London East Phase 3 Development Update 3

Update three of the London East expansion project shows great progress on the envelope works, during which time we’ve seen the two spaces breached to become one single building – an early but poignant milestone for the project.

The various doorways have also been rough-cut into position ahead of final finish cuts – and being raised to finished floor height – allowing the real-world flow of the space to be experienced for the first time.

Here are the photo updates:

Envelope
The wall panels which form the main first floor corridor make for an imposingly tall space at this stage, ahead of the raised floor and ceiling installation in due course
Envelope
The main corridor on the ground floor sits directly below that of the first floor
Envelope
The second corridor on the ground floor leads to the power servicing rooms, sitting perpendicular to the main corridor run, with some doorways now rough-cut in here (to slab, for access)
Envelope
The shell of Data Hall 6 on the ground floor is an ideal place for the storage of materials, prior to use
Envelope
Another view across Data Hall 6, looking towards the main entrance of the hall – this leads into the main access corridor, and through onto the loading bay, which is just visible here
Envelope
The doorways have been rough-cut to enable access at slab and deck level, ahead of final cuts and installation at their finished heights (accounting for the raised access flooring)
Envelope
The main first floor corridor connects the expansion to the current live footprint, providing access to the new data halls, as well as onward access to the amenities within the new space
Envelope
Here we see the installation of the walls which will form part of the cold corridor area within Data Hall 5, as trim finishes also begin to see installation
Envelope
The area to the side of Data Hall 5 will be home to new offices and a high specification meeting room – the far end wall visible here, at the end of the first floor corridor, will be the breach point location for this floor, connecting into the live side of the facility
Envelope
There will be another corridor positioned here for access to the three rooms on this end of the building, however as this will be entirely glazed, this will be installed further into the project
Envelope
Here we see the two ground floor corridors as captured from their intersection point – this location is also home to another breach, into the ground floor of the front-of-house area
Envelope
This view of Data Hall 5 shows the initial shell close to completion, ahead of doors, floors and ceilings – some of this will follow later, as there will be a significant round of containment works due ahead of then
Envelope
Data sheets have been placed around the facility to aid in the installation of the door sets, as well as the datum lines for finished floor heights and checker plating
Envelope
The back end of the ground floor is home to the new UPS and power distribution rooms, as well as the new service corridors for cable route management
Envelope
One of the next modifications to the new wall structure will be the cutting of any required cable penetrations between rooms and floors

We can now look at the breach works, which were definitely a significant milestone on-site:

Envelope
The hoarding installed within the ground and first floor corridors (within the active side of the facility) have since been over-clad with more attractive covers – these serve as dust penetration protection, and can act as temporary routes into the new space during the build
Breach
Here we see the breach of the ground floor, which sits behind the hoarding visible on each floor of the active facility – all cuts at this stage are ‘roughed in’, ahead of final cutting and flashing, and of course the installation of double doors
Breach
Here’s a view of the first floor breach underway – the building steels require modification here, which involves the installation of a fully custom steel frame insert
Breach
The horizontal building steel seen here, which forms part of the fabric of the building, will be cut away, with a full replacement steel frame to be installed in its place
Breach
A view of the first floor breach, as seen from the new office area, with the entrance to Data Hall 5 on the left, and the first floor loading access door on the right
Breach
There will be a full timelapse of the entire envelope installation – from empty space to finished shell – coming later in the project
Envelope
While slightly obstructed from view here, the new end-to-end corridor runs, following the breach works, are certainly impressive
Breach
Here we can see the new steel reinforcement frame in place, as seen from the ground floor breach location – the finished raised floor and ceiling, along with the checker plate, is visible on the other side of the breach
Breach
The new steel frame sits within a very tight space – between the two mezzanine structures on each side of the facility – and uses a combination of bolted fixings and welding to marry into the building
Breach
The top of the new frame can be seen here on the first floor, along with the various required repairs to the block wall, now that the installation access requirements are complete – this will all be hidden behind new wall panels and flashings
Breach
This is the view from the existing ground floor corridor, through the temporary hoarding, into the new ground floor corridor
Breach
The view is quite impressive, and gives an idea of the forthcoming scale of the expanded site
Breach
There are two further block wall breaches within the build schedule – this is the third, which connects the ground floor corridors to the reception area, and additional office space
Breach
The other side of this third breach shows the door installation underway, at raised floor height – there will be many further modifications to make to this side to reach completion, including stairs and a ceiling well

Here are some additional shots from around the site:

Exterior
The side return yard of the new expansion space is large, and will house extended parking, as well as required plant equipment for the new data halls – this will of course be fully enclosed with new perimeter security, to match that of the existing space
Windows
The window manifestations have been installed on all relevant panels, to match the active side of the facility
Windows
The new reception area on this side of the facility will primarily serve as a staff entrance, with the main entrance for clients remaining on the current side of the site
Windows
The corner profile of the new expansion shows the full-wrap access that this side of the facility is afforded
Windows
All of the ground floor window manifestations are installed, including black-out manifestations on windows covered by new internal walls towards the rear half of the space – some of the comfort cooling and fresh air system equipment can be seen here

As expected, progress continues at great pace at this stage in the project, in tandem with Phase 2 works on the active side of the facility (more to come on that soon).

We look forward to sharing more with you soon.

London East Phase 3 Development Update 2

Work on the London East expansion continues at pace as we head into February, with sizable progress made on the first stage of the envelope.

This allows us to see the various spaces within the new footprint realised for the first time, as the walls for the data halls, access corridors, and all other areas begin to section off the internal space.

Let’s get straight to it with the updates:

Mezz
A final look across to the completed mezzanine ahead of the envelope works getting underway
Mezz
The column casings were the final element of the mezzanine installation, which are for fire protection and to provide a matching finish for the wall system
Mezz
The top surface of the mezzanine has now had its protective coating laid down, which will be covered by the raised floor in due course
Mezz
Here’s another view of the insulated coverings which block off the skylights, which will be further covered by the hung ceilings in due course
Envelope
The first delivery of the Eurobond wall system arriving on-site, which is the same system deployed in the current footprint at NLE
Envelope
There’s around 15 tons of wall panels as part of the envelope within the new expansion
Envelope
The wall panels are stored in pre-marked stacks based on their installation location, ahead of customisation (where required) and fitment
Envelope
Having the stacks pre-marked allows for each bundle to be moved to the installation area as appropriate
Pallet Racking
We’ve erected part of the heavy-duty pallet racking which will live permanently in the loading bay area of the new space – this will house various construction components and materials during the build
Pallet Racking
Once the build phase is complete, the racking will be extended, and will cover a large portion of the new loading bay area
Envelope
A view of the first wall sections being installed on the first floor
Envelope
This is the main corridor wall that will be home to the entrance to Data Hall 5
Envelope
Here we look across to the wall system installation that will enclose Data Hall 5, from the eventual location of the new meeting room
Envelope
The enclosure of Data Hall 5 continues to take shape, as the envelope installation works push ahead
Envelope
For context on positioning, this view shows the space for Data Hall 5 on the left, and the current opening down into the loading bay, with the position of the temporary barriers here sat inside what will become the access corridor and loading access for the first floor
Envelope
This is a view of the same area from the ground floor loading bay, which now also shows the installation of the wall for the perpendicular access corridor which will lead to the new offices, meeting room, and break out area
Envelope
Another view from what will become the cold corridor area within Data Hall 5, as works continue
Envelope
This is the view from the eventual meeting room location, looking down towards the forthcoming offices, and the eventual location of the wall breach which will lead through to the break out area and additional office / NOC space
Envelope
A view of the same wall from the first floor corridor – this encloses Data Hall 5, and will become the junction point between the two first floor access corridors
Envelope
The ground floor main access corridor seen with both walls part way through installation, looking towards the breach area which will connect the ground floor to the current footprint
Envelope
A view of both floors progressing with access corridor walling, which will provide both entry points to the new data halls, and also level loading capabilities to each floor
Envelope
Ongoing inspections of progress by the Netwise design team are undertaken multiple times each day
Envelope
This is the view from one of the new UPS and power distribution rooms, looking across to Data Hall 6, ahead of further access corridor walling being installed in the foreground
Envelope
A view from inside Data Hall 6, with further walling stock as installation of the envelope continues
Envelope
Here we see preparation ahead of the main run of enclosing wall on the first floor, which requires a custom drop mounting system
Envelope
Another view of preparation work underway, ahead of installing the next main run of walling
Envelope
Further progress on access corridors within the ground floor
Envelope
The view from one of the new cable access corridors, looking across the new UPS and power distribution area ahead of further sub-division of rooms
Exterior
The temporary site fencing has had additional branding applied to more clearly indicate the expansion project to visitors

We’re very pleased with progress, and the whole Netwise team is very excited to see the new space take shape in such a tangible way. The next update will show the completion of the walling phase of the envelope installation, at which point our team will begin installing first stage containment and a certian level of flood cabling, before the install of the ceilings and raised floors.

All of this work follows on from the completion of the mezzanine sub-structure, which we captured in a timelapse much like last time:

The timelapse of the mezzanine install inside of the NLE expansion, comprised of ~7,000 photos

There are plenty more updates to come, with no let up on the pace of progress at this stage, so watch this space for further updates on the expansion works. We have further updates coming soon on the final part of Phase 2 works, which will see the completion and onlining of Data Hall 3.

London East Phase 3 Development Update 1

Our significant expansion of Netwise London East (NLE) is now well underway, which is Phase 3 of development at our flagship data centre.

This will result in the addition of two new data halls, alongside a range of additional amenities and site features. Works began in December 2024, and will continue throughout 2025, with various completion milestones at multiple stages along the way.

The main focus at this stage is the installation of the new mezzanine, as this forms the basis of the entire internal sub-structure, around which we build our facilities (as seen at our London Central site, and also the current footprint at London East).

Here are some photo updates from the early stages of Phase 3:

Exterior
Some of the earliest works centred around a full internal and external renovation of the new unit, including a significant amount of work on the roof
Exterior
The exterior cladding of the building also enjoyed a full refinish, which will become evident in later photos
Exterior
This is the view across to the expansion project within the new unit, from the existing facility entrance / footprint
Interior
The inside of the new space also required significant refurbishment before our main works schedule began
Interior
The front-of-house areas also got completely ripped out ahead of a total refurbishment
Interior
We’ll be adding further office and administration spaces in this new side of the facility, and the existing upstairs office also saw a full strip-out ahead of refurbishment
Exterior
This is the main frontage of the extended footprint after the completion of the initial refurbishment, ahead of our main works schedule commencing
Office Prep
This space will become a second / extended NOC and operations space, after the initial refurbishment, and with the new carpet covered ready for the next phase of work to begin
Office Prep
The site has been fully prepared for our main work schedule here, including all protective covering of newly installed surfaces, and the various required temporary site boards and signage in place
Signage
The temporary signage extends to all areas of the site
Office Prep
One of the existing ground floor spaces has become the on-site canteen and break room, ready for the various contractors that will be working on-site in the coming months
Site
One of the early stage jobs, beyond our initial laser survey of the space, is to laser plot the main column locations for the new mezzanine sub-structure
Site
With such a high degree of accuracy required for the installation of the mezzanine, collaboration between engineers, project managers and installers is key
Site
A view across the main space, as column locations are marked up according to the installation plans
Site
Here are some of the many heavy-duty custom steel columns as delivered, ahead of installation
Site
A view across the main space, following the initial refurbishment, as the main work schedule begins
Site
Another view across the main space, following the initial refurbishment, as the main work schedule begins
Mezz
The mezzanine sub-structure is a surprisingly quick component to install, with much of the work front-loaded during the planning and engineering phase
Mezz
The mezzanine is installed in bays / sections, and progresses across the space from the initial column locations
Mezz
A view of the mezzanine progress from the rear corner of the new space
Mezz
We have an installation timelapse of the mezzanine install, which we’ll be making available in the near future – 19,000 photos in total!
Mezz
Here we see part of the structure standing in isolation, ahead of the installation of the purlins that will make up this particular bay
Mezz
This is the underside of a partially complete bay
Mezz
Here we see further progress, as the temporary safety netting is installed to the underside of the mezzanine ahead of installing the top surface
Mezz
The main beams are partially assembled on the ground, ahead of lifting into place
Mezz
A view of progress as the mezzanine structure continues to take shape
Mezz
A view of the underside of the structure, as top surface boards begin to be positioned
Mezz
The boards are fixed to the structure, and will form the initial face upon which the next stage is built, which will be the main envelope
Mezz
Here we look down from the partially completed half of the structure, which will continue across this span to the far side of the space
Breach
Despite the expansion project taking place within an adjoining unit to the existing live footprint, the two spaces will be combined into a single facility – as part of this, we will be breaching between the two units; we have installed temporary dust and fire barriers, ahead of the cut through process
Breach
Here we can see the initial breach of the outer skin of the envelope within the ground floor corridor
Mezz
Progress continues with the mezzanine installation
Mezz
The view here is taken from what will eventually be the cooling plant area for Data Hall 6 – the two halls within this new expansion will be larger than those within the current footprint, each housing three containment pods
Mezz
The final columns being cross-checked after installation, as the mezzanine continues towards completion
A view back across the mezzanine structure, as works progress
Mezz
The scissor lifts work in conjunction with our forklift in getting components to the correct height for installation
Mezz
The view looks across the area that will make up Data Hall 6 on the ground floor of the new space
Mezz
This view is from the approximate eventual location of Pod 3 within Data Hall 6
Mezz
All parts of the steel structure are now complete, with only the remaining top surface installation to go
Mezz
The view here looks across to the outside face of the facility, which will house offices, a new meeting room, and supporting electrical infrastructure for the new data halls
Mezz
This is the view from the top surface as it continues towards completion – this is taken from the eventual first floor corridor, looking into the area that will house Data Hall 5
Mezz
The top surface installation continues here
Mezz
Members of the Netwise team undertake regular inspections as part of the installation process
Mezz
This view sits on the edge of what will become the B-side UPS and switchgear room for the two new data halls, and the associated cable access corridor (a new cable handling methodology that we’re deploying as part of the expansion) – the new meeting room will be directly above this
Mezz
Here we see the underside of the completed mezzanine structure
Mezz
Another view of the completed mezzanine, as viewed from the eventual location of Pod 3 in Data Hall 6, looking towards the eventual location of the UPS rooms and cable access corridors
Mezz
The completed structure, as seen from the new loading bay area, with temporary barriers in place until the envelope is installed
Mezz
The next action on the underside of the mezzanine structure will be the column encasements
Mezz
Here we see the top side of the new structure, as some minor additional works begin on the sky lights
Mezz
This is the view from the eventual location of Pod 3 within Data Hall 5, looking across to the eventual location of the new offices and meeting space
Mezz
Our scaffold tower is being used for roof-level access now that the top surface is complete
Mezz
The insulation and closure of the sky lights can be seen underway here
Mezz
All of the sky lights above the data halls will be insulated and closed off as part of the pre-envelope works, which replicates the setup in the existing live data halls
Mezz
Our facilities team are undertaking this work, ahead of the next major contractor stage – the envelope
Mezz
The view down into the new loading bay, as viewed from the edge of the mezzanine, where the access corridor will be located – there will be level loading capabilities here, as with the existing loading bay

As you can see, we’ve been able to make quite an impressive start to the project. To have the mezzanine complete in the first week of January sets up our work schedule incredibly well, allowing for the envelope to begin later this month.

We have also now started a range of other preparatory works ahead of this, including the insulation and closure of the skylights, encasement of the columns with fire protection, and some of the breaching works for interconnecting the units and other internal areas.

We have more updates coming as part of Phase 2 soon also, so watch this space for plenty more build content throughout Q1 2025 and beyond.

A look back at 2024

As we close the doors on yet another record-beating year at Netwise, we can now take a look back at the last 12 months of change and development, which have been host to major leaps forward in a wide range of areas within the organisation.

We always knew that 2024 would be a big year, and we were not wrong. In the last 12 months, we have made great strides in the development of our London East facility, which continues to grow into one of London’s most compelling independent data centre offerings.

Exterior
Perhaps the most important project of 2025 began late in 2024 – our expansion project at NLE, which will see the onlining of two new data halls this year

Here are some of the headlines from 2024:

  • Netwise turned 15 – having been founded in 2009, Netwise turned 15 in 2024, which is a great milestone and a testament to the unwavering stability of the organisation.
  • We fully deployed Data Hall 4 – Data Hall 4 reached completion in early 2024, allowing for continued client deployments throughout the year. The build process for Data Hall 4 can be found on our #BuildBlog.
  • The deployment of Data Hall 3 began – in the closing stages of 2024, we began pre-stage works on Data Hall 3, which is the final hall for deployment in the current footprint at London East (ahead of the large-scale expansion in 2025). This will be the final hall as part of the Phase 2 development cycle, and will be documented on our #BuildBlog in the coming months.
  • We closed NLC in the summer – the summer of 2024 saw the closure of our legacy site in Bermondsey, Netwise London Central. This was a very large project that had been under planning for many months prior to execution, resulting in an extremely smooth closure process once the work schedule began. This included extensive decommissioning works, while also continuing with the Phase 2 development schedule at London East.
  • We migrated all live systems from NLC to NLE – as part of the NLC closure, we migrated all client systems from NLC to NLE. This was a very complex operation spanning eight evenings in total, with the entire operation being completed extremely smoothly, thanks to the extensive planning phase, and the in-house expertise of our world-class team. In total, 126 enclosures were moved out of NLC.
  • We upgraded our core network – all of our on-net nodes received an extensive upgrade in the first half of the year, increasing overall capacity and improving performance for clients that utilise our world-class transit network.
  • Lee Smith joined as Junior Engineer – in Q4, we expanded our team with the joining of Lee, our new Junior Engineer, who is already and integral part of our in-house electrical engineering team. Expect a full introductory post very soon.
  • The NLE expansion project officially started in Q4 – very late in 2024, we broke ground on the next phase of development at NLE. The installation of the mezzanine structure within the new footprint began in December – you can expect plenty of #BuildBlog updates as Phase 3 progresses in 2025.
  • Works began on the full redevelopment of our customer portal – we have big plans for our customer portal in 2025 and beyond, as we begin a full rework of the UI/UX. We’ve teamed up with the same outfit behind our company rebrand and main website redesign from 2019 for this project, and we hope to have more news on this later in the year. The design of this new portal began in the closing stages of 2024, as a collaborative project including our development team.

Aside to the somewhat unique task of closing NLC, the main focus of the year has absolutely centred around the continued expansion of our flagship data centre, NLE. This likely comes as no real surprise, given the pace at which our services are being taken up in the market, and the unabating growth within the sector as a whole. Our current forecasting sees no slow up in this ongoing trend, and as such we will continue to invest heavily in our future at NLE and beyond.

Matthew Butt, Managing Director, and Matt Seaton, Director, stood outside of NLC on the day of its final closure
The closure of NLC in the summer was a notable milestone for Netwise, as focus shifts to the ongoing development of NLE

Looking past the more tangible projects in 2024, financial performance has again been exceptionally positive, which further solidifies our position as a leader in the market, providing unmatched stability for our growing roster of clients, and of course enabling our expansion in the years ahead. Base revenues for the year have grown by 21% – despite the distraction of closing NLC in the summer – which in our fifteenth year of operation is all the more remarkable.

Mezz
The internal fit-out of Phase 3 is now well underway, which will house Data Halls 5 and 6, along with a host of exciting new amenities

In short, 2024 has been another incredible year for Netwise, setting us up for another truly exceptional year in 2025.

So, how are things looking for the year ahead? We’re expecting more of the same, with a major focus on the completion of Phase 2 (Data Hall 3), and the larger expansion project as part of Phase 3, which will run in tandem throughout the first few months of the year (Data Halls 5 and 6, plus amenities). While we can’t comment too far in advance on other plans for the year, we do have some very exciting developments in the works, that could see further expansion plans confirmed before the end of 2025 – watch this space!

Team in focus: Josh Carvalho

We’re very excited for you to meet our Engineering Manager, Josh Carvalho.

Josh joined us back in late 2023, from the demanding world of electrical engineering, having spent the formative years of his career garnering extensive experience across all facets of electrical system design and implementation.

With a passion for powering the future and an impressive background in the design and installation of critical power systems, Josh brings with him a wealth of experience and knowledge to our ever-growing team. His arrival marked another pivotal moment in our journey, as we continue to strengthen our position as a world-leading data centre operator.

As our Engineering Manager, Josh plays a crucial role in shaping the future of Netwise and its deployed assets. His leadership, technical acumen, and commitment to excellence has undoubtedly resulted in another ‘level up’ to our in-house capabilities, as we continue to expand our suite of services.

JC
Josh can be found working his magic across all areas of our data centres, keeping them in top-tip shape around the clock for our clients
UPS
Electrical engineering sits front and centre of any data centre operation, so having Josh head this up internally for us is a major operational advantage

Josh’s arrival has tangibly demonstrated our unwavering commitment to providing only the very highest quality of service to our clients, with limited reliance on any third parties.

You can expect to see Josh in a design and implementation role across our core infrastructure, as well as in the field, getting hands on with the systems responsible for keeping your business online 24×7.