London East Phase 2 Development Update 2

We’ve been making steady progress on Phase 2 of our deployment plan at Netwise London East (NLE). This includes the total completion of Pod 2 in Data Hall 1, and large strides towards the onlining of Data Hall 2 in the coming months. This will be followed shortly thereafter with the base infrastructure deployment for Data Halls 3 and 4 later in the year.

We’ve been moving ahead firmly across various areas of general infrastructure, electrical and cooling systems for Data Hall 2, with the primary evaporative cooling system now in place ahead of commissioning. The feeder connections from the LV rooms to the in-hall distribution boards are now also in place, ahead of the main electrical works for the diverse rack feeds beginning in the coming weeks.

We’ll keep things brief this time around, so let’s get straight to the update photos:

Cabling
Here we have some of the additional cabling required to bring the next phase online at NLE
Cabling
Each of our data halls require a significant quantity of cabling to link them back to our diverse LV rooms
Cabling
We’ve certainly worked our way through a healthy number of large cable drums at this stage
Cabling
Pulling in these large armoured cables between floors can certainly be a challenge for the teams involved in this work
Cabling
With the main power cabling route handled under the raised floor at NLE, certain areas are cordoned off while works are underway, however disruption is generally kept to no more than a couple of hours at a time, per area
Cabling
These cable routes are already populated with live service power, as Data Hall 1 is fed via the same risers – here we see some new cabling ahead of being tied and cleated
Cabling
The longer of the two routes for the DH2 power delivery is from LV A – here we see the longer run with some of the cabling loose laid into the underfloor ladder
Cabling
The cabling routes flow down the risers to the diverse LV rooms, once they leave the main corridor(s)
Cabling
Considered placement of the large cable drums is vital in ensuring a smooth run-off of the cabling into the raised floor area – the same can be said for the cable rollers
Cabling
Drum placement must consider disruption, ease of access, and result in the least possible amount of free tail once the cable is fully released
DH2
Data Hall 2 has a range of components ready for installation, including some of the distribution boards, and the custom-made ODFs
Cooling
The primary cooling system for DH2 is now in place, that being our evaporative system which famously delivers our world-leading PUE figures
Cooling
As with DH1, we have space for seven CREC units, however we have deployed four initially – it is not expected that additional coolers will be needed, however installing them later would be a straightforward addition
Cooling
The cold corridor filtration system and overhead extraction loop are now complete for DH2 – this is taken ahead of the lights being installed, hence the low light conditions and temporary insulation panels
Pod 2
Pod 2 now has a range of active client deployments within it – in fact, Row C is now almost entirely accounted for
Pod 2
Pod 2 now also completes the full in-hall ODF to ODF pathway using the overhead ladder and trough system
Pod 2
Here’s a view of the back end of Data Hall 1, with both rear Pod entry door systems in view, and the CREC system for this room
Pod 2
This is the view inside Pod 2, as viewed from the rear entry doors
BuildRoom
Our Build and Break Room is now fully fitted out, and sees great use already by our clients
BuildRoom
The function of this one space is split at our London Central facility, which makes use more tricky, so we decided to consolidate amenities at London East for an improved visitor experience
BuildRoom
The wall features continue here, to tie in with other areas of the facility
BuildRoom
We’re particularly proud of our customer kitchen here, which has been expertly installed by our in-house facilities team, to the highest specification
BuildRoom
Be sure to check out the Build and Break Room on your next visit

We now have a dedicated roof hatch system installed over the storage mezzanine, for easier, direct access to the roof, which is important for speedy access to our heat extraction loop. We’ll update readers with photos of this area next time around.

We’re expecting to see a dramatic uptick in progress on Data Hall 2 in the next few weeks, as we head towards the peak activity period which will enable occupation of the space. This will also provide some additional visual change to enable a more in-depth update, which is something which has been lacking since the completion of Phase 1 – we apologise to our regular Build Blog readers for this!