Progress has been made on a number of areas again this week, most notably the installation of our access control systems.
![A look at the completed ceiling, complete with lighting, fire detector and cable entry / exit points](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2722-300x225.jpg)
A look at the completed ceiling, complete with lighting, fire detector and cable entry / exit points
![A look at our cooling stacks with their new bag filters fitted to the exterior of the wet boxes, taking our total number of pre-data hall filtration layers to 4](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2728-300x225.jpg)
A look at our cooling stacks with their new bag filters fitted to the exterior of the wet boxes, taking our total number of pre-data hall filtration layers to 4
![A look at the access control units being installed, in this instance to the first floor data hall entrance](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2729-300x225.jpg)
A look at the access control units being installed, in this instance to the first floor data hall entrance
![A look at the components which make up one side of the customer kitchen / reception entrance, one of the more complex doors to fit out in this facility](http://blog.netwise.co.uk/wp-content/uploads/2015/06/IMG_2736-300x225.jpg)
A look at the components which make up one side of the customer kitchen / reception entrance, one of the more complex doors to fit out in this facility