With the final elements of the facility wide containment systems now finalised, we can run headlong into the final stage of the project, which will involve running cabling, commissioning the power and network, and final testing. With all being well we are hoping to welcome existing and pre-sale customers into the new site very soon, with absolute finalisation to follow (smaller ancillary works such as signage, finishing touches, etc).
London Central Build Blog – Week 47
London Central Build Blog – Week 46
Again this has been a week of change across various elements of the facility, as we draw near to the stage of initial occupation.

Flow controllers in place for cooler stack supplies, which will be controlled by our building management systems
London Central Build Blog – Week 45
This week saw the first of our generators land on site, which is a massive step forwards for us, and allows for the power side of the build project to begin in earnest after Christmas – essentially the final phase ahead of moving existing clients into the new site.
The arrival of the first generator sets is a big milestone for us as we head towards Christmas for a short period of well earned rest.
Our generators will always run at N+1. When at capacity, we will have 5 identical units inside of our compound, with a new unit added each time additional capacity is required to maintain the level of redundancy that we have specified.
London Central Build Blog – Week 44
This week has again seen dramatic progress as we head towards the final stage of the build, largely in the layout of the data hall ready for initial occupation early next year.

First row of cabinets in the first containment pod being bayed together, including the in-line UPS seen towards the middle

A look at the rear of the first row, with a custom solution for creating a seamless rear door surface despite the UPS being a different depth to the server cabinets