Now that raised floors have started to go back down, and termination of cabling is essentially complete, impactful visual change has slowed down slightly, however progress is still pushing forwards at great pace.
We’ve been preparing for some of the final trades to land on site to end-out phase one, which will include the CRAC pipework team and the wall fabrication team from earlier in the project, who will be finishing off some of the final cooling system segregation now that the fans are installed.
Weekly overview
Much of the change this time centres around supplementary cooling, VESDA / fire panels, and data cabling for things such as CCTV, access control and monitoring / system control.
We’re now very much in the end-out phase of the project at this point, which means that various elements that until now were operating separately are coming together quickly.
For example, our evaporative cooling units are now connected back to both their power delivery and control systems, meaning that they will soon be ready for their first spin up and test. This is the same for a number of the core systems which make up the infrastructure of the facility.
We’re getting to the point at which photographing visual change is likely to slow down somewhat, as we move onto more detailed work such as the interconnection of critical systems, and the onlining of various electrical elements including CCTV and door access control.
Excitement is starting to build as the many months of extremely hard work from all those involved begins to show its final fruits, which will become all the more exciting as we start to see systems roar into life.
What’s next?
While build and installation works will continue in a few final areas – such as CRAC pipework, final airflow containment for extraction in Data Hall 1, and the end stages of general system containment – we are now also in a position to begin the early-stage commissioning process.
We are entering an exciting phase of the project, as things finally begin to slot back into place after a good few months of ordered chaos; a necessary evil associated with the extensive electrical work required to take the building from completed shell to functioning data centre.
Over the next few weeks, we expect to see the site visually return to a state of completion (for phase one), at which point the site will be onlined, and commissioning of critical systems will begin in earnest.