London Central Build Blog – Week 9

Week 9 has seen some more of the Sutton data centre decommissioned ahead of its closure, as well as the extension of our systems in Docklands. The Docklands facilities we use help form part of our global network, giving us access to carriers and connectivity. By operating our own rack space in other key London locations, we are able to maintain end-to-end control over our systems.

Decoupling racks in Sutton ready for relocating

Core system extensions in Docklands

A look across a section of the Sutton data floor after part-decommissioning

The on-site storage facility at our new data centre has also seen advancements this week, with flooring reaching completion ahead of storage rack assembly.

Floor edging installation in storage area

Floor edging installation in storage area

Flooring in storage lobby completed

Flooring in Customer Lounge being laid

As you can see, this week has seen a division of work across 3 sites, making for a very busy period in terms of physical work and planning / orchestration.

London Central Build Blog – Week 8

This week has seen extensive planning for the data floor works to begin in earnest. There have also been finalisations made to the cabling infrastructure feeding the office, as well as preparation works on the core services room ready for cable runs to begin on the network. Because much of the work at the London Central facility has been hidden from view, there are no worthy progress photos for this week, bar one shot showing the flooring in the large ground floor storage area reaching completion.

Flooring reaching completion in storage area

One area of interest is the secondary team decommissioning the London South (Sutton) facility. The office space has seen a transformation back to its post-refurbished empty state. We took great pride in the building of our Sutton facility, and it is saddening to see it decommissioned, however we are moving on to far bigger and better things in Bermondsey.

Furniture being removed from London South office space

Removal of Netwise Hosting signage from Sutton office

We will have some further pictorial updates for you in the coming weeks.

London Central Build Blog – Week 7

This is a pivotal week for the project, in that migratory planning and preparations will be in full swing alongside build works. Works are now ready to begin on network and power for the data floors, which will see the project enter into it’s second phase – technical engineering.

Custom double-width bookcase for our board room

Lighting system being fitted to board room book case

Lighting being tested before positioning of the unit

Lighting being tested before positioning of the unit

A closer look at our new 50" board room monitors

Flooring reaching completion in the office kitchen

Flooring being laid in ground floor storage facility

Flooring being laid in ground floor storage facility

Flooring being laid in ground floor storage facility

Flooring being laid in ground floor storage facility

London Central Build Blog – Week 6

Further transformations have been made to the offices this week, with completion of various areas including the shower room and board room. Some of the office furniture from Sutton has now been migrated to the new site. Full office operations are expected to function from Bermondsey very shortly.

On-going works to power systems

Shower facilities ahead of new flooring

Tiled flooring completed in the shower room

Our new Vitra boardroom table with seating for 8

Flooring in the first floor corridor taking shape

Threshold between office carpet and completed corridor tiling

Flooring taking shape in the male toilets

First layer of glazing installed into vision panels

The first data hall ready for final structural works

Completed office-side vision panels

Sideboard ready for board room screens

Completed Recycling Station with lighting

Completed decoration of ground floor storage areas ahead of new flooring

Completed decoration of ground floor storage areas ahead of new flooring

Completed decoration of ground floor storage areas ahead of new flooring

A look across the office as furniture begins to be placed

Our brand new 50" board room monitors

Completed sound proof glazing in vision panels

Completed flooring in male toilets

Completed flooring in male toilets

As you can see, the amenities at the new site are rapidly reaching completion. The final migration of office furniture and systems will be taking place imminently.

London Central Build Blog – Week 5

Week 5 has been truly revolutionary for the office space, with a tangible change for building site to a space ready for occupation.

Test mount of our 4x 40" NOC screens

New carpet laid in the staff lounge

Carpet in the main office beginning to take shape

Carpet in the main office spreading across the space

Carpet reaching the feature wall to the rear of the office

Office carpet cut in around the complex glass atrium

A look at the detailed edging which encircles the office space

Line of grey carpet at the edge of the new board room, ahead of glass partitioning installation

Main office carpet reaching completion

A view across the office, with decoration reaching completion

Installation of custom Recycling Station under way

Recycling Station cabinets being installed

Recycling Station reaching completion

The offices are now rapidly approaching a state fit for occupancy.  We will be installing the final items in week six, after which point the office will be migrated.