London Central Build Blog – Week 48

With the final elements of the facility wide containment systems now finalised, we can run headlong into the final stage of the project, which will involve running cabling, commissioning the power and network, and final testing. With all being well we are hoping to welcome existing and pre-sale customers into the new site very soon, with absolute finalisation to follow (smaller ancillary works such as signage, finishing touches, etc).

Multi-tiered containment basket running across pod rows

Multi-tiered containment basket running across pod rows

Second pod bridge in place between backbone containment and racks

Second pod bridge in place between backbone containment and racks

Second pod containment bridge in place

Second pod containment bridge in place

A look at the containment system taking shape

A look at the containment system taking shape

Inter-pod containment bridge in place, to allow for maximum cross-connect flexibility

Inter-pod containment bridge in place, to allow for maximum cross-connect flexibility

Power and network bridges between rows in place through cold aisle

Power and network bridges between rows in place through cold aisle

First UPS power cabling being installed

First UPS power cabling being installed

UPS cable bridging through cold aisle for first UPS run

UPS cable bridging through cold aisle for first UPS run

Power cable running into distribution rack, ahead of power management fit out

Power cable running into distribution rack, ahead of power management fit out

Power cabling being tied into containment backbone

Power cabling being tied into containment backbone

Main power cable exit point from primary power riser onto first floor data hall

Main power cable exit point from primary power riser onto first floor data hall

Power cabling to second pod tied into containment bridge

Power cabling to second pod tied into containment bridge

Final networking bridge in place between first pod and main backbone, thus completing the containment system for the first two online pods

Final networking bridge in place between first pod and main backbone, thus completing the containment system for the first two online pods

A look at the scale of the first cable pull - 4 initial cables weighing close to 500kg

A look at the scale of the first cable pull – 4 initial cables weighing close to 500kg

Ground floor rear warehouse flooring taking shape

Ground floor rear warehouse flooring taking shape