This week has seen works under way in the electrical intake room, as well as other power-related areas throughout the site.

Glands being fitted to the top of the main generator breaker cabinet

A look at some of the copper inside of the main generator breaker cabinet

Here we see the generator / backup supply side of the electrical intake room taking shape

A look at the internals of the generator breaker cabinet, as the first two gen-sets are being terminated

A look at the internals of the generator ATS

Current generator feeds as they enter the breaker cabinet

External facials of the generator control and distribution cabinets reaching completion

A look at progress on internal cabling

BT circuit now live inside of the meet me room