Much progress has been made again this week, with a vast amount of the remaining cable pulls completed ready for extensive commissioning over the next few weeks.
![Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2377-300x225.jpg)
Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers
![Final cable runs wind their way through the building - this shows an access point inside of the staff lounge](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2379-300x225.jpg)
Final cable runs wind their way through the building – this shows an access point inside of the staff lounge
![Riser cover fitted to cable containment on first floor data hall](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2415-300x225.jpg)
Riser cover fitted to cable containment on first floor data hall, as final commissioning is completed on the primary VESDA unit
![Cutting of gland holes in generator power and control termination cabinets in electrical intake room underway](http://blog.netwise.co.uk/wp-content/uploads/2015/02/IMG_2416-300x225.jpg)
Cutting of gland holes in generator power and control termination cabinets in electrical intake room under way
As you can see, we are now very much in the final phase of the project, with primary focus in the coming weeks placed on the electrical intake room, which will allow us to bring the site online.