London Central Build Blog – Week 50

Cabling, termination and commissioning continues this week, as we head towards taking the site live very soon.

Power cable reaching the electrical intake room on overhead containment system

Power cable reaching the electrical intake room on overhead containment system

Cable coiled together for one of the generators, ready for taking outside through the cladding onto the cable ladder

Cable coiled together for one of the generators, ready for taking outside through the cladding onto the cable ladder

Cabling pulled through awaiting break out to generators in external compound

Cabling pulled through awaiting break out to generators in external compound

Power cables exiting facility to generator compound

Power cables exiting facility to generator compound

Power cables exiting facility to generator compound

Power cables exiting facility to generator compound

Power cables being tied into containment basket internally

Power cables being tied into containment basket internally

Power cables for one generator set tied into the cable ladder system

Power cables for one generator set tied into the cable ladder system

A look at the cable path down the side of the generator set

A look at the cable path down the side of the generator set

A look at the cable path down the side of the generator set

A look at the cable path down the side of the generator set

A look at the containment frame being fitted above the meet-me room infrastructure

A look at the containment frame being fitted above the meet-me room infrastructure

Meet-me room containment frame in place

Meet-me room containment frame in place

Containment frame complete with basket, ready for livening up any manner of connectivity requirements

Containment frame complete with basket, ready for livening up any manner of connectivity requirements

Backup / failover AC system being fitted into meet-me room

Backup / failover AC system being fitted into meet-me room

Containment for AC feeds to external condenser being fitted

Containment for AC feeds to external condenser being fitted

Copper piping feeds run to external cladding

Copper piping feeds run to external cladding

External pipework and cable containment installed, along with bracket for external condenser

External pipework and cable containment installed, along with bracket for external condenser

External condenser in place ahead of gas and electrical connections being made

External condenser in place ahead of gas and electrical connections being made

External portion of the backup / failover meet-me room AC system completed

External portion of the backup / failover meet-me room AC system completed

Internal portion of the backup / failover meet-me room AC system completed

Internal portion of the backup / failover meet-me room AC system completed