London Central Build Blog – Week 33

Fantastic progress again this week, as we head towards September.

A look at the completed tanked flooring

A look at the completed tanked flooring in the cold corridor

A look at the completed tanked flooring in the cold corridor

A look at the completed tanked flooring in the cold corridor

Flooring being laid in the first floor build room / server prep area

Flooring being laid in the first floor build room / server prep area

First floor build room with build workstations positioned for testing ahead of room decoration

First floor build room with build workstations positioned for testing ahead of room decoration

First floor data hall flooring ready for installation

First floor data hall flooring ready for installation

Anti-static interlocking floor tiles make for a highly robust technical space floor

Anti-static interlocking floor tiles make for a highly robust technical space flooring solution

A look across the (currently congested) first floor data hall as works continue this week

A look across the (currently congested) first floor data hall as works continue this week

Custom extended lift shaft door installed on first floor

Custom extended lift shaft door installed on first floor

Blanking panels installed on extraction outlets which will not be fully installed from opening date

Blanking panels installed on extraction outlets which will not be fully installed from opening date

Blanking panels installed on extraction outlets which will not be fully installed from opening date

Blanking panels installed on extraction outlets which will not be fully installed from opening date

The blanking panels seen above allow us to extend the cooling and extraction system as the facility capacity increases. The entire data centre has been designed to a fully modular standard, meaning new elements are installed and brought online as required. This includes generators, UPS’s and racks, cooling and extraction – every element of the technical space is modular. The cooling and extraction system will always be able to maintain 2N on the load, extended whenever we are reaching a capacity at which we deem additional resilience is required.