London East Phase 3 Development Update 5

With focus turning back to Phase 3 in Q4, following the completion of Phase 2 in Q3, we have some updates to relay as the build schedule for Data Halls 5 and 6 begins to gain traction again.

Development work continues to see a certain level of distribution across both the operational side of the facility, as well as the new expansion. Despite Phase 2 now being complete with the onlining of Data Hall 3, we had an additional works list for the active side of London East, which will see the improvement of various functions and features throughout the facility.

Let’s get straight to the updates for Phase 3:

Exterior
The new perimeter fencing and associated access routes have seen lots of progression since the end of the summer
Exterior
Here’s a wider contextual view of the new Unit 5 frontage, with the existing frontage of Unit 6 in view on the right hand side
Exterior
The view from the main east-side entrance to the Datapoint estate, looking across what is now the full extent of the London East facility footprint
Fencing
Here we see the turnstile installed for the first time, ahead of access control implementation in the new expansion space
Fencing
The new vehicle access gate opening is now ready for installation of the 5-metre folding gate itself
Entry U5
The new gate is now hung ahead of automation, and the full perimeter has had its razor wire fitted along the top to match that of the existing perimeter
Exterior
This is the view of the new Unit 5 frontage from the main entrance of the Datapoint estate, following the completion of the perimeter (aside to full access control implementation)
Exterior
Access control integration is now well underway, which will enable the onlining of the main entry points to the new footprint, which all remain in a physical hard-locked state at this point – signage and panelling has now also seen completion in this area
Exterior
As part of this same work-set, the client entrance to Unit 6 (which will remain the main client entrance after the expansion project is complete) has been fully refreshed, with new panels and signage, as well as a new small package drop box
Access Control
The access control systems are being deployed in the front of the new footprint, which will ultimately control the entry and exit process on this side of the facility
Fencing
A side access gate has also been installed, which will securely isolate the new external plant area from the additional parking facilities in the front
Fencing
Here is a view of the side and rear perimeter as completed
Fencing
The new vehicle gate is centre-folding to accommodate different space constraints on this side of the facility, unlike the sliding gate deployed as part of the existing frontage
Exterior
Here is an elevated view of the main entrance to the new space, along with the fencing installation in this area – the new logo is on it’s way to us for installation soon
Exterior
Here we have an elevated view across the active centre of the London East facility, and onward to the new expansion project – the newly added Unit 7 is just visible on the right hand side
Unit 7
This elevated view shows the full extent of the London East footprint, following the successful integration of Unit 7 into Netwise control
Exterior
The addition of Unit 7 completes our footprint control strategy for the London East facility
Fencing
Work on the new expansion project continues across a wide range of areas, including work on the roof which requires specialist access equipment
Door Openings
The new door openings across the facility have seen progression, but remain in a ‘roughed-in’ state in non-technical spaces
Door Openings
The new openings have been framed out head of repair work to refinish adjoining surfaces
Walls
In the new office and meeting room area of the expansion footprint, first fix adjustments have begun to enable certain areas to be refinished, in keeping with their new use case
Walls
Here we see plasterboard being prepared to cover the block wall in the office area
Walls
The new surface here will form one of the new private offices, along with the glazed corridor for accessing the rest of the spaces in this area
Walls
One major component of making the new office and meeting space work is acoustic treatment – there have been many engineering meetings to discuss how best to implement this, as an additional layer to the main composite wall structure
Walls
The acoustic treatment in this area creates a new isolation barrier, which will form one side of a new access corridor, leading to the offices and meeting room
Wall
The main sound insulating wall is approaching initial completion here
Wall
The new office and meeting room area will bring a new visual language to our facilities, as we are working with an interior designer to really make this spaces shine
Wall
This view is from the new meeting room, looking down what will be a glazed corridor leading to the offices, breakout area and second NOC
Breach
This area will be the new staff breakout and kitchen area, sitting between the new NOC space and the offices / meeting room
Breach
The breach points between the technical areas of the facility have now been trimmed out – this is the first floor breach point
Breach
Here we see the ground floor breach point
Breach
We’ve also trimmed out the additional breach on the ground floor which runs between the front of house and the technical spaces on the ground floor
Warehouse
The racking in the new warehouse / loading bay in now complete, and is primarily used to store materials ahead of their eventual requirement as part of the build project
Flooring
Various materials are now being distributed across the facility – the raised floor materials for Data Hall 5 have now landed in the hall to acclimate ahead of installation
Flooring
The technical spaces within the facility are set to see transformation in the early stages of 2026, as the containment works begin in full force
Walls
Further apertures have been cut for cable access in various areas throughout the facility – here we see a range within one of the new UPS rooms, ahead of final trimming
Elec
Some of the new electrical boards have started landing ready for deployment in time

We’re naturally very pleased to see progress pick back up on the Unit 5 expansion project (Phase 3), given that this had to take a backseat during the close-out of Phase 2.

In the early stages of 2026, the build schedule will move more firmly back towards technical works, as containment will begin flowing in ahead of the main flood-cabling action.


Supplementary works on the active side of the facility

In addition to the main build phases / schedules, we’ve spent time on

Earthing
Alongside the continuation of works for the Unit 5 expansion, we’ve also had additional second-path earth deployed on the existing backup gen-sets
Earthing
The adjustments made here were of course non-service impacting, and result in an improvement to earthing redundancy as a safety improvement on this backup power delivery system
Earthing
You’ll now see multiple earth pits around the generator area in Unit 6
Earthing
The new earthing rod installation is an example of iterative improvement on existing systems (as opposed to a set-and-forget mindset), and undertaken by our in-house electrical engineering team
Reception
The main client reception has seen adjustments to the check in area, to streamline the arrivals process ahead of some procedure changes landing in the new year
Reception
We now have a twin iPad setup for our check in app, which enables faster check in for visits with multiple engineers, or where multiple clients arrive at the same time

We’re also happy to leak some preview shots of our new customer portal, which is under development and will be launching in 2026. This is something that’s been in the works for a while, a collaboration between our own team, as well as a UI/UX designer, and our development partner, and we’re very excited to get this pushed out to clients next year.


More on the Unit 7 expansion

As you may have already seen from our official announcement post, we have now secured Unit 7 of the Datapoint estate, which joins Unit 5 (our current expansion project) and Unit 6 (the live footprint), creating a single ~38,000ft² facility, and giving us total control over the entire free-standing building and secure compound areas.

Work has already begun on this side of the footprint, with the initial refurbishment works now complete, and the exterior perimeter bolstered to a pre-conversion state.

U7
Initial refurbishment works have been undertaken in the new space, ahead of our own works schedule in due course – this readies the shell for conversion as the next phase of expansion at NLE (Phase 4)
U7
Refurbishment works spanned the entire footprint of Unit 7, including some significant layout adjustments internally to ready the space for eventual conversion
U7
A view of the front of the new space, as initial refurbishment works are undertaken
U7
Here we see preparations underway for the new perimeter fencing, to enclose the entire NLE footprint, which required adjustments to the demise line and external slab / drainage
U7
We will be largely completing the Phase 3 expansion works in Unit 5 ahead of starting on Phase 4, however there may be some developmental cross-over later in the Phase 3 build cycle
U7
As with both other footprints that make up the London East facility, the new space brings with it plenty of opportunity for expanded amenities for both customers and staff alike
U7
The new footprint is now back to the same matching baseline condition as the prior footprints ahead of their conversion – we’re very excited to see this new space come into the Netwise London East fold
U7
A view of the new space as seen from the corner of the front compound
U7
Taking on Unit 7 provides masses of additional compound space, which has now been fully enclosed in our palisade fencing – this will have the razor wire and our own specialise access control automation added later
U7
Having full control of the perimeter, as well as masses of additional space for parking and plant equipment, is a welcome addition to the NLE ecosystem
U7
The full-width frontage of our London East facility, which now encompasses the entirety of the south side of the Datapoint estate, makes for quite an imposing approach

We’ve had yet another incredible year here at Netwise, which we’re please to top off with a final build blog post update for our readers.

We’ll have another year in review landing in January, as is tradition, but in the meantime we’d like to wish everyone a very merry Christmas, and a happy New Year. We’ll see you in 2026 for further progress on our multi-faceted expansion schedule.