Things are really heating up now in terms of progress on-site at NLE, as we document another three weeks of work at our forthcoming data centre.
We’re almost at the one year mark in terms of when we first gained access to the new building, and despite some setbacks early on due to the Coronavirus pandemic, we’ve been extremely pleased with how quickly we’ve transformed the site from shell to data centre.
We’re not quite there yet, but we’re getting ever closer!
Weekly overview
The last three weeks have seen tremendous progress across a wide range of project areas. The most notable changes have centred around the physical adjustments to the rear of the facility, as the first set of louvred intake panels are cut into the exterior walls for Data Hall 1.
As we hope is self-evident, the visual and functional change on-site has been noteworthy, to say the least.
Big advances have been made in containment, which helps move the project along in many areas. Our fire contractors are now able to bring all systems together, and complete the VESDA and extinguishant panel integrations with the main building system.
Having Pod 1 reach point of completion from an assembly perspective is also a major project milestone, and gives a tangible focus point for any tours of the site ahead of it opening.
What’s next?
Next week we will reach 12 months on-site at NLE, although due to COVID-19 restrictions early on, we’re probably more like 9 months of true work into the project.
The next set of louvres will be installed in the next week or so, along with further works on various open projects. This all falls alongside larger project work, which will see broader stroke progress as the build continues towards full onlining in the next few months.