London Central Build Blog – Week 61 & 62

This next period of work has seen the cooling system reach completion, and final works start on the data hall side of the power commissioning.

A look at the wiring of a supply fan inside one of our custom cooling stacks

A look at the wiring of a supply fan inside one of our custom cooling stacks

The completed internals of a cooling stack control unit

The completed internals of a cooling stack control unit

A completed cooling stack control unit with all covers fitted, ready for operation

A completed cooling stack control unit with all covers fitted, ready for operation

Completed A-side cooling power distribution board

Completed A-side cooling power distribution board, ahead of additional stacks being added modularly in the future

A look inside the now fully commissioned electrical intake room, ahead of future additions when needed

A look inside the now fully commissioned electrical intake room, ahead of future additions when needed

Completed termination on site-wide networking, with a temporary patch visible to liven up our front door access control until proper patching begins shortly

Completed termination on site-wide networking, with a temporary patch visible to liven up our front door access control unit until proper patching begins shortly

A look at in-progress fit out of the custom cooling stack control cabling as it enters the main containment backbone before heading back to the control units

A look at in-progress fit out of the custom cooling stack control cabling as it enters the main containment backbone before heading back to the control units

A closer look at one of the louvred panel actuators

A closer look at one of the louvred panel actuators

One of the water supply actuators with cabling run back to the control unit

One of the water supply actuators with cabling run back to the control unit

One of the multiple environmental sensors fitted - in this case an extract air temperature sensor

One of the multiple environmental sensors fitted – in this case an extract air temperature sensor

A look at a wired extract fan inside of its custom duct work

A look at a wired extract fan inside of its custom duct work

A completed extract fan, safety grill and sensor assembly - more of these will be added modularly as additional stacks are introduced

A completed extract fan, safety grill and sensor assembly – more of these will be added modularly as additional stacks are introduced

Duct access hatch frame fitted for access to stack supply fans

Duct access hatch frame fitted for access to stack supply fans

Ceiling void recirculation ducting installed to feed recirculation chamber, which helps to regulate air temperatures inside of the facility in the winter

Ceiling void recirculation ducting installed to feed recirculation chamber, which helps to regulate air temperatures inside of the facility in the winter

Flexible duct work to link ceiling grills with the recirculation chambers

Flexible duct work to link ceiling grills with the recirculation chambers

3-stage high-pressure sealant applied to all duct work

3-stage high-pressure sealant applied to all duct work

Supply-side louvred panels fitted to cold corridor for external air supply

Supply-side louvred panels fitted to cold corridor for external air supply

Custom modifications made to APC Maintenance Bypass Modules for our UPS systems

Custom modifications made to APC Maintenance Bypass Modules for our UPS systems

One of the modified bypass switches mounted in one of the distribution racks

One of the modified bypass switches mounted in one of the distribution racks

Inlet / outlet glands fitted to UPS panels, including red EPO gland and smaller control/comms cable gland

Inlet / outlet glands fitted to UPS panels, including red EPO gland and smaller control/comms cable gland

Commissioning works in progress on the UPS systems

Commissioning works in progress on the UPS systems

London Central Build Blog – Week 56 to 60

Major advancements have been made this week on the generator and UPS systems, which brings us ever closer to having clients online at the new facility.

The past few weeks have been spent finalising the electrical intake room, which has allowed us to commission most of the power-side systems (generators etc), as well as re-energising the facility in its final state, ready for initial occupation. As such, our office has been offline, which has meant no updates to the blog (other administrative jobs took precedent while under limited access).

This post contains a large number of images from works undertaken over the past 3/4 weeks.

Internals of the generator-side control units reaching completion

Internals of the generator-side control units reaching completion

Internals of the generator-side power distribution with earthing in place

Internals of the generator-side power distribution with earthing in place

Internals of the generator-side power distribution reaching completion

Internals of the generator-side power distribution reaching completion

Custom control cable junction boxes for generators reaching completion

Custom control cable junction boxes for generators reaching completion

Custom control cable junction boxes for generators reaching completion

Custom control cable junction boxes for generators reaching completion

UPS battery modules containing their brand new cells fitted and on the data hall floor, ready to fill out to first 3 UPS's

UPS battery modules containing their brand new cells fitted and on the data hall floor, ready to fill out to first 3 UPS’s

Legacy electrical systems being removed ahead of total re-distribution and commissioning

Legacy electrical systems being removed ahead of total re-distribution and commissioning

Intake room wall being re-clad ahead of fit-out, much alike the opposite wall which contains the generator control and distribution systems

Intake room wall being re-clad ahead of fit-out, much alike the opposite wall which contains the generator control and distribution systems

First of our new main distribution panels fitted -which will be the B side - along with our custom monitoring system flanking either side

First of our new main distribution panels fitted -which will be the B side – along with our custom monitoring system flanking either side

A look at the monitoring which runs either side of the main power distribution panels

A look at the monitoring which runs either side of the main power distribution panels

A closer look at our power monitoring system, which will total 24 screens when completed on both A and B sides

A closer look at our power monitoring system, which will total 24 screens when completed on both A and B sides

New cable containment allows for multiple routes both in and out of the facility distribution cabinets

New cable containment allows for multiple routes both in and out of the facility distribution cabinets

A look at the earthing bars in the intake room, ahead of completion

A look at the earthing bars in the intake room, ahead of completion

Progression as earthing in the facility runs back to the earthing bars here

Progression as earthing in the facility runs back to the earthing bars here

Facility power distribution having the various breakers fitted

Facility power distribution having the various breakers fitted

Progress shot as the facility distribution panels are wired

Progress shot as the facility distribution panels are wired

The completed facility power distribution panel (A side), which powers facility-wide systems such as lighting and sockets

The completed facility power distribution panel (A side), which powers facility-wide systems such as lighting and sockets

The B-side main distribution panel fitted with its breakers, which feed the UPS systems on the data hall

The B-side main distribution panel fitted with its breakers, which feed the UPS systems on the data hall and at the core

Distribution panels for the facility-wide systems completed in the centre here, ahead of the A-side primary panel being installed

Distribution panels for the facility-wide systems completed in the centre here, ahead of the A-side primary panel being installed

A-side distribution being installed, along with flanking monitoring columns

A-side distribution being installed, along with flanking monitoring columns

Containment basket fitted, ready to take large input power cables between cabinets

Containment basket fitted, ready to take large input power cables between cabinets

A look at additional cable containment and control above the primary distribution panels, and up the wall to reach the mains incomers

A look at additional cable containment and control above the primary distribution panels, and up the wall to reach the mains incomers

A look at cable runs being installed between the power distribution panels and the B-side of the mains failover system

A look at cable runs being installed between the power distribution panels and the B-side of the mains fail-over system

Stage one cabling complete for power systems feeding first floor data hall

Stage one cabling complete for power systems feeding first floor data hall

Mains output feeds on the B-side supply, which feed into the B-side throughout the site

Mains output feeds on the B-side supply, which feed into the B-side throughout the site

A look at the inlets atop the generator control and distribution cabinets

A look at the inlets atop the generator control and distribution cabinets

A look at the internals of the B-side AMF panel, which has its termination in progress here

A look at the internals of the B-side AMF panel, which has its termination in progress here

The completed internals of the B-side AMF panel

The completed internals of the B-side AMF panel

A look at the primary breakers for the generator supplies

A look at the primary breakers for the generator supplies

The AMF panel control unit powered and ready for configuring

The AMF panel control unit powered and ready for configuring

From here on out, updates will be less based on weeks, and more on tasks, as we push to get the site ready for initial occupancy.

London Central Build Blog – Week 55

This week has seen works under way in the electrical intake room, as well as other power-related areas throughout the site.

Glands being fitted to the top of the main generator breaker cabinet

Glands being fitted to the top of the main generator breaker cabinet

A look at some of the copper inside of the main generator breaker cabinet

A look at some of the copper inside of the main generator breaker cabinet

Here we see the generator / backup supply side of the electrical intake room taking shape

Here we see the generator / backup supply side of the electrical intake room taking shape

A look at the internals of the generator breaker cabinet, as the first two gen-sets are terminated

A look at the internals of the generator breaker cabinet, as the first two gen-sets are being terminated

A look at the internals of the generator ATS

A look at the internals of the generator ATS

Current generator feeds as they enter the breaker cabinet

Current generator feeds as they enter the breaker cabinet

Generator control and distribution cabinets reaching completion

External facials of the generator control and distribution cabinets reaching completion

A look at progress on internal cabling

A look at progress on internal cabling

BT circuit now live inside of the meet me room

BT circuit now live inside of the meet me room

London Central Build Blog – Week 54

Much progress has been made again this week, with a vast amount of the remaining cable pulls completed ready for extensive commissioning over the next few weeks.

Meet me room Emergency Power Off (EPO) unit in place

Meet me room Emergency Power Off (EPO) unit in place

Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers

Final assembly completed on our custom cooling control units in the meet me room, with new Honeywell cooling controllers

Delivery of further Suprema BioEntry Plus units arrived this week

Delivery of further Suprema BioEntry Plus units arrived this week

Cabling on our custom cooling control units under way

Cabling on our custom cooling control units under way

Final cable runs wind their way through the building - this shows an access point inside of the staff lounge

Final cable runs wind their way through the building – this shows an access point inside of the staff lounge

Riser cover fitted to cable containment on first floor data hall

Riser cover fitted to cable containment on first floor data hall, as final commissioning is completed on the primary VESDA unit

Cutting of gland holes in generator power and control termination cabinets in electrical intake room underway

Cutting of gland holes in generator power and control termination cabinets in electrical intake room under way

As you can see, we are now very much in the final phase of the project, with primary focus in the coming weeks placed on the electrical intake room, which will allow us to bring the site online.

London Central Build Blog – Week 53

Cabling continues this week, along with completion of final routes around the facility for cable runs. Our Emergency Power Off (EPO) system also took shape this week, which is an added safety feature that will allow the site to be blacked out should there be any major issues requiring a total power off (fire, electric shock etc).

Preparations for network riser between ground floor and first floor

Preparations for network riser between ground floor and first floor

First floor side of network riser completed, awaiting basket protection lid

First floor side of network riser completed, awaiting basket protection lid

Cable run holes in meet me room, which feed out to both data floors

Cable run holes in meet me room, which feed out to both data floors

Cable run holes in lift shaft, ahead of flexible conduit connections

Cable run holes in lift shaft, ahead of flexible conduit connections

Emergency Power Off (EPO) system being installed

Emergency Power Off (EPO) system being installed

Emergency Power Off (EPO) system being installed

Emergency Power Off (EPO) system being installed

Emergency Power Off (EPO) system being installed

Emergency Power Off (EPO) system being installed

All elements of the EPO system have been deployed in red

All elements of the EPO system have been deployed in red

Another EPO junction and control box in the meet me room

Another EPO junction and control box in the meet me room

Custom red faceplates for EPO connection to core UPS units

Custom red face plates for EPO connection to core UPS units

Red continues all the way to the rear of the UPS, where the final connection is made

Red continues all the way to the rear of the UPS, where the final connection is made