As we head towards the Holiday Season, we’ve been able to clear away a range of outstanding tasks on our list, setting things up nicely for the continuation of scheduled work in Q1 2021.
This short entry covers the items that have seen progress in the weeks leading up to the Festive holiday.
Weekly overview
We’ll be keeping this post relatively brief, however we’ve seen dramatic developments in a couple of key areas; cooling and lighting.
The entire first floor is now fully lit through the Klik system, which provides power to our overhead LED panels. This means that all temporary site lighting on the first floor can now be removed. Emergency bulkheads have also been wired up, ready for final directional label application in due course.
We’ve also built out our cooling system much further, with Data Halls 1 and 2 now very near completion, ahead of plumbing and cabling. The supplementary air conditioning systems are now also in place, pending commissioning much later in the project.
The past few weeks have been vital in driving the project forwards, as we continue to line up the various items required for the next phase of the build.
What else has been happening?
We have two new deployments underway in Frankfurt and Amsterdam, which have been in the works now for some time. These will reach completion in the next few weeks, with a large number of high-specification servers and high-performance connectivity rolling out in both locations.
These have both been top-to-bottom deployments for us, from consultation, hardware supply, project management, right through to provisioning.
We’re very excited to see these two new systems come online. Amsterdam will be a new location for Netwise, and the roll-out in Frankfurt sees us expand our existing footprint in Germany’s most important data centre hub.
We’ve also had confirmation this week of our plans for fully diverse fibre routes back to our core nodes in THN and LD8, which is great news. The ball is now rolling on installation of these lines, which will provide us with dark fibre access to our existing metro network. Our network will then span five key London data centres.
In other news, we’ve been working directly with TfL to update the content on our travel notice screen in reception at NLC, which will carry over to a the new system being installed at NLE. Look out for the updated screens on-site at our facilities soon!
What’s next?
We will be continuing with progress on outstanding items throughout the holiday season, ready for larger trade work to continue in Q1. This will most notably include the electrical portion of the project – both HV and LV – which will take us right through to the point of onlining the site.
With the internal shell now complete, and with far fewer trades now on-site until the electrical works begin, we’ve been able to get various supplementary works underway across a number of key areas.
The last few weeks have proved to be an excellent springboard for getting things like access control integration started, with the first doors at NLE now online and interacting with our core systems at NLC.
Weekly overview
While final plans and schedules for the LV and HV electrical works continue, we’ve been able to press ahead on-site with a range of supplementary projects which have helped to drive forward general progress.
We’ve spent time on the main access control elements, which will secure the client entry points to the facility. This includes the frame installation of our turnstile, the integration of the main reception door onto the access control system, and the deployment of our lovely new Boon Edam speed gates.
Alongside access control works, we’ve also now flood cabled the first data hall with its final lighting cables, which means we can begin to light the data halls with their overhead LED panels for the first time.
We’ve also had trades back on-site over the past few weeks to bring all doors to full completion, which includes the checking of tile stability around the frames, and adjusting all doors for their opening angles and closing speeds. Given the number of door systems installed, this is quite the undertaking.
Though not something pictured, our lift is now operational, and can move between floors. We’re now just waiting on some final integration work to be undertaken, which will bring that particular element of the project to a close.
The custom frame system we’ve had designed for our cooling plant and cold corridors arrived during this time, which we hope to begin installing in the next couple of weeks, on the lead up to Christmas.
What’s next?
Details are now finalised on much of the HV and LV front, meaning we’re close to having that stage of the project begin.
In the lead up to this, we’ll be continuing with lighting, access control, and the chequer plating of all client areas.
Another major job that will be undertaken both now and throughout the electrical installation works will be the integration of our new CREC system. This will include getting the coolers plumbed, powered and interconnected for their control systems, along with the installation of our custom-fabricated containment frame, which will blank off any cooler bays which are presently unoccupied, as well as providing a mounting location for the extraction louvres.
We’re very excited to show you another transformative fortnight of works on-site at NLE, as the internal envelope of our new data centre reaches full completion.
We’re now looking at a complete internal shell, giving us the physical structure we need to begin installing equipment and deploying electrical services.
Weekly overview
As you can see from the range of shots below, we’re now at a major turning point in this project. The internal shell has now been signed off as complete (with one final pass for minor snags pending), meaning we have the final internal structure of the building set and ready for the next phase of works that will take us into early 2021.
The facility is now presented with immaculate, high specification white spaces for all technical deployments, as well as our usual top tier front of house amenities, something our clients continue to take great advantage of at our London Central data centre.
As you can see in some of the shots of our new doors above, we’re using a fully integrated Paxton system, with the card readers forming part of the handle assembly. This not only keeps our facility access installation as neat and as clean as possible, but will also massively improve the time to onlining the system, as these readers operate wirelessly.
We’ve also been working on some addition access infrastructure, including our main entrance turnstile, and the pedestrian access gates which lead from reception into the technical side of the facility; more on this next time.
All of our lighting cable specifications are now with our manufacturer, who are going to be assembling these for us for compatibility with our Klik system. These are all being made to length, using the specialist Klik hardware, which will enable rapid installation to the overhead grid once it all arrives on-site. This will allow us to light all rooms using the overhead LED panels, and allow for the removal of all temporary site lighting.
We’re incredibly excited to have reached this point, as we now begin what will be the most critical phase of technical works – preparing to properly energise the facility. This is still a little way off of course, however we are now moving into the set of works that will enable this to happen.
What else has been happening?
After a lengthy wait while we got everything just right, we’re now also in a position to tease our new van, which will be the first of our new fleet – aptly named ‘001’.
This, coupled with our custom flight cases, makes inter-facility migrations and new deployments an absolute breeze.
Since our last instalment of the build blog, we’ve also seen new restrictions come into play with regards to the national response to COVID-19. We are of course following these guidelines closely, as we did during the first set of restrictions earlier this year, and will continue to do so.
As a result, we’ve now implemented Test and Trace QR codes at both of our sites, which should be used during normal check in procedures. This helps us to keep everyone safe, and to keep our facilities running without a hitch 24×7, as your businesses rely more heavily than ever before on remote services held within data centres.
What’s next?
With the envelope now complete, we will be moving onto electrical works in the very near future. This includes both internal LV work, and external HV work.
On the lead up to this next phase beginning, we will be undertaking a wide range of tasks to bring other aspects of the project either to completion, or to a stage that makes their completion post-electrical works much more straight forward.
We have three more weeks of fantastic progress on-site at NLE to report, as we rapidly approach completion of the internal envelope.
We’ve seen dramatic changes across the entire facility, as the raised access floor begins to be installed throughout the building, supplemented by ongoing works across a wide range of areas.
Weekly overview
We’re now beginning to see the finished floor surface in the technical spaces for the first time, following the top surface leak protection coating which has been applied to the first floor mezzanine structure.
Aside from the hanging of the internal doors and some cooling plant integration to the rear of each hall, the data halls are now essentially complete, ahead of the first items of equipment rolling into place next month.
Alongside the mezzanine floor surface protection paint, which you can see above, we’ve also completely silicone sealed each room to complete the leak protection in each hall. The cold corridors in each hall will also have a full vinyl tank installed, as the areas which house the CREC units themselves.
We’ve begun lighting the facility with the final overhead LED panels, by temporarily wiring up each of the newly installed Klik boxes. The Klik system allows for rapid installation, along with enhanced control and functionality, including emergency lighting and PIR sensors.
Emergency exit pathways have begun to become more clearly visible in their final guise, with the installation of the emergency LED bulkheads that will light the way to the nearest exit once the facility is open to clients.
Quite a considerable amount of time over the past couple of weeks has been spent in the movement of materials from ingress to final point of use, as the second container of raised access flooring materials arrived with us (not photographed this time around). This has enabled the on-site trades to continue to work at pace as we approach finalisation on the internal envelope.
What’s next?
Works on the floors and access doors will continue into the beginning of November, along with some final finishing trims, which will take the envelope to completion.
The doors have already begun to go in, however we’re saving those shots for the next instalment of the blog, to give a clearer picture of the finished envelope.
Next time around, we’ll also be able to show the completed emergency exit gantry which is now installed at the rear of the facility, which gives a new emergency exit pathway to the rear of the first floor.
Our van is now also complete, but again we’re going to wait for a final detail on that before showing photos – so watch this space!
Further impressive progress to report on finalising the envelope this time around, as we prepare for the final stages of this phase, taking us to the end of our first six months on-site at NLE.
Weekly overview
Week 26 marks exactly half a year on-site at London East. This is quite the milestone, and while we did encounter several minor delays at the beginning of the project (thanks to the initial peak of the COVID-19 pandemic), we’re enormously proud of what’s been achieved in that time.
Much of the first seven or eight weeks were spent undertaking small-scale works in the office to prepare it for housing our management team when on-site at NLE. So realistically, it’s fairer to say that the broader strokes of the project have only been in effect for four solid months, which makes progress – in our eyes at least – all the more impressive.
We’ve had the envelope trades on-site over the past two weeks to continue progress, taking things to the point of readiness for our raised access floors to be installed. The materials for this phase have begun to land with us from our manufacturers in South Africa, the first container of which is seen arriving below.
As you can see, we’re now tantalisingly close to having our completed internal shell handed over to us. We just have the raised access flooring left to go at this point, along with the doors and some final checkerplate wall protection that will follow later down the line.
Having the shell completed will allow for the next phase of the project to begin, that being containment and electrical. While this is underway, we will also be orchestrating the installation of our evaporative cooling system into Data Hall 1.
One of the most exciting points of the project we’ve reached so far is the placement of our first machine plinths, which will hold our cooling system; both the primary evaporative and secondary / supplementary air conditioning units. These are the first pieces of equipment to be placed in their final positions on-site, and while we’re still a fair way off seeing any actual air be pushed through them to live client equipment, we’re very happy to see them sat in place none-the-less!
What’s next?
Next up, the raised access floor will be installed. This will bring the internal shell to a point of completion that allows for the next major phase of the project to begin.
We’ll also be undertaking another deep clean of the facility at this point, to ensure the site is ready for the less invasive, non-construction type works to push ahead inside properly prepared clean spaces.