Our significant expansion of Netwise London East (NLE) is now well underway, which is Phase 3 of development at our flagship data centre.
This will result in the addition of two new data halls, alongside a range of additional amenities and site features. Works began in December 2024, and will continue throughout 2025, with various completion milestones at multiple stages along the way.
The main focus at this stage is the installation of the new mezzanine, as this forms the basis of the entire internal sub-structure, around which we build our facilities (as seen at our London Central site, and also the current footprint at London East).
Here are some photo updates from the early stages of Phase 3:
As you can see, we’ve been able to make quite an impressive start to the project. To have the mezzanine complete in the first week of January sets up our work schedule incredibly well, allowing for the envelope to begin later this month.
We have also now started a range of other preparatory works ahead of this, including the insulation and closure of the skylights, encasement of the columns with fire protection, and some of the breaching works for interconnecting the units and other internal areas.
We have more updates coming as part of Phase 2 soon also, so watch this space for plenty more build content throughout Q1 2025 and beyond.
This month we’re very happy to officially announce the next major phase of development and expansion at our Netwise London East (NLE) data centre.
We’re facilitating this expansion by pushing into the adjacent building on the Datapoint estate, which sits alongside our existing four-hall facility. This will result in a single expanded facility housing six high-specification data halls.
The initial fit-out phase began in July, with the main internal schedule of technical works set to begin in early 2025. This project will expand NLE by 168 racks, increasing the total internal area of the building by around 13,000ft2.
The new building is being fully refurbished – both inside and out – following the departure of the previous occupants, ahead of the main work schedule which will start thereafter.
This is our first major step towards developing NLE into a campus-style facility, which spans multiple buildings on the same estate. The two units will become a single operational building, with multiple pass-through points for clients and staff, as well as for the sharing of core services.
Alongside the additional rack capacity, this new space will also introduce further amenities and technical features, including increased capacity for staff, a second loading bay and storage area, more on-site parking and EV charging, as well as improvements to our water handling capabilities.
There will also be flexible space held for future use, which will provide additional service options for potential wholesale customers, for things such as private on-site NOC capabilities.
"This represents another seven-figure investment by Netwise in its own future, and the future of its clients. To be announcing this level of growth at NLE only a couple of years after the first clients moved in is something we're very proud of; it's a testament to the strength of this sector, and our own position within it."Matt Seaton, Director
The uptake of services at NLE has been extremely impressive since it soft-opened in the spring of 2022, with the phased fit-out schedule just keeping pace with demand. The current building now has three of the four data halls deployed. The final hall in this building is scheduled to be online by the end of 2024.
The two new halls coming as part of the facility expansion project will be larger than the halls in the current building, housing 84 racks per hall at maximum rack density – a 33% increase per hall. These new halls will house three containment pods each, giving greater scope for private space options.
In June, the Netwise London Central (NLC) facility officially closed, having served clients for 10 years. The forthcoming expansion at Netwise London East would become one of the main driving factors behind the decision to shutter NLC, as many core components within the site reached end of life.
The large seven-figure reinvestment required to adequately refresh NLC has instead been diverted to the new facility, which has the forward-looking scope to springboard Netwise into the next phase in its growth cycle.
The NLE expansion comes as Netwise continues to welcome an exciting range of new clients into its facilities, as well as facilitating the growth of its long-standing customers.
"We always knew that we'd be expanding NLE in time, to facilitate our growth trajectory, however to be at that stage already is a tangible demonstration of our performance and reputation in this industry. I'm very excited by this next phase, particularly as we come out the back of the NLC closure, which required considerable care and attention."Matthew Butt, Managing Director
The expansion of NLE will bolster our position as a leading data centre operator in the high-demand East London / Docklands region, as we further the already significant investments made in our flagship facility, which has been in operation since mid-2022.
While finer details of the technical plans are still expected to develop over the closing months of 2024, the overarching plans are already locked in, and can be discussed with interested parties that may be looking to utilise bulk space in the new side of the facility.
The Netwise team cannot wait to show you around the new side of the facility as it develops. And as always, the #buildblog will be back in action, documenting the entire build process, so be sure to keep an eye out for new posts.
It’s been a while since we last published a Phase 2 update from Netwise London East (NLE), so we thought it would be a good time to update everyone on the current state of play.
We’ve been remarkably busy with both the ongoing expansion works at NLE, alongside the closure of Netwise London Central (NLC), which was retired from active service in early June.
Data Hall 4 went live in May, and quite remarkably, it’s already a touch over half full, despite opening to new clients just a couple of months ago. This is in large part thanks to the absorption of our customer base from NLC, which we migrated over the course of eight evenings in May, however we have also welcomed a host of exciting new clients into our latest data hall.
Let’s take a look at what’s been happening. We start with updates from back in mid-April, before jumping ahead to current day:
It’s fair to say that this summer has already been one of our busiest periods on record. Deploying a new data hall at NLE is no small task in itself, but to deliver this alongside the decommissioning of NLC – which also involved the in-house planning and execution of an entire facility migration – leaves us feeling incredibly proud of the team we have driving Netwise. The complexity of successfully realising a multi-faceted project like this cannot be understated, and seeing these tasks result in tangible improvements to service for our clients is always incredibly pleasing, particularly after making seven figure investments in our future here at London East.
But as with any operation of this nature, these are just the headline deliverable outcomes that have been worked on over the past several months. We’ve undertaken plenty of additional projects in tandem over the last quarter, which may be of interest to our readers.
We completed our full core network upgrade in May, with the final upgrade – and the most major works list – happening at our HEX/LD8 node. This involved a full conversion of this location to our Supernode architecture, which in this case required a full cabinet swap to accommodate. This type of thing requires considerable planning, however our team were able to complete the entire works list within the four hour maintenance window, which was an impressive feat. We also undertook a minor upgrade to our core node in Redcentric Shoreditch (formerly CLL), which brought the entire network upgrade project to completion. This comes as demand on our network grows rapidly, delivering world-class connectivity to clients across all of our on-net locations.
We also grew our fleet in spring, with the addition of an electric pick-up truck, and our own low-loader, which is perfect for rack migrations. The latter vehicle comes in a relatively rare specification for us, with extra height and a 750kg tail lift, which makes it absolutely ideal for the movement of fully populated racks – a game changer for most facility migration projects.
As part of bringing Data Hall 4 online in May, we rolled out new cooling system architecture, which involved some adjustments to how the extraction side of the system works. We now have a twin-hall shared extraction plenum, with a centralised control system, which we believe to be the first of its kind for an evaporative system such as ours. This involved the expert design work of multiple teams, and will also be a part of the roll-out for Data Hall 3 later this year.
Further to this, we have additional cooling being deployed in all data halls in the next few weeks, through the modular installation of further evaporative coolers. Each room is growing from four CREC units, to six CREC units.
NLC closure and migration project
In May, we migrated all of the clients in our London Central facility to our new London East facility.
This took many months of planning, however we were able to complete the physical migration process in just eight evening sessions – a real testament to our broad in-house capabilities.
All 126 enclosures were successfully transitioned to our London East facility (with a few landing in other on-net locations where required), with most racks moved in a fully-populated state. This allowed for minimal client disruption, and the fastest possible transition from one site to the other. The fastest migration window took just two hours, from power down at NLC, to being back online at NLE.
Here we have some photos of the now retired facility, which served our clients well for nearly a decade:
The end of an era, but the beginning of a truly special new chapter for Netwise, as we focus on our campus site, London East. We will be expanding this location significantly in the coming months – more on this very soon.
What’s next?
The biggest upcoming build work will be the onlining of Data Hall 3, the final hall in the current building at Netwise London East. Work will begin on this hall in the coming weeks. This will be the final component of Phase 2, before Phase 3 works begin in late 2024 / early 2025 – this will be a major development phase.
We hope to announce the next phase of works in an official capacity in the next few weeks.
Otherwise, we will continue to welcome new clients to our world-class facilities, along with the provision of assistance to existing clients looking to grow. This is an exciting time for Netwise, and we look forward to sharing more news with you very soon.
It’s been another very busy stint of work over at Netwise London East, as we continue to deploy Data Hall 3 and Data Hall 4.
While we’ve taken a relatively lengthy break from the #BuildBlog since the last update, the same cannot be said for the development schedule itself, which has been continuing at pace without pause.
Let’s get straight to the photo updates:
This all sits alongside a whole host of additional organisation-wide projects, which includes the full upgrade of our entire core network, across all on-net locations. This will see the staged upgrade of all routing assets on our core network, to cope with ever-increasing demand from our clients. Telehouse has already been undertaken, with our London East site to follow in the next couple of weeks. Equinix LD8 will follow shortly thereafter.
We’ve also had another major round of development work undertaken on our customer portal. This predominantly concerns the backend of the system, with a custom IPAM administration and deployment module now live. We also have additions to the client-side coming very soon, which will improve the booking, tracking and handling of deliveries.
We’re tantalisingly close to announcing some very significant expansion news, but we’ll have to hold back on that for a little while longer – keep an eye on announcements in the coming weeks / months.
We’ve been reasonably quiet with the #BuildBlog of late, with focus squarely on the deployment of additional capacity at London East, leaving little room for deep dives into progress (unfortunately!).
But we’re now back with this latest instalment, as we begin tracking progress on Data Halls 3 and 4.
Looking back on our last instalment of the build blog, Data Hall 2 was still very much under construction. This space is now fully fitted out as a private data hall for a single client, and is now under occupancy.
We’ve also got plenty of other updates to report across a range of areas within our London East facility, thanks to an ongoing development programme which extends beyond footprint capacity alone.
Let’s move onto the update photos. This first set were actually taken back in June, however the next instalment of the build blog ended up getting significantly delayed, so here they are:
Now we can catch up in time to where things stand today, with the next run of photos from the past couple of weeks – apologies for any gaps in progress, we’ve been very busy!
As you can see, despite the delay in getting this build blog instalment posted, we’ve been rather busy.
We’ll continue to get our head down with development work on the run up to the new year, as demand for our services remains exceptionally high. We hope to have another update prepared for our avid readers in the next couple of months.
We also have some further news on the horizon with regards to continued expansion, which we hope to be releasing early next year. Needless to say, we’re very excited for what 2024 will bring.