London Central Build Blog – Week 54

Much progress has been made again this week, with a vast amount of the remaining cable pulls completed ready for extensive commissioning over the next few weeks.

Meet me room Emergency Power Off (EPO) unit in place

Meet me room Emergency Power Off (EPO) unit in place

Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers

Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers

Delivery of further Suprema BioEntry Plus units arrived this week

Delivery of further Suprema BioEntry Plus units arrived this week

Cabling on our custom cooling control units under way

Cabling on our custom cooling control units under way

Final cable runs wind their way through the building - this shows an access point inside of the staff lounge

Final cable runs wind their way through the building – this shows an access point inside of the staff lounge

Riser cover fitted to cable containment on first floor data hall

Riser cover fitted to cable containment on first floor data hall, as final commissioning is completed on the primary VESDA unit

Cutting of gland holes in generator power and control termination cabinets in electrical intake room underway

Cutting of gland holes in generator power and control termination cabinets in electrical intake room under way

As you can see, we are now very much in the final phase of the project, with primary focus in the coming weeks placed on the electrical intake room, which will allow us to bring the site online.