London Central Build Blog – Week 32

Massive progress has been made over the past few days, with major leaps forward in the cooling system installation which means that technical systems are ready for installation imminently. Great progress has been made in a number of areas throughout the facility, which is always good for seeing the project come together more quickly as we reach the final furlong.

A look across the first data hall after the initial mist coating

A look across the first data hall after the initial mist coating

Extraction holes prepared for 2N air extraction system

Extraction holes prepared for 2N air extraction system

Extraction holes prepared for 2N air extraction system

Extraction holes prepared for 2N air extraction system

First air filter delivery on-site

First air filter delivery on-site

Air filters installed in ceiling grid, for first cold corridor containment pod

Air filters installed in ceiling grid, for first cold corridor containment pod

Air filters installed in ceiling grid, for second cold corridor containment pod

Air filters installed in ceiling grid, for second cold corridor containment pod

Office-side structured cabling tied off ready for entry into patching cabinet

Office-side structured cabling tied off ready for entry into patching cabinet

The first of an eventual 96 office and supplementary amenity / system ports

The first of an eventual 96 office and supplementary amenity / system ports

Tool-free termination on our Cat 6 cabling saves lots of time

‘Tool-free’ termination on our Cat 6 cabling saves lots of time

Flooring in ground floor access corridors reached completion

Flooring in ground floor access corridors reached completion

Installation of our custom tanked floor begins in the cold corridor

Installation of our custom tanked floor begins in the cold corridor

Up-stands are installed in cold corridor access doors to allow for floor tanking

Up-stands are installed in cold corridor access doors to allow for floor tanking

Installation of transitional edging is completed

Installation of transitional edging is completed

Installation of top edging is completed

Installation of top edging is completed

Floor covering is laid out in main data hall and provisionally cut to size

Floor covering is laid out in main data hall and provisionally cut to size

Floor covering is laid into corridor ready for gluing and fitting

Floor covering is laid into corridor ready for gluing and fitting

Floor covering is glued to the subsurface

Floor covering is glued to the subsurface

Flooring is cut to size and fitted to the edging

Flooring is cut to size and fitted to the edging

As is clearly visible, progress has been impressive over the past week, with serious headway made in a number of critical areas.

London Central Build Blog – Week 31

As our first data hall reaches shell completion, and technical installations can begin in earnest, progress in the new facility is set to rocket towards completion, expected before Christmas this year.

Emergency lighting row installed into ceiling, along the main access run leading to cold corridor pods

Emergency lighting row installed into ceiling, along the main access run leading to cold corridor pods

Lighting and door installations reaching completion

Lighting and door installations reaching completion

First coat of weatherproof paint applied to inside of cold corridor

First coat of weatherproof paint applied to inside of cold corridor

A look at construction works in the first floor data hall from the vision panels along the board room wall

A look at construction works in the first floor data hall from the vision panels along the board room wall

Large cable delivery, weighing in at over 1,000kg

Large cable delivery, weighing in at over 1,000kg

Earth cabling ready for installation, another few hundred kilograms

Earth cabling ready for installation, another few hundred kilograms

We have reached a pivotal stage in our progress this month (September 2014), as many of the tasks which have been required to push forwards with larger works are now completed. Although the state of the facility indicates to our readers that we are still deep in the middle of the project, we are in fact not that far away from having the first racks deployed in the data hall, ahead of building final elements such as cold corridor enclosures and finishing touches.

London Central Build Blog – Week 30

There have been dramatic leaps forward this week with regards to the first data halls readiness for technical installations. The ceiling has now been installed, creating the air plenum above which will handle the air in this first hall.

Zoning of plenum completed

Zoning of overhead air plenum completed

Zoning of overhead air plenum completed

Zoning of overhead air plenum completed

Ceiling edging being installed around perimeter

Ceiling edging being installed around perimeter

Ceiling grid installation underway

Ceiling grid installation under way

Ceiling grid installation under way

Ceiling grid installation under way

The completed ceiling grid ahead of light placement modifications

The completed ceiling grid ahead of light placement modifications

Tiles in place after lighting modifications have been made to the grid

Tiles in place after lighting modifications have been made to the grid

A view inside the air plenum, with the air handling apertures in view

A view inside the air plenum, with the air handling apertures in view

Lighting boxes installed ready to for the light fittings to be installed into the grid

Lighting boxes installed ready to for the light fittings to be installed into the grid

Another look inside the air plenum void ahead of lighting fitting installation

Another look inside the air plenum void ahead of lighting fitting installation

Fire doors being hung between the cold corridor and the data floor

Fire doors being hung between the cold corridor and the data floor

We apologise for the grainy photographs; light in the data halls is now extremely limited, as they have been fully enclosed. This makes photography difficult until our lighting system is online.

London Central Build Blog – Week 29

The cold corridor enclosure reached completion in terms of its structure this week. Apart from the installation of the cooling stacks, all that remains is to fit the louvred panels, decorate the corridor using climate resistant paints, and tank the floor with moisture resistant rubber.

Top of the corridor enclosure flown up to ceiling height

Top of the corridor enclosure flown up to ceiling height

Internal face of corridor reaching completion

Internal face of corridor reaching completion

Enclosure insulation reaching ceiling

Enclosure insulation reaching ceiling

Internal face of corridor enclosure completed ahead of finishing

Internal face of corridor enclosure completed ahead of finishing

Delivery of Celotex reflective insulation to box in our ceiling lights to remove their volume from the overhead air plenum

Delivery of Celotex reflective insulation to box in our ceiling lights, removing their volume from the overhead air plenum

Filling completed ahead of sanding down

Filling completed ahead of sanding down

Air plenum zoning installed in ceiling, blocking out the large overhead ceiling windows with reflective Celotex insulation

Air plenum zoning installed in ceiling, blocking out the large overhead ceiling windows with reflective Celotex insulation

Air plenum zoning installed in ceiling, blocking out the large overhead ceiling windows with reflective Celotex insulation

Air plenum zoning installed in ceiling, blocking out the large overhead ceiling windows with reflective Celotex insulation

A look across the data hall as plenum zoning reaches completion, and all natural light in the data hall is removed (once completed)

A look across the data hall as plenum zoning reaches completion, and all natural light in the data hall is removed (once completed)

London Central Build Blog – Week 28

Week 28 has seen further progress on the cold corridor enclosure, though focus has also been turned to other areas of the facility as various elements of the project near completion.

Rear wooden panelling completed around cooling apertures

Rear wooden panelling completed around cooling apertures

A look at the wooden cladding on the rear of the cold corridor enclosure

A look at the wooden cladding on the rear of the cold corridor enclosure

Insulation fitted into cold corridor enclosure

Insulation fitted into cold corridor enclosure

First fireboard sheets being fitted to enclosure

First fireboard sheets being fitted to enclosure

First fireboard run completed on outer face of enclosure

First fireboard run completed on outer face of enclosure

First 3M fireboard sheets being fitted to inner enclosure wall

First 3M fireboard sheets being fitted to inner enclosure wall

Upholstery completed on our custom NOC lounge seating

Upholstery completed on our custom NOC lounge seating

Upholstery completed on our custom NOC lounge seating

Upholstery completed on our custom NOC lounge seating

First carrier entering our Meet Me room, the first of many over the next few weeks / months

First carrier entering our Meet Me room, the first of many over the next few weeks / months

The cold corridor enclosure wall alone is comprised of over 3 tonnes of fireboard, which gives an indication of the sheer quantity of raw materials involved in building an entire data centre. Each 3 metre sheet is just shy of 50kgs.