installed to handle all fire systems in these rooms
VESDA
The steel conduit bending station as setup in Data Hall 4, which has allowed for the smooth bend radius forming of conduit which needs to change directions

As you can see, things are changing rapidly now that the main electrical works are underway. Next week, we’re expecting to see completion on the in-room work for Data Hall 1, meaning containment works will begin in the LV rooms, and all of the runs in between.

We’re now eagerly awaiting the arrival of the large LV switchboards, which will be an exciting development for us. It’s a part of the project that we’ve been excited to see take shape, and an area of enormous financial investment.

While the base of the transformer may appear to be a somewhat simple hole in the ground, and a straightforward concrete pour, in reality it’s anything but. The internal rebar structure has been welded on-site, and is bonded directly to very deep earthing rods to ensure safety during operation.

Once Data Hall 1 is phase one complete on commando cabling, our team will move in to complete some additional items, including M&E feeds for cooling, VESDA pipework, ODF installation for network and fibre, and other related containment and cabling pieces.


What else has been happening?

We’ve extended our reach in Telehouse through to North 2.

As part of a private client deployment, we’ve rolled out two new racks in North 2, and as part of this we’ve now got diverse 10Gbps feeds from our network delivered into the building, from our Supernode in North, and our core node in HEX / LD8.

We’re excited to see our network continue to grow, reaching new facilities as our transit proposition helps business grow their presence online.


What’s next?

We’ve really just got lots of the same coming up; containment and cabling for the most part, throughout the facility, as we head towards energisation.

This will include works on the HV and transformer side, and will lead onto various M&E works including cooling power, data, control, and further leading on from that, VESDA air sample pipework.