Cabling continues this week, along with completion of final routes around the facility for cable runs. Our Emergency Power Off (EPO) system also took shape this week, which is an added safety feature that will allow the site to be blacked out should there be any major issues requiring a total power off (fire, electric shock etc).
London Central Build Blog – Week 52
London Central Build Blog – Week 51
Much progress has been made again this week across many areas of the project, as we head towards our launch.
Next week will see many of the elements completed, along with a primary emphasis on finalising all cable runs ahead of a period of commissioning.
London Central Build Blog – Week 50
Cabling, termination and commissioning continues this week, as we head towards taking the site live very soon.

Cable coiled together for one of the generators, ready for taking outside through the cladding onto the cable ladder
London Central Build Blog – Week 49
Cable pulling and system commissioning is now in full swing here at the London Central facility, which is a very exciting time for our entire team. Things are coming together very quickly now, and the data centre will soon have power and connectivity flowing through it as we head into a testing phase shortly thereafter.

We took delivery of our new forklift this week, which will be employed to move heavy equipment around our campus moving forwards – it will be getting a full respray and livery soon

Final containment bridge in place, linking the first pod with the network backbone which runs across the entire data floor

APC maintenance bypass switch for UPS being fitted with custom fabricated rack ears, for fitment into power distribution rack

Internal generator containment spine along external cladding, ahead of cable exits being cut into the external facade

New fire alarm call points being installed throughout the facility, along with install and commissioning of centralised alarm and VESDA systems