We’re now a little way into Phase 2 of development here at our London East data centre, with good progress made across a number of areas throughout the facility since our last update.
The deployment of Pod 2 in Data Hall 1 is well underway, with all racks now positioned and bayed, and with the first tenants in the space already deploying live kit. The complete containment system is now being installed, which will bring the capacity expansion project within Data Hall 1 to a close.
Beyond this, further work has been undertaken as part of the Data Hall 2 expansion project, as we prepare for that space to take initial occupancy in the early stages of 2023.
Aside to the data halls, we’ve also seen developments elsewhere, such as the onlining of our new lift, the installation of our new gates and razor wire system to the rear compound fencing, our new Naturewall welcome screen in the speed gate entranceway, and additional development work undertaken on our customer portal.
The Build and Break Room has also seen notable advances towards its completion and full opening, which is something we’re very excited about. We’ll be continuing to keep this under wraps for the time being, and will publish a separate update about this once ready for use.
We’ll get straight to it with the photos:
Progress is expected to pick up as we head towards Christmas, with several weeks of additional activity planned for the back half of November, which will focus on continued work inside of Data Hall 1, along with further preparatory works as part of the Data Hall 2 onlining process.
We’ll also be rolling out some new features on our customer portal and back-end systems, with further news to follow in that regard when suitable.
In late August, works began full-force on Phase 2 of our London East data centre build project.
While we won’t be publishing a Build Blog to the same degree as Phase 1 – the forthcoming modular roll-out of additional capacity will be less technically involved (and perhaps interesting) than the front-loaded primary build – we are still going to document this process, and put out updates as things progress.
Phase 2 will predominantly focus on two areas of expansion at London East; the deployment of Pod 2 in Data Hall 1 for an immediate capacity boost, and the full deployment of Data Hall 2, for mid-term growth enablement.
This phase is less time-sensitive than the initial build, and will likely be a split development phase as works continue in other areas, including our Build and Break Room and our new personnel lift, both coming in October.
Updates
We’re now a couple of ‘split weeks’ into Phase 2, and have some initial visual updates to share with our readers.
We’re extremely pleased with developments so far, despite being early into Phase 2. It is a phase of work which is expected to take us into next year for full realisation, however it will complete in stages. For example, the deployment of Pod 2 in Data Hall 1 will come first, and will be a relatively fast process, as this simply requires the physical construction of the containment pod and the integration of some monitoring and operating systems. The supporting infrastructure is already in place, with no required additions at this stage.
The deployment of Data Hall 2 is a larger operation, as this still requires lots of work under the raised floor to make the space ready for power and connectivity.
We’ll be posting updates to this process as and when suitable progress is made.
We’ve taken a much longer break than usual between build blog updates this time around, as we turned focus to the final stages of systems integration and commissioning.
However visual changes have been happening, and in what became the concluding run up to welcoming in our first client deployments to London East, we can relay some of those to you here, and give you a final overview of the facility following Phase One completion.
Weekly overview
With Phase One of the build project now concluded, we’ll be keeping things short and sweet this time, and direct attention to the most recent round of visual evolutions. These now span a period of several months, and in that time we have in fact welcomed our first clients into the new facility, with a very healthy provisioning queue ahead of us.
This is of course a major milestone for us, as we soft-launch the site to clients that have been on the waiting list for entry for quite some time now. Our official public launch is expected in the near future – details to be confirmed.
The main purpose of this post is to present the current state of play at London East following Phase One of construction, which sees Pod 1 online in Data Hall 1, servicing live clients. We will periodically dip back into the Build Blog, to update on individual projects, and of course the move into Phase Two.
We’re dubbing the next phase of development Phase One-Point-Five, and that’s for some of the ancillary areas which had to be pushed back in favour of technical readiness for client systems. This includes customer facing amenities such as the customer break-out kitchen and lounge area, the personnel lift, and a few remaining internal developments such as our new power monitoring system and some customer portal improvements.
What else has been happening?
Since completing on Phase One, introducing our first set of customer deployments, and the forthcoming Phase Two works, we’ve continued with the fit-out of our customer build and break area.
Works are well underway in terms of laying the section of herringbone floor on which the kitchen and lounge areas of the room will be situated, and our high-specification kitchen installation is also in progress.
Here’s a very small sneak peak at progress so far.
What’s next?
In the immediate term, we’re welcoming a range of clients into Data Hall 1. In fact, we’ve already deployed systems into 17 enclosures, with plenty more lined up for both London East and London Central.
To keep pace with demand looking ahead, and to allow for the next deployment phases, we’ve just had 89x new APC racks delivered to site, which are currently being held in a 60 square metre block in Data Hall 4.
Phase 1.5 is already underway, and expected to last into early autumn. Phase 2 works will begin shortly thereafter, which will see Pod 2 come online, and Data Hall 2 shortly thereafter.
In early July, we spent an entire week on intensive portal development works, as we roll out our brand new client power monitoring platform, client port and bandwidth monitoring re-integration (something that’s been on the cards for a long time now!), and a range of other UX improvements.
We also have some extremely exciting additional developments to pass on very soon, pertaining to our ongoing expansion in all areas. We’re hoping to be able to break silence on this in the coming few weeks.
With the final utility connections now upon us, and the last elements of our stage one internal fit-out now reaching completion, we’re now tantalisingly close to welcoming our first clients into NLE.
A large portion of the facility has in fact been ready to receive client systems for some time now, however as is always the way with projects of this scale and complexity, a number of tasks did run into delays for various reasons as we headed into the back quarter of last year.
Weekly overview
As much as this is a five week update – one of the longest spanning periods to date on the NLE Build Blog – it is somewhat light in visual change, as we’ve been focusing most of our attention on systems integration. Naturally, this is an incredibly important and complex part of onlining any new data centre, however it does prove a tricky side of the project to relay visually.
Regardless, we do have some photo updates to relay this time around.
Much of the work in this period has been happening in less visual areas, including the onlining of systems and bringing them into our centralised control and monitoring platforms. This has been an ongoing part of the commissioning process for some time now, and is nearing completion.
The facility is in a position to accept client systems on a pre-staging basis, with all internal power systems online.
As we head into the final month of Q1, we’re extremely excited to be as close as we are to full readiness. We’re expecting the first client systems to begin rolling into the facility in March, which will of course be the most major milestone of this project to date.
What’s next?
We are continuing with our extensive commissioning works, which span all areas of the facility and its various systems.
All the while this is happening, the final elements relating to our core utilities are being finalised, which will bring phase one of our build to a conclusive state. There will be a certain amount of post-onlining works, which could be dubbed ‘phase one-point-five’, ahead of the later technical space expansion into Data Hall 2, which will be phase two.
We even have some early interest in our ground floor data halls for singular client project use, so it could be that plans for internal expansion are indeed brought forwards, depending on how these things come together in the coming months.
We’ve had a busy start to the year as final stage works continue, taking us towards close-out on phase one at London East.
Our core team got to enjoy some much-deserved time off over the holiday season, ready for action as usual in the new year – one which is set to hold a wide range of milestones for Netwise.
Weekly overview
We’ll get straight to it with the photos this time, as we’ve got lots of changes to show our readers, which have materialised in both the run up to and exit from the holiday season.
It’s an exciting time, as we begin to see many aspects of the new site ‘go live’ for the first time. Aside from some final elements due to close off in the coming few weeks, the site is now essentially service-ready, with some early deployment options for particular clients taking shape.
One system that we’ve been excited to see take shape is our new fully-integrated CCTV and access control platform. While we still have our long-retention continuous recording setup on all cameras, we now also have AI-driven motion tracking and sensing, which means that our system is able to follow visitors around the site automatically, generating points of interest as event triggers. This is also tied into the door entry system, which can actively track activity in the facility and record contextualised snapshots from nearby angles, to create journey data for future reference (if ever required). This level of automation is fantastic for enhancing our security.
What’s next?
Next up, we’ll be continuing with commissioning works across the board, as we liven up all areas of the site.