The past few weeks have seen lots of time spent on stabilising the migrated estate, so in terms of build progress there isn’t a huge amount to report. That said, there has of course been progress in a number of areas, as our efforts to bring the site to total completion continue.
![Large headway has been made in fitting out the remaining doors with their furniture and door closers](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2680-300x225.jpg)
Large headway has been made in fitting out the remaining doors with their furniture and door closers
![A fourth layer of filtration has been added to the cold corridor, which acts as the first filtration point, catching large particulates on their entry to the building](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2681-300x225.jpg)
A fourth layer of filtration has been added to the cold corridor, which acts as the first filtration point, catching large particulates on their entry to the building