This week has seen works under way in the electrical intake room, as well as other power-related areas throughout the site.
London Central Build Blog – Week 54
Much progress has been made again this week, with a vast amount of the remaining cable pulls completed ready for extensive commissioning over the next few weeks.

Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers

Final cable runs wind their way through the building – this shows an access point inside of the staff lounge

Riser cover fitted to cable containment on first floor data hall, as final commissioning is completed on the primary VESDA unit

Cutting of gland holes in generator power and control termination cabinets in electrical intake room under way
As you can see, we are now very much in the final phase of the project, with primary focus in the coming weeks placed on the electrical intake room, which will allow us to bring the site online.
London Central Build Blog – Week 53
Cabling continues this week, along with completion of final routes around the facility for cable runs. Our Emergency Power Off (EPO) system also took shape this week, which is an added safety feature that will allow the site to be blacked out should there be any major issues requiring a total power off (fire, electric shock etc).
London Central Build Blog – Week 52
London Central Build Blog – Week 51
Much progress has been made again this week across many areas of the project, as we head towards our launch.
Next week will see many of the elements completed, along with a primary emphasis on finalising all cable runs ahead of a period of commissioning.