Our significant expansion of Netwise London East (NLE) is now well underway, which is Phase 3 of development at our flagship data centre.
This will result in the addition of two new data halls, alongside a range of additional amenities and site features. Works began in December 2024, and will continue throughout 2025, with various completion milestones at multiple stages along the way.
The main focus at this stage is the installation of the new mezzanine, as this forms the basis of the entire internal sub-structure, around which we build our facilities (as seen at our London Central site, and also the current footprint at London East).
Here are some photo updates from the early stages of Phase 3:
Some of the earliest works centred around a full internal and external renovation of the new unit, including a significant amount of work on the roof
The exterior cladding of the building also enjoyed a full refinish, which will become evident in later photos
This is the view across to the expansion project within the new unit, from the existing facility entrance / footprint
The inside of the new space also required significant refurbishment before our main works schedule began
The front-of-house areas also got completely ripped out ahead of a total refurbishment
We’ll be adding further office and administration spaces in this new side of the facility, and the existing upstairs office also saw a full strip-out ahead of refurbishment
This is the main frontage of the extended footprint after the completion of the initial refurbishment, ahead of our main works schedule commencing
This space will become a second / extended NOC and operations space, after the initial refurbishment, and with the new carpet covered ready for the next phase of work to begin
The site has been fully prepared for our main work schedule here, including all protective covering of newly installed surfaces, and the various required temporary site boards and signage in place
The temporary signage extends to all areas of the site
One of the existing ground floor spaces has become the on-site canteen and break room, ready for the various contractors that will be working on-site in the coming months
One of the early stage jobs, beyond our initial laser survey of the space, is to laser plot the main column locations for the new mezzanine sub-structure
With such a high degree of accuracy required for the installation of the mezzanine, collaboration between engineers, project managers and installers is key
A view across the main space, as column locations are marked up according to the installation plans
Here are some of the many heavy-duty custom steel columns as delivered, ahead of installation
A view across the main space, following the initial refurbishment, as the main work schedule begins
Another view across the main space, following the initial refurbishment, as the main work schedule begins
The mezzanine sub-structure is a surprisingly quick component to install, with much of the work front-loaded during the planning and engineering phase
The mezzanine is installed in bays / sections, and progresses across the space from the initial column locations
A view of the mezzanine progress from the rear corner of the new space
We have an installation timelapse of the mezzanine install, which we’ll be making available in the near future – 19,000 photos in total!
Here we see part of the structure standing in isolation, ahead of the installation of the purlins that will make up this particular bay
This is the underside of a partially complete bay
Here we see further progress, as the temporary safety netting is installed to the underside of the mezzanine ahead of installing the top surface
The main beams are partially assembled on the ground, ahead of lifting into place
A view of progress as the mezzanine structure continues to take shape
A view of the underside of the structure, as top surface boards begin to be positioned
The boards are fixed to the structure, and will form the initial face upon which the next stage is built, which will be the main envelope
Here we look down from the partially completed half of the structure, which will continue across this span to the far side of the space
Despite the expansion project taking place within an adjoining unit to the existing live footprint, the two spaces will be combined into a single facility – as part of this, we will be breaching between the two units; we have installed temporary dust and fire barriers, ahead of the cut through process
Here we can see the initial breach of the outer skin of the envelope within the ground floor corridor
Progress continues with the mezzanine installation
The view here is taken from what will eventually be the cooling plant area for Data Hall 6 – the two halls within this new expansion will be larger than those within the current footprint, each housing three containment pods
The final columns being cross-checked after installation, as the mezzanine continues towards completion
A view back across the mezzanine structure, as works progress
The scissor lifts work in conjunction with our forklift in getting components to the correct height for installation
The view looks across the area that will make up Data Hall 6 on the ground floor of the new space
This view is from the approximate eventual location of Pod 3 within Data Hall 6
All parts of the steel structure are now complete, with only the remaining top surface installation to go
The view here looks across to the outside face of the facility, which will house offices, a new meeting room, and supporting electrical infrastructure for the new data halls
This is the view from the top surface as it continues towards completion – this is taken from the eventual first floor corridor, looking into the area that will house Data Hall 5
The top surface installation continues here
Members of the Netwise team undertake regular inspections as part of the installation process
This view sits on the edge of what will become the B-side UPS and switchgear room for the two new data halls, and the associated cable access corridor (a new cable handling methodology that we’re deploying as part of the expansion) – the new meeting room will be directly above this
Here we see the underside of the completed mezzanine structure
Another view of the completed mezzanine, as viewed from the eventual location of Pod 3 in Data Hall 6, looking towards the eventual location of the UPS rooms and cable access corridors
The completed structure, as seen from the new loading bay area, with temporary barriers in place until the envelope is installed
The next action on the underside of the mezzanine structure will be the column encasements
Here we see the top side of the new structure, as some minor additional works begin on the sky lights
This is the view from the eventual location of Pod 3 within Data Hall 5, looking across to the eventual location of the new offices and meeting space
Our scaffold tower is being used for roof-level access now that the top surface is complete
The insulation and closure of the sky lights can be seen underway here
All of the sky lights above the data halls will be insulated and closed off as part of the pre-envelope works, which replicates the setup in the existing live data halls
Our facilities team are undertaking this work, ahead of the next major contractor stage – the envelope
The view down into the new loading bay, as viewed from the edge of the mezzanine, where the access corridor will be located – there will be level loading capabilities here, as with the existing loading bay
As you can see, we’ve been able to make quite an impressive start to the project. To have the mezzanine complete in the first week of January sets up our work schedule incredibly well, allowing for the envelope to begin later this month.
We have also now started a range of other preparatory works ahead of this, including the insulation and closure of the skylights, encasement of the columns with fire protection, and some of the breaching works for interconnecting the units and other internal areas.
We have more updates coming as part of Phase 2 soon also, so watch this space for plenty more build content throughout Q1 2025 and beyond.
Related