London East Build Blog – Weeks 32 to 34

With the internal shell now complete, and with far fewer trades now on-site until the electrical works begin, we’ve been able to get various supplementary works underway across a number of key areas.

The last few weeks have proved to be an excellent springboard for getting things like access control integration started, with the first doors at NLE now online and interacting with our core systems at NLC.


Weekly overview

While final plans and schedules for the LV and HV electrical works continue, we’ve been able to press ahead on-site with a range of supplementary projects which have helped to drive forward general progress.

We’ve spent time on the main access control elements, which will secure the client entry points to the facility. This includes the frame installation of our turnstile, the integration of the main reception door onto the access control system, and the deployment of our lovely new Boon Edam speed gates.

Speedgates
The first of our three speedgate terminals fixed down to the floor in our entrance foyer, seen against the grey feature wall which runs the length of this area
Speedgates
A view of all three speedgate terminals now in place, which make up one large double-leaf access lane, and one smaller single-leaf pedestrian access lane
Speedgates
Here we see the interconnecting conduit now installed, with flood cabling in place between all three terminals for power, data and fire integration
Speedgates
A look at the custom DIN rail installed at the base of each terminal, to handle incoming and outgoing connections for all cable services
Speedgates
We’re fully integrating these speedgates with our Paxton door entry system, and as such, the two lanes each have a Net2 Plus control board internally mounted
Speedgates
A look at the progressing installation from the top of the access ramp
Speedgates
This view shows the conduit as it pitches up the feature wall for overhead access to service routes above the ceiling line
Frontdoor
Here we see the front door access control systems being installed, which will also house control points for the main compound turnstile
Frontdoor
This 600kg maglock matches those used at NLC, and is the result of a fully custom installation with parts fabricated in-house to achieve the correct mounting position
Frontdoor
Here we see the inside of the front door, as the access hardware begins to reach final state, pending the door exit mushroom button
Frontdoor
The outside of the main entrance, with the newly mounted entry panel on the left to match those found at NLC, along with various pieces of custom door security furniture
Frontdoor
A closer look at the matching door entry panel, which will also feature on the main turnstile as to replicate NLC’s secure entry setup – the colour match is quite impressive, and purely coincidental!
Frontdoor
The door entry control panel boxes seen with their installation nearing completion
Frontdoor
A look at the completed door entry control enclosures and associated power distribution, which now neatly hide many hours of termination work
Envelope
A quick look at some of the now fully-completed door systems, this one showing the entrance to one of our LV power rooms, and the ground floor lift entrance – this is being custom painted to match all other doors soon
Envelope
A view down the length of the ground floor corridor, with the entrance to Data Hall 4 in the foreground, leading on to the entrance to Data Hall 3 – the fully-integrated Paxton readers are visible here, as part of the handle assembly
Hardhat
With hard hat tours starting in early 2021, we’ve been getting the tour PPE kit on-site ready for use by our visitors
Hardhat
We’ve again gone with high-quality Dickies vests, which we’ve used for our engineering hi-vis vests for some time now, along with custom branded black hard hats

Alongside access control works, we’ve also now flood cabled the first data hall with its final lighting cables, which means we can begin to light the data halls with their overhead LED panels for the first time.

We’ve also had trades back on-site over the past few weeks to bring all doors to full completion, which includes the checking of tile stability around the frames, and adjusting all doors for their opening angles and closing speeds. Given the number of door systems installed, this is quite the undertaking.

Though not something pictured, our lift is now operational, and can move between floors. We’re now just waiting on some final integration work to be undertaken, which will bring that particular element of the project to a close.

The custom frame system we’ve had designed for our cooling plant and cold corridors arrived during this time, which we hope to begin installing in the next couple of weeks, on the lead up to Christmas.


What’s next?

Details are now finalised on much of the HV and LV front, meaning we’re close to having that stage of the project begin.

In the lead up to this, we’ll be continuing with lighting, access control, and the chequer plating of all client areas.

Another major job that will be undertaken both now and throughout the electrical installation works will be the integration of our new CREC system. This will include getting the coolers plumbed, powered and interconnected for their control systems, along with the installation of our custom-fabricated containment frame, which will blank off any cooler bays which are presently unoccupied, as well as providing a mounting location for the extraction louvres.

The importance of sustainable data centres in London

The internet is used by more than 4 billion people worldwide.

The UK makes up for 60.3 million of these internet users, Great Britain bringing in 46.6 million as of 2016. That’s 92.6 per cent of our nation’s population; and growing.

We in London spend large chunks of our days on the internet, amplified further at the moment by the current COVID-19 restrictions. Whether it’s viewing our feeds on social media, sending work emails, video conference calls, uploading files, sending messages, downloading information, or simply surfing the web, data centres in London are working rigorously to transfer this information from one sector to the next.

Simply put, it’s fair to say that the majority rely extremely heavily on the internet.

We spend a lot of our lives online, and yet the environmental impact caused by our heavy use of the internet is commonly overlooked.

As we increasingly become more digitalised, the internet continues to play a key role in our lives. As such, there comes a time in which we must address the effect the internet has on the environment. There’s no doubt the internet requires a massive amount of energy to operate, so how can we remedy the effects of our carbon footprint? Where do we begin to address these effects?

It all starts at the data centre.


The internet in tangible form – data centres

It’s easy to fall short in understanding just how the internet requires so much energy due to its “invisible” nature. Nevertheless, there are four main areas that drive the digital world; devices, networks, manufacturing, and data centres. The latter being of tangible form and largely contributing to the egregious energy consumption the internet partakes in. 

Think of a data centre as you would a modern-day factory. They are physical facilities that function as large scale communication hubs and centralised computing facilities. These buildings can essentially be viewed as a collection of specialised computers, known as servers. These computers house a wide variety of things, including databases, websites, communication platforms, AI systems, and much more.

In short, data centres are the internet, materialized. They are the closest thing to the internet in physical form and they are one of two main components of the internet that contribute to having a very notable impact on the environment.


Why do data centres consume so much energy?

Think about data centres as you would your own personal computer. Your computer generates heat when in use. This heat is that energy. You know you’re generating a lot of heat when you hear the fans in your computer start to hum. Now imagine this but on a much, much larger scale. Millions of these specialised computers, known as servers, which are often many times more powerful (and power hungry) than your average home computer.

As a result, more than 4 billion individuals indirectly contribute to the IT sector’s energy consumption, which equates to 10 per cent of all energy consumption worldwide. This number is on continuously on the rise as we become more and more digital. It’s predicted that this number could increase to as much as 33 per cent by 2025.

Because of your indirect contribution to this consumption through use of your various digital services and platforms, a fair part of your carbon footprint comes from the operation of data centres. As an end-user, you have no input regarding what kind of energy your indirect data centre operators are purchasing and using. 

So, what is there to do?


The future of internet sustainability 

Thankfully, we’ve too found ourselves in a collective cultural transition into renewable energy and the IT sector has followed suit – in fact, it’s lead the way in pervasive use of renewables. As society has shifted to having more concern for our impact on the environment, corporations have also looked to shift towards sustainable energy.

Data centre operators have been racing towards a completely renewable internet for quite some time. Not only is this change great for the environment, it’s also advantageous from a financial standpoint; sustainable energy is consistent in its nature, and therefore holds great value for companies and investors.

‘Going green’ has become standard in terms of what business are looking for when choosing a data centre partner. Because of this, modern internet companies are now actively pursuing green, more sustainable providers to partner with on a long-term basis. Finding a truly sustainable data centre operator in the centre of a city like London can be tough, but they are


Sustainable data centres In London

We at Netwise want to be a part of the solution, in creating sustainable data centres to house critical business systems here in London. We do so currently as the UK’s leading colocation and data centre service provider, delivering end-user content on a global scale. We’ve been able to put together two sustainable data centres right in the heart of London, with our third centre in London East coming in 2021.

Our London Central facility uses 100 per cent renewable energy. We aim to be a part of the solution. We aim to keep London sustainable and set the standard for corporations to follow. This enables the reduction of carbon footprint concerns for you as an end-user, as we lead the way in reducing data centre power consumption in the capital.

London East is the next chapter in our journey. We’re taking note from our London Central facility, amping up to a facility with 256 racks, and of course remaining 100 per cent renewable in our purchase and consumption of energy. 

Our mission is to provide world-class data centre facilities in enviable locations, while always operating on 100 per cent renewable energy. Our data centres are some of the greenest in all of Europe, powered by energy sourced from the wind, sun, and sea, ensuring you enjoy services with a reduced carbon footprint.

So we ask you, why not come and be part of the solution? Feel free to get in touch or schedule a tour at any of our facilities, or check out our blog for more detail on our upcoming data centre, London East.

London deserves this. London deserves sustainable systems to be put in place and so does the world. We cannot fall short and disregard the invisible nature of the internet. Together, let’s be part of the solution and never the problem.

London East Build Blog – Weeks 30 and 31

We’re very excited to show you another transformative fortnight of works on-site at NLE, as the internal envelope of our new data centre reaches full completion.

We’re now looking at a complete internal shell, giving us the physical structure we need to begin installing equipment and deploying electrical services.


Weekly overview

As you can see from the range of shots below, we’re now at a major turning point in this project. The internal shell has now been signed off as complete (with one final pass for minor snags pending), meaning we have the final internal structure of the building set and ready for the next phase of works that will take us into early 2021.

The facility is now presented with immaculate, high specification white spaces for all technical deployments, as well as our usual top tier front of house amenities, something our clients continue to take great advantage of at our London Central data centre.

Floor
A look at the flooring in Data Hall 3 as it moves across the space, towards completion
Floor
The floor reaching completion in Data Hall 4, as it hits the door aperture ahead of the door kit being installed
Floor
A view of the floor in Data Hall 3 as it encloses the mezzanine supports, which will have tiles cut in to fully wrap around
Floor
The completed raised access floor in the ground floor corridor area, with one of the door kits installed for entry to Data Hall 4
Floor
The floor being cut in around the access stair case in the atrium on the ground floor
Floor
The ground floor access atrium, showing a completed door system alongside an awaiting aperture, as well as the differing floor layouts across each space, so as to reflect the ceiling grids in each space exactly – thresholds will be installed between rooms
Doors
A look at the doors installed in the Build Room and Customer Breakout Area, showing a solid twin-leaf riser door set on the left, and the main room access door on the right, ajar
Doors
An open door set for entry into Data Hall 3 – all data halls have the same double-door setup for easy access with equipment
Doors
A look down the first floor corridor, with all door sets now installed
Doors
A set of solid twin-leaf doors for entry into one of our LV rooms, with a view out onto the ground floor loading platform in the warehouse area – our fully-integrated Paxton door access systems can also be seen here, as part of the door handle assembly
Envelope
A final pass of envelope finishing works are now also underway, with this shot showing a new custom finishing trim installed to cover the ground-to-first floor joining seam in our double-height atrium
Equipment
Here we see a pair of UPS’s and their associated battery enclosures, along with a set of core network racks, which are being held in one of our LV rooms – with temporary dust bags / wraps still in place
Equipment
This is an exciting shot, showing the first client enclosures placed in Data Hall 1, which gives an idea of real-world placement for the first time
Equipment
This angle shows placement of the first vent tiles, which will supply cool air from the underfloor plenum to the first pod of racks in Data Hall 1
Equipment
This contextual angle shows the placed racks in relation to the cooling plant, now sited at the rear of Data Hall 1, backing onto the cold corridor
Coolers
Here we see four CRECs in place on their custom plinths in Data Hall 1, which will cool the opening phase of this space, to be followed by a further four units when required
Coolers
This is a closer look at the next-generation CREC system that we’re installing at NLE, ahead of a fully custom blanking system for the currently empty cooler bays, which will also house our custom extraction system
Exterior
A night time exterior shot, taken from the front compound, looking towards our warehouse and loading bay

As you can see in some of the shots of our new doors above, we’re using a fully integrated Paxton system, with the card readers forming part of the handle assembly. This not only keeps our facility access installation as neat and as clean as possible, but will also massively improve the time to onlining the system, as these readers operate wirelessly.

We’ve also been working on some addition access infrastructure, including our main entrance turnstile, and the pedestrian access gates which lead from reception into the technical side of the facility; more on this next time.

All of our lighting cable specifications are now with our manufacturer, who are going to be assembling these for us for compatibility with our Klik system. These are all being made to length, using the specialist Klik hardware, which will enable rapid installation to the overhead grid once it all arrives on-site. This will allow us to light all rooms using the overhead LED panels, and allow for the removal of all temporary site lighting.

We’re incredibly excited to have reached this point, as we now begin what will be the most critical phase of technical works – preparing to properly energise the facility. This is still a little way off of course, however we are now moving into the set of works that will enable this to happen.


What else has been happening?

After a lengthy wait while we got everything just right, we’re now also in a position to tease our new van, which will be the first of our new fleet – aptly named ‘001’.

Van
The side of our van features both our main logo, as well as an oversized matt finish logomark as an abstract background
Van
The rear of the van features a full Chapter 8 chevron kit, as well as more detailing on the door panels – amber light bar still to follow

This, coupled with our custom flight cases, makes inter-facility migrations and new deployments an absolute breeze.

Since our last instalment of the build blog, we’ve also seen new restrictions come into play with regards to the national response to COVID-19. We are of course following these guidelines closely, as we did during the first set of restrictions earlier this year, and will continue to do so.

As a result, we’ve now implemented Test and Trace QR codes at both of our sites, which should be used during normal check in procedures. This helps us to keep everyone safe, and to keep our facilities running without a hitch 24×7, as your businesses rely more heavily than ever before on remote services held within data centres.


What’s next?

With the envelope now complete, we will be moving onto electrical works in the very near future. This includes both internal LV work, and external HV work.

On the lead up to this next phase beginning, we will be undertaking a wide range of tasks to bring other aspects of the project either to completion, or to a stage that makes their completion post-electrical works much more straight forward.

Do you need a colocation centre to store your business data?

Every year, businesses collectively spend trillions of dollars on IT products and services worldwide. In fact, the global forecast for the sector reached $3.46 trillion for this year, which is quite a staggering figure.

All over the world, businesses have to make the right decisions in IT management every year. So how can you make the correct cost-effective moves that will truly protect your business?

Most businesses have basic IT needs such as affordable server space and server hardware.

If you’re looking for more in-depth options to manage your business data, here’s how and why a colocation centre might be the best solution for your organisation.


What are colocation centres?

Colocation centres, or “co-lo” data centres, contain enterprise data servers at a remote location away from your own business premises. This is a purpose-built facility designed specifically to house business data systems and infrastructure.

Your own IT technicians are then able to visit the site for any maintenance or updates, or use the facility operators in-house technical team to assist you remotely.


The transfer process

Your service provider may supply you with the physical server hardware, or if you already have hardware in place, you can choose from a variety of service packages for the space you need.

To find how much infrastructure you require, you will need to consider a variety of factors, including the power requirements for each of your servers. Your provider can help you understand what specification service you’d need to support your systems.

During this process, you should evaluate how much space and resources you need, both now and in the future. You may also want to take this opportunity to immediately upscale or downscale, since you’re now entering into the process of bolstering your technical capacity. 


Common issues in business data management

For many businesses, server space is a limited commodity on-premise. This is especially true for small businesses that typically have smaller operations.

IT resources simply grow in proportion to the scale of large businesses. No matter how much building capacity your business has now, more data in the future tends to mean more space will be required.

Physical space is just one of the issues that many businesses run into when growing their systems. Overall costs for data solutions can grossly overtax a business’s financial resources. 

Colocation centres are uniquely designed to hit both of these major pain points for business.

In general, a colocation data centre helps businesses centralise their data management and scale the space to their needs. This offers more flexibility, reliability, and predictability to help you achieve your operational priorities. 


Maintenance and flexibility

Colocation data centres often function like managed IT services. Because of this, data service providers can conduct regular maintenance on your behalf. This can be a big cost saver, and reduces stress on internal technical resources that can spend more time on core business functions. This also reduces the in-house personnel required to perform maintenance.

However, you also have the option to manage your own hardware maintenance through your internal IT department if you choose. 


Reliability

Choosing to make use of an outsourced colocation service provider will always offer you increased security and reliability over going in-house.

Colocation server hosting can be an alternative to cloud storage. Many organisations that made the leap to cloud services when they began taking hold a few years ago are now moving back to physical colocation services. This is because they offer greater value for money, decentralise the control of data from the large US cloud service operators, and allow for far easier compliance when it comes to data domicile and security.

Being able to point to your own server hardware, and make physical changes to it, has major operational advantages.


Predictable expenses 

Operating costs for data management can become expensive over time. When businesses choose to manage their own IT needs the expenses typically include:

  • Electricity to power servers
  • Maintenance and equipment
  • Security
  • Data recovery
  • General overhead costs

Fortunately, you can reduce these expenses when you choose a colocation data centre. One of the best advantages to outsourcing your IT management is that providers offer services at predictable, contracted rates. 


Breaking down monthly costs

For example, a proper colocation plan will show you exactly how much space your services will occupy. These spaces are typically measured in “rack units,” also labelled as a “U.” Units will be the first expense in your data management plan, usually coming with a monthly rate for the space.

There are also predictable monthly rates for power flowing to your servers and your network bandwidth. 

Some providers may also offer additional consulting or hardware resources that may be included in your service free of charge. However, some may come at additional cost. 

At any rate, the necessary expenses for colocation data centres are largely predictable and simplified. This allows you to anticipate the costs by tailoring your service to the specific needs of your business.

Unlike traditional IT management, you don’t have to worry about surprise costs. You simply pay for exactly what you need.


Find better business data solutions

The best advantage to colocation data centres is the fact that you can customize your service to the needs of your business. 

Whatever your data management goals are, we’re here to help you achieve them with colocation solutions.

If you’d like to discuss your business data solutions, please get in touch with us by email, chat, or phone. We have some of the top award-winning locations in London to provide the safest environment for your data. 

London East Build Blog – Weeks 27 to 29

We have three more weeks of fantastic progress on-site at NLE to report, as we rapidly approach completion of the internal envelope.

We’ve seen dramatic changes across the entire facility, as the raised access floor begins to be installed throughout the building, supplemented by ongoing works across a wide range of areas.


Weekly overview

We’re now beginning to see the finished floor surface in the technical spaces for the first time, following the top surface leak protection coating which has been applied to the first floor mezzanine structure.

Aside from the hanging of the internal doors and some cooling plant integration to the rear of each hall, the data halls are now essentially complete, ahead of the first items of equipment rolling into place next month.

Containment
Klik box, conduit and bulkhead installations have now begun across the entire facility
Envelope
The entrance to the technical side of the facility has now had its aperture cut in, which takes visitors into the double-height atrium
Envelope
A look directly up as you head through into the double-height atrium
Envelope
Let there be light: the atrium was the first area to have all overhead LEDs lit up for the first time
Lift Wall
The lift shaft wall has now been clad in MDF, which will serve as a backing surface for our double height green wall
Another view of the newly clad lift shaft wall, including some of the finishing trims
Envelope
The first floor access corridor was the second space to have its overhead LED panels lit up
Envelope
The protective leak coating is seen in place here, now covering the entire first floor, with some additional Correx protection in place as raised access floor materials begin to land in each first floor room
Envelope
A look at the lift shaft assembly and access door in the first floor atrium
Envelope
The lift base on the ground floor has now been coated in the same hard wearing epoxy coating as laid on the first floor
Floor
Raised access flooring materials landing in each room on-site
Floor
Raised access flooring materials landing in each room on-site
Floor
Raised access flooring materials landing in each room on-site
Floor
Works begin in Data Hall 1 with respect to the raised access floor system
Floor
Works begin in Data Hall 1 with respect to the raised access floor system
Floor
A look at some of the pedestals as they begin to be unpacked and prepared for installation
Floor
The raised access floor begins to take shape in Data Hall 1
Floor
The raised floor taking shape in Data Hall 1
Floor
The finished floor height as seen in the upstairs landing and atrium area, now finished to the lift door
Floor
The finished floor in the first floor corridor now meeting the floor in Data Hall 1, awaiting the installed door frame and doors
Floor
A look along the first floor corridor, with the raised floor now in place, with finishing works still underway
Floor
The floor surface now complete in Data Hall 2

Alongside the mezzanine floor surface protection paint, which you can see above, we’ve also completely silicone sealed each room to complete the leak protection in each hall. The cold corridors in each hall will also have a full vinyl tank installed, as the areas which house the CREC units themselves.

We’ve begun lighting the facility with the final overhead LED panels, by temporarily wiring up each of the newly installed Klik boxes. The Klik system allows for rapid installation, along with enhanced control and functionality, including emergency lighting and PIR sensors.

Emergency exit pathways have begun to become more clearly visible in their final guise, with the installation of the emergency LED bulkheads that will light the way to the nearest exit once the facility is open to clients.

Quite a considerable amount of time over the past couple of weeks has been spent in the movement of materials from ingress to final point of use, as the second container of raised access flooring materials arrived with us (not photographed this time around). This has enabled the on-site trades to continue to work at pace as we approach finalisation on the internal envelope.


What’s next?

Works on the floors and access doors will continue into the beginning of November, along with some final finishing trims, which will take the envelope to completion.

The doors have already begun to go in, however we’re saving those shots for the next instalment of the blog, to give a clearer picture of the finished envelope.

Next time around, we’ll also be able to show the completed emergency exit gantry which is now installed at the rear of the facility, which gives a new emergency exit pathway to the rear of the first floor.

Our van is now also complete, but again we’re going to wait for a final detail on that before showing photos – so watch this space!