It’s been a while since we last published a Phase 2 update from Netwise London East (NLE), so we thought it would be a good time to update everyone on the current state of play.
We’ve been remarkably busy with both the ongoing expansion works at NLE, alongside the closure of Netwise London Central (NLC), which was retired from active service in early June.
Data Hall 4 went live in May, and quite remarkably, it’s already a touch over half full, despite opening to new clients just a couple of months ago. This is in large part thanks to the absorption of our customer base from NLC, which we migrated over the course of eight evenings in May, however we have also welcomed a host of exciting new clients into our latest data hall.
Let’s take a look at what’s been happening. We start with updates from back in mid-April, before jumping ahead to current day:
It’s fair to say that this summer has already been one of our busiest periods on record. Deploying a new data hall at NLE is no small task in itself, but to deliver this alongside the decommissioning of NLC – which also involved the in-house planning and execution of an entire facility migration – leaves us feeling incredibly proud of the team we have driving Netwise. The complexity of successfully realising a multi-faceted project like this cannot be understated, and seeing these tasks result in tangible improvements to service for our clients is always incredibly pleasing, particularly after making seven figure investments in our future here at London East.
But as with any operation of this nature, these are just the headline deliverable outcomes that have been worked on over the past several months. We’ve undertaken plenty of additional projects in tandem over the last quarter, which may be of interest to our readers.
We completed our full core network upgrade in May, with the final upgrade – and the most major works list – happening at our HEX/LD8 node. This involved a full conversion of this location to our Supernode architecture, which in this case required a full cabinet swap to accommodate. This type of thing requires considerable planning, however our team were able to complete the entire works list within the four hour maintenance window, which was an impressive feat. We also undertook a minor upgrade to our core node in Redcentric Shoreditch (formerly CLL), which brought the entire network upgrade project to completion. This comes as demand on our network grows rapidly, delivering world-class connectivity to clients across all of our on-net locations.
We also grew our fleet in spring, with the addition of an electric pick-up truck, and our own low-loader, which is perfect for rack migrations. The latter vehicle comes in a relatively rare specification for us, with extra height and a 750kg tail lift, which makes it absolutely ideal for the movement of fully populated racks – a game changer for most facility migration projects.
As part of bringing Data Hall 4 online in May, we rolled out new cooling system architecture, which involved some adjustments to how the extraction side of the system works. We now have a twin-hall shared extraction plenum, with a centralised control system, which we believe to be the first of its kind for an evaporative system such as ours. This involved the expert design work of multiple teams, and will also be a part of the roll-out for Data Hall 3 later this year.
Further to this, we have additional cooling being deployed in all data halls in the next few weeks, through the modular installation of further evaporative coolers. Each room is growing from four CREC units, to six CREC units.
NLC closure and migration project
In May, we migrated all of the clients in our London Central facility to our new London East facility.
This took many months of planning, however we were able to complete the physical migration process in just eight evening sessions – a real testament to our broad in-house capabilities.
All 126 enclosures were successfully transitioned to our London East facility (with a few landing in other on-net locations where required), with most racks moved in a fully-populated state. This allowed for minimal client disruption, and the fastest possible transition from one site to the other. The fastest migration window took just two hours, from power down at NLC, to being back online at NLE.
Here we have some photos of the now retired facility, which served our clients well for nearly a decade:
The end of an era, but the beginning of a truly special new chapter for Netwise, as we focus on our campus site, London East. We will be expanding this location significantly in the coming months – more on this very soon.
What’s next?
The biggest upcoming build work will be the onlining of Data Hall 3, the final hall in the current building at Netwise London East. Work will begin on this hall in the coming weeks. This will be the final component of Phase 2, before Phase 3 works begin in late 2024 / early 2025 – this will be a major development phase.
We hope to announce the next phase of works in an official capacity in the next few weeks.
Otherwise, we will continue to welcome new clients to our world-class facilities, along with the provision of assistance to existing clients looking to grow. This is an exciting time for Netwise, and we look forward to sharing more news with you very soon.