London Central Build Blog – Week 52

Fantastic progress yet again this week, as various elements of the project come together as we continue to head towards making the site ready for initial occupancy.

Power supply for meet me room VESDA being installed

Power supply for meet me room VESDA being installed

Clips for VESDA pipework installed on wall and ceiling grid

Clips for VESDA pipework installed on wall and ceiling grid

VESDA pipework being fitted in meet me room

VESDA pipework being fitted in meet me room

VESDA pipework in first data hall reaching completion

VESDA pipework in first data hall reaching completion

Power for core UPS systems installed

Power for core UPS systems installed

Power for core UPS systems installed

Power for core UPS systems installed

Speedy Fuels delivery - generators now ready for commissioning

Speedy Fuels delivery – generators now ready for commissioning

Our first two generator sets are now fuelled and ready for commissioning in the coming weeks

Our first two generator sets are now fuelled and ready for commissioning in the coming weeks

Power feed for fork lift charging station installed

Power feed for fork lift charging station installed in warehouse / loading bay

Network cabling run in for cooling system control units

Network cabling run in for cooling system control units

Cabling for the future second data hall on the ground floor awaiting their final pull into the meet me room

Cabling for the future second data hall on the ground floor awaiting their final pull into the meet me room

An exclusive look at our custom made APC quarter rack enclosures

An exclusive look at our custom made APC quarter rack enclosures

An exclusive look at our custom made APC quarter rack enclosures

An exclusive look at our custom made APC quarter rack enclosures

Our new BT duct installed on Old Jamaica Road

Our new BT duct installed on Old Jamaica Road