The pace has certainly picked up now, as we push towards phase one completion at London East.
This acute focus has left little time for the blog, and as broad strokes visual change has slowed down at this point, we’ve put together a four week short summary of the last month on-site at NLE.
Weekly overview
Phase one completion will see the facility ready to take its first clients, which is an enormous milestone for us here at Netwise.
There will still be some ongoing works beyond phase one, which will include things like our customer lounge and some other secondary niceties, as primary focus at this point is getting the technical spaces completed and ready to receive live client systems.
Looking slightly further ahead still, phase two will involve the preparation and roll-out of further technical space, making use of the other data halls, which given the amount of work put in ahead of time for this will certainly come to fruition much more quickly. This is expected in 2022, and will be based on a dynamic roll-out schedule, driven largely by demand.
The largest area of progress in this instalment of the build blog has been centred around air conditioning. This is not our primary cooling source in the technical spaces at NLE, with that role falling to our extremely efficient adiabatic systems, however traditional AC does still play a crucial role in both supplementary cooling in critical spaces, and comfort cooling in customer and staff areas.
As you can see, NLE is still an extremely busy site, with lots of finishing stage work underway. Yet so much more of the work being undertaken at this point is not of a visual nature; commissioning of power systems, access control, network setup, CCTV etc, these are all tasks with little to photograph. However progress across all of these areas will be relayed when suitable.
We’re certainly entering into an exciting period of the build, as major systems begin to see energisation for the first time.
What’s next?
More of the same as we head towards phase one end-out. Keep your eyes peeled for the next instalment of the blog, which will show much of the major infrastructure being onlined for the first time!
Now that raised floors have started to go back down, and termination of cabling is essentially complete, impactful visual change has slowed down slightly, however progress is still pushing forwards at great pace.
We’ve been preparing for some of the final trades to land on site to end-out phase one, which will include the CRAC pipework team and the wall fabrication team from earlier in the project, who will be finishing off some of the final cooling system segregation now that the fans are installed.
Weekly overview
Much of the change this time centres around supplementary cooling, VESDA / fire panels, and data cabling for things such as CCTV, access control and monitoring / system control.
We’re now very much in the end-out phase of the project at this point, which means that various elements that until now were operating separately are coming together quickly.
For example, our evaporative cooling units are now connected back to both their power delivery and control systems, meaning that they will soon be ready for their first spin up and test. This is the same for a number of the core systems which make up the infrastructure of the facility.
We’re getting to the point at which photographing visual change is likely to slow down somewhat, as we move onto more detailed work such as the interconnection of critical systems, and the onlining of various electrical elements including CCTV and door access control.
Excitement is starting to build as the many months of extremely hard work from all those involved begins to show its final fruits, which will become all the more exciting as we start to see systems roar into life.
What’s next?
While build and installation works will continue in a few final areas – such as CRAC pipework, final airflow containment for extraction in Data Hall 1, and the end stages of general system containment – we are now also in a position to begin the early-stage commissioning process.
We are entering an exciting phase of the project, as things finally begin to slot back into place after a good few months of ordered chaos; a necessary evil associated with the extensive electrical work required to take the building from completed shell to functioning data centre.
Over the next few weeks, we expect to see the site visually return to a state of completion (for phase one), at which point the site will be onlined, and commissioning of critical systems will begin in earnest.
We have more exciting progress to share in this instalment of the Build Blog, as cabling continues to run into the facility at pace.
This progress has been seen across the board, from the largest runs out to external connection points, right down to the smallest termination points inside of the Data Hall PDUs.
Weekly overview
In the last two weeks, we’ve doubled the labour force involved in the electrical side of the project, adding a dedicated cable gang to the on-site trades to help push through the final cable runs, most of which are very substantial armoured cables.
This has seen the vast majority of the on-site cable drums emptied and returned to the vendor, as the cables now lay in place, with termination well underway across the board.
We also have a dedicated jointer on-site, who is heading up much of the largest termination activity, such as inside the generator canopies.
This has been a fantastic fortnight for project development, with tremendous progress on the cabling side of things.
We’ve been very excited to see all of the cabling begin to disappear under the floor and into the risers, ready for termination and testing. We’re also very excited to see some additional visual elements installed, such as the bright red VESDA air sampling pipework.
What’s next?
We will continue with progress on all things electrical. As cable pulling nears completion, focus will shift more completely onto termination, along with supplementary power installations, including small scale non-critical power delivery to things like cleaner’s sockets.
Beyond this, the VESDA pipework installations will continue, and with the arrival of additional cabling for things such as the CREC control and monitoring system, this will also begin to take shape.
Focus on the Build Blog this time around has been firmly on progress with cabling and containment, which continues to develop across the entire site.
A hefty quantity of the largest internal cabling is now all in place, totalling around 8 tonnes. This will now be terminated, along with a host of smaller internal cabling, while additional large external cabling is run in thereafter, as we head ever closer to energisation at London East.
Weekly overview
We’ll get straight into the photos again this time around, as we take a look at cabling and containment developments on-site at NLE.
As you can see, the main focus here has been on continued progression with cabling and containment, which will continue into the next instalment of the Build Blog.
As always, other works have of course been underway, both in the development of London East, and elsewhere across our ever-growing operation, however we’re keeping this post concise and on topic.
What’s next?
As with the previous ‘what’s next?’ update, we’re looking at more of the same over the next few weeks. We have a vast amount of cabling and termination to undertake, which we hope to see nearing completion by the time we next post to the Build Blog.
We’ll also be moving onto further work on fire and VESDA systems, and will be moving ahead with commissioning on cooling systems, as well as continued work on power, such as the roll out of ‘small power infrastructure’ (supplementary building-wide power sockets for cleaning equipment etc).
Vast changes again this time, as the electrical works push on at pace both inside and outside of the new facility.
While visually the site now appears a little less finished than before, with masses of flooring taken up to accommodate the newly installed containment and cabling, from a more wholistic view point, things are pushing forwards in a big way at the moment.
Weekly overview
The pace of work and progress on-site has certainly been turned up a gear, as multiple trades now work together on various aspects of the facility’s power systems, alongside work on other related areas to maintain solid progression throughout.
We have a lot of photos to present this time around, so rather than spending too much time on the introduction, we’ll let them do the talking.
As you can see, it’s been a busy few weeks on-site here at NLE.
Things are certainly ramping up as we move into the closing stages of the opening phase of the project, which will allow our first clients to install kit into Data Hall 1.
It’s certainly a rather intense time to be a part of the NLE project, as multiple trades push on with various aspects of the build in tandem, ultimately taking us towards the finish line at pace, and in line with expectations on our phase one launch.
What’s next?
For the time being, much of the same. Progress will continue on electrical over the coming weeks, and we will also be pushing ahead with other areas, including the various cooling systems throughout the facility.