This week has seen works under way in the electrical intake room, as well as other power-related areas throughout the site.
![Glands being fitted to the top of the main generator breaker cabinet](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_0001-300x225.jpg)
Glands being fitted to the top of the main generator breaker cabinet
![A look at some of the copper inside of the main generator breaker cabinet](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_0002-225x300.jpg)
A look at some of the copper inside of the main generator breaker cabinet
![Here we see the generator / backup supply side of the electrical intake room taking shape](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_0003-225x300.jpg)
Here we see the generator / backup supply side of the electrical intake room taking shape
![A look at the internals of the generator breaker cabinet, as the first two gen-sets are terminated](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_0004-225x300.jpg)
A look at the internals of the generator breaker cabinet, as the first two gen-sets are being terminated
![A look at the internals of the generator ATS](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_0005-225x300.jpg)
A look at the internals of the generator ATS
![Current generator feeds as they enter the breaker cabinet](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2417-300x225.jpg)
Current generator feeds as they enter the breaker cabinet
![Generator control and distribution cabinets reaching completion](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2420-300x225.jpg)
External facials of the generator control and distribution cabinets reaching completion
![A look at progress on internal cabling](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2422-300x225.jpg)
A look at progress on internal cabling
![BT circuit now live inside of the meet me room](http://blog.netwise.co.uk/wp-content/uploads/2015/03/IMG_2421-300x225.jpg)
BT circuit now live inside of the meet me room