London Central Build Blog – Week 34

This week has seen our cold corridor and cooling system build out progress dramatically, with sensor driven lighting system and cooling unit frameworks being installed, ready for the main coolers and ductwork to follow suit. We have also run new power feeds to the roller shutters for loading bay access.

Infrastructure in place for lighting system ahead of cabling

Infrastructure in place for lighting system ahead of cabling

Cabling installation under way along conduit backbone

Cabling installation under way along conduit backbone

Lighting system being installed along conduit

Lighting system being installed along conduit

Stripped wet box cooling unit placed into corridor for framework testing

Stripped wet box cooling unit placed into corridor for framework testing

Beginnings of the cooling stack framework construction for stack one

Beginnings of the cooling stack framework construction for stack one

Beginnings of the cooling stack framework construction for stack one

Beginnings of the cooling stack framework construction for stack one

Test fitting of the bottom wet box unit in cooler stack one

Test fitting of the bottom wet box unit in cooler stack one

Safety measures installed on tanked floor thresholds between cold corridor and data hall

Safety measures installed on tanked floor thresholds between cold corridor and data hall

Plenty of progress has been made this week, particularly with regards to the cooling system installation. From opening, there will be two cooling stacks online, totalling four wet boxes.  This gives 2N resilience on the cooling system for the two pods online from day one. Our modular design allows us to then liven up new stacks as required. Once both stacks are in their final positions, the duct work will be installed that will allow the stacks to feed the data hall.

We have taken some panoramic shots of the facility this week, something which we will be doing at regular intervals from here on out.

Data hall nearing completion panorama

Data hall nearing completion panorama

NOC to board room panorama

NOC to board room panorama

Office area panorama

Office area panorama

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.