Our significant expansion of Netwise London East (NLE) is now well underway, which is Phase 3 of development at our flagship data centre.
This will result in the addition of two new data halls, alongside a range of additional amenities and site features. Works began in December 2024, and will continue throughout 2025, with various completion milestones at multiple stages along the way.
The main focus at this stage is the installation of the new mezzanine, as this forms the basis of the entire internal sub-structure, around which we build our facilities (as seen at our London Central site, and also the current footprint at London East).
Here are some photo updates from the early stages of Phase 3:
As you can see, we’ve been able to make quite an impressive start to the project. To have the mezzanine complete in the first week of January sets up our work schedule incredibly well, allowing for the envelope to begin later this month.
We have also now started a range of other preparatory works ahead of this, including the insulation and closure of the skylights, encasement of the columns with fire protection, and some of the breaching works for interconnecting the units and other internal areas.
We have more updates coming as part of Phase 2 soon also, so watch this space for plenty more build content throughout Q1 2025 and beyond.
As we close the doors on yet another record-beating year at Netwise, we can now take a look back at the last 12 months of change and development, which have been host to major leaps forward in a wide range of areas within the organisation.
We always knew that 2024 would be a big year, and we were not wrong. In the last 12 months, we have made great strides in the development of our London East facility, which continues to grow into one of London’s most compelling independent data centre offerings.
Here are some of the headlines from 2024:
Netwise turned 15 – having been founded in 2009, Netwise turned 15 in 2024, which is a great milestone and a testament to the unwavering stability of the organisation.
We fully deployed Data Hall 4 – Data Hall 4 reached completion in early 2024, allowing for continued client deployments throughout the year. The build process for Data Hall 4 can be found on our #BuildBlog.
The deployment of Data Hall 3 began – in the closing stages of 2024, we began pre-stage works on Data Hall 3, which is the final hall for deployment in the current footprint at London East (ahead of the large-scale expansion in 2025). This will be the final hall as part of the Phase 2 development cycle, and will be documented on our #BuildBlog in the coming months.
We closed NLC in the summer – the summer of 2024 saw the closure of our legacy site in Bermondsey, Netwise London Central. This was a very large project that had been under planning for many months prior to execution, resulting in an extremely smooth closure process once the work schedule began. This included extensive decommissioning works, while also continuing with the Phase 2 development schedule at London East.
We migrated all live systems from NLC to NLE – as part of the NLC closure, we migrated all client systems from NLC to NLE. This was a very complex operation spanning eight evenings in total, with the entire operation being completed extremely smoothly, thanks to the extensive planning phase, and the in-house expertise of our world-class team. In total, 126 enclosures were moved out of NLC.
We upgraded our core network – all of our on-net nodes received an extensive upgrade in the first half of the year, increasing overall capacity and improving performance for clients that utilise our world-class transit network.
Lee Smith joined as Junior Engineer – in Q4, we expanded our team with the joining of Lee, our new Junior Engineer, who is already and integral part of our in-house electrical engineering team. Expect a full introductory post very soon.
The NLE expansion project officially started in Q4 – very late in 2024, we broke ground on the next phase of development at NLE. The installation of the mezzanine structure within the new footprint began in December – you can expect plenty of #BuildBlog updates as Phase 3 progresses in 2025.
Works began on the full redevelopment of our customer portal – we have big plans for our customer portal in 2025 and beyond, as we begin a full rework of the UI/UX. We’ve teamed up with the same outfit behind our company rebrand and main website redesign from 2019 for this project, and we hope to have more news on this later in the year. The design of this new portal began in the closing stages of 2024, as a collaborative project including our development team.
Aside to the somewhat unique task of closing NLC, the main focus of the year has absolutely centred around the continued expansion of our flagship data centre, NLE. This likely comes as no real surprise, given the pace at which our services are being taken up in the market, and the unabating growth within the sector as a whole. Our current forecasting sees no slow up in this ongoing trend, and as such we will continue to invest heavily in our future at NLE and beyond.
Looking past the more tangible projects in 2024, financial performance has again been exceptionally positive, which further solidifies our position as a leader in the market, providing unmatched stability for our growing roster of clients, and of course enabling our expansion in the years ahead. Base revenues for the year have grown by 21% – despite the distraction of closing NLC in the summer – which in our fifteenth year of operation is all the more remarkable.
In short, 2024 has been another incredible year for Netwise, setting us up for another truly exceptional year in 2025.
So, how are things looking for the year ahead? We’re expecting more of the same, with a major focus on the completion of Phase 2 (Data Hall 3), and the larger expansion project as part of Phase 3, which will run in tandem throughout the first few months of the year (Data Halls 5 and 6, plus amenities). While we can’t comment too far in advance on other plans for the year, we do have some very exciting developments in the works, that could see further expansion plans confirmed before the end of 2025 – watch this space!
We’re very excited for you to meet our Engineering Manager, Josh Carvalho.
Josh joined us back in late 2023, from the demanding world of electrical engineering, having spent the formative years of his career garnering extensive experience across all facets of electrical system design and implementation.
With a passion for powering the future and an impressive background in the design and installation of critical power systems, Josh brings with him a wealth of experience and knowledge to our ever-growing team. His arrival marked another pivotal moment in our journey, as we continue to strengthen our position as a world-leading data centre operator.
As our Engineering Manager, Josh plays a crucial role in shaping the future of Netwise and its deployed assets. His leadership, technical acumen, and commitment to excellence has undoubtedly resulted in another ‘level up’ to our in-house capabilities, as we continue to expand our suite of services.
Josh’s arrival has tangibly demonstrated our unwavering commitment to providing only the very highest quality of service to our clients, with limited reliance on any third parties.
You can expect to see Josh in a design and implementation role across our core infrastructure, as well as in the field, getting hands on with the systems responsible for keeping your business online 24×7.
This month we’re very happy to officially announce the next major phase of development and expansion at our Netwise London East (NLE) data centre.
We’re facilitating this expansion by pushing into the adjacent building on the Datapoint estate, which sits alongside our existing four-hall facility. This will result in a single expanded facility housing six high-specification data halls.
The initial fit-out phase began in July, with the main internal schedule of technical works set to begin in early 2025. This project will expand NLE by 168 racks, increasing the total internal area of the building by around 13,000ft2.
The new building is being fully refurbished – both inside and out – following the departure of the previous occupants, ahead of the main work schedule which will start thereafter.
This is our first major step towards developing NLE into a campus-style facility, which spans multiple buildings on the same estate. The two units will become a single operational building, with multiple pass-through points for clients and staff, as well as for the sharing of core services.
Alongside the additional rack capacity, this new space will also introduce further amenities and technical features, including increased capacity for staff, a second loading bay and storage area, more on-site parking and EV charging, as well as improvements to our water handling capabilities.
There will also be flexible space held for future use, which will provide additional service options for potential wholesale customers, for things such as private on-site NOC capabilities.
"This represents another seven-figure investment by Netwise in its own future, and the future of its clients. To be announcing this level of growth at NLE only a couple of years after the first clients moved in is something we're very proud of; it's a testament to the strength of this sector, and our own position within it."Matt Seaton, Director
The uptake of services at NLE has been extremely impressive since it soft-opened in the spring of 2022, with the phased fit-out schedule just keeping pace with demand. The current building now has three of the four data halls deployed. The final hall in this building is scheduled to be online by the end of 2024.
The two new halls coming as part of the facility expansion project will be larger than the halls in the current building, housing 84 racks per hall at maximum rack density – a 33% increase per hall. These new halls will house three containment pods each, giving greater scope for private space options.
In June, the Netwise London Central (NLC) facility officially closed, having served clients for 10 years. The forthcoming expansion at Netwise London East would become one of the main driving factors behind the decision to shutter NLC, as many core components within the site reached end of life.
The large seven-figure reinvestment required to adequately refresh NLC has instead been diverted to the new facility, which has the forward-looking scope to springboard Netwise into the next phase in its growth cycle.
The NLE expansion comes as Netwise continues to welcome an exciting range of new clients into its facilities, as well as facilitating the growth of its long-standing customers.
"We always knew that we'd be expanding NLE in time, to facilitate our growth trajectory, however to be at that stage already is a tangible demonstration of our performance and reputation in this industry. I'm very excited by this next phase, particularly as we come out the back of the NLC closure, which required considerable care and attention."Matthew Butt, Managing Director
The expansion of NLE will bolster our position as a leading data centre operator in the high-demand East London / Docklands region, as we further the already significant investments made in our flagship facility, which has been in operation since mid-2022.
While finer details of the technical plans are still expected to develop over the closing months of 2024, the overarching plans are already locked in, and can be discussed with interested parties that may be looking to utilise bulk space in the new side of the facility.
The Netwise team cannot wait to show you around the new side of the facility as it develops. And as always, the #buildblog will be back in action, documenting the entire build process, so be sure to keep an eye out for new posts.
It’s been a while since we last published a Phase 2 update from Netwise London East (NLE), so we thought it would be a good time to update everyone on the current state of play.
We’ve been remarkably busy with both the ongoing expansion works at NLE, alongside the closure of Netwise London Central (NLC), which was retired from active service in early June.
Data Hall 4 went live in May, and quite remarkably, it’s already a touch over half full, despite opening to new clients just a couple of months ago. This is in large part thanks to the absorption of our customer base from NLC, which we migrated over the course of eight evenings in May, however we have also welcomed a host of exciting new clients into our latest data hall.
Let’s take a look at what’s been happening. We start with updates from back in mid-April, before jumping ahead to current day:
It’s fair to say that this summer has already been one of our busiest periods on record. Deploying a new data hall at NLE is no small task in itself, but to deliver this alongside the decommissioning of NLC – which also involved the in-house planning and execution of an entire facility migration – leaves us feeling incredibly proud of the team we have driving Netwise. The complexity of successfully realising a multi-faceted project like this cannot be understated, and seeing these tasks result in tangible improvements to service for our clients is always incredibly pleasing, particularly after making seven figure investments in our future here at London East.
But as with any operation of this nature, these are just the headline deliverable outcomes that have been worked on over the past several months. We’ve undertaken plenty of additional projects in tandem over the last quarter, which may be of interest to our readers.
We completed our full core network upgrade in May, with the final upgrade – and the most major works list – happening at our HEX/LD8 node. This involved a full conversion of this location to our Supernode architecture, which in this case required a full cabinet swap to accommodate. This type of thing requires considerable planning, however our team were able to complete the entire works list within the four hour maintenance window, which was an impressive feat. We also undertook a minor upgrade to our core node in Redcentric Shoreditch (formerly CLL), which brought the entire network upgrade project to completion. This comes as demand on our network grows rapidly, delivering world-class connectivity to clients across all of our on-net locations.
We also grew our fleet in spring, with the addition of an electric pick-up truck, and our own low-loader, which is perfect for rack migrations. The latter vehicle comes in a relatively rare specification for us, with extra height and a 750kg tail lift, which makes it absolutely ideal for the movement of fully populated racks – a game changer for most facility migration projects.
As part of bringing Data Hall 4 online in May, we rolled out new cooling system architecture, which involved some adjustments to how the extraction side of the system works. We now have a twin-hall shared extraction plenum, with a centralised control system, which we believe to be the first of its kind for an evaporative system such as ours. This involved the expert design work of multiple teams, and will also be a part of the roll-out for Data Hall 3 later this year.
Further to this, we have additional cooling being deployed in all data halls in the next few weeks, through the modular installation of further evaporative coolers. Each room is growing from four CREC units, to six CREC units.
NLC closure and migration project
In May, we migrated all of the clients in our London Central facility to our new London East facility.
This took many months of planning, however we were able to complete the physical migration process in just eight evening sessions – a real testament to our broad in-house capabilities.
All 126 enclosures were successfully transitioned to our London East facility (with a few landing in other on-net locations where required), with most racks moved in a fully-populated state. This allowed for minimal client disruption, and the fastest possible transition from one site to the other. The fastest migration window took just two hours, from power down at NLC, to being back online at NLE.
Here we have some photos of the now retired facility, which served our clients well for nearly a decade:
The end of an era, but the beginning of a truly special new chapter for Netwise, as we focus on our campus site, London East. We will be expanding this location significantly in the coming months – more on this very soon.
What’s next?
The biggest upcoming build work will be the onlining of Data Hall 3, the final hall in the current building at Netwise London East. Work will begin on this hall in the coming weeks. This will be the final component of Phase 2, before Phase 3 works begin in late 2024 / early 2025 – this will be a major development phase.
We hope to announce the next phase of works in an official capacity in the next few weeks.
Otherwise, we will continue to welcome new clients to our world-class facilities, along with the provision of assistance to existing clients looking to grow. This is an exciting time for Netwise, and we look forward to sharing more news with you very soon.