We are now rapidly approaching readiness for initial occupation, with this week seeing completion of the power commissioning, and the deployment of the core network.

Three of the first four custom power distribution panels having their internal components fitted, ahead of wiring

A look at the 16A and 32A commando sockets fitted to our laser cut and painted doors, ready for fitting onto the panels

A look at the upper internals of the distribution panels with termination completed, with just the connections to the sockets left to complete

A look at the external louvred panels that will allow our dynamic cooling system to ‘breathe’ external air

Our BMS interface in the electrical intake room, which will allow for instant facility status read-outs – there will be many of these around the site