Much progress has been made again this week across many areas of the project, as we head towards our launch.
![Small VESDA unit installed for sampling air in the meet me and electrical intake rooms](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2297-300x225.jpg)
Small VESDA unit installed for sampling air in the meet me and electrical intake rooms
![Power outlets installed for the A side of the core UPS system](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2299-300x225.jpg)
Power outlets installed for the A side of the core UPS system
![Custom made cooling control box installed for backup AC supply in meet me room](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2300-300x225.jpg)
Custom made cooling control box installed for backup AC supply in meet me room
![Conduit run into top of outlets ahead of commissioning](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2309-300x225.jpg)
Conduit run into top of outlets ahead of commissioning
![Testing operation of the backup AC controller](http://blog.netwise.co.uk/wp-content/uploads/2014/01/IMG_2312-300x225.jpg)
Testing operation of the backup AC controller
![Secondary cooling controller being installed for primary cooling from main evaporative system](http://blog.netwise.co.uk/wp-content/uploads/2014/01/IMG_2310-300x225.jpg)
Secondary cooling controller being installed for primary cooling from main evaporative system
![VESDA system being installed in first data hall](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2313-300x225.jpg)
VESDA system being installed in first data hall
![A-side power distribution installed in cold corridor](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2315-300x225.jpg)
A-side power distribution installed in cold corridor
![B-side power distribution installed in cold corridor](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2314-300x225.jpg)
B-side power distribution installation under way in cold corridor
![Supplies in place for first two generators, ahead of finalisation](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2319-300x225.jpg)
Supplies in place for first two generators, ahead of finalisation
![Generator feed breakouts to external compound including custom junction boxes for control cables](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2324-300x225.jpg)
Generator feed breakouts to external compound, including custom junction boxes for control cables
![VESDA pipework installation begins](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2320-300x225.jpg)
VESDA pipework installation begins
![VESDA pipework leading to first containment pod](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2321-300x225.jpg)
VESDA pipework leading to first containment pod
![VESDA pipework reaching the far side of the first data hall](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2322-300x225.jpg)
VESDA pipework reaching the far side of the first data hall
![VESDA pipework backbone which feeds back to the control and analysis unit](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2323-300x225.jpg)
VESDA pipework backbone which feeds back to the control and analysis unit
Next week will see many of the elements completed, along with a primary emphasis on finalising all cable runs ahead of a period of commissioning.
Related