Our team enjoyed some much-needed time off over Christmas, following a long run of works on-site at NLE in the closing months of 2020.
This first instalment of the Build Blog for the new year shows the current state of the facility as we head firmly into 2021 – the year in which our new site will launch to clients for the first time.
Before we start, did you catch our NLE envelope time lapse video? If not, here it is again for your viewing pleasure!
Weekly overview
The first few weeks of January have primarily been comprised of desk work, bringing end-out plans together as we enter the next phase of development.
As part of this, we’ve made great strides in finalising plans for our diverse dark fibre routes, which we will be announcing very soon.
Aside to planning work, we’ve also been completing some smaller tasks on-site, which have helped keep progress up despite the Christmas break and the focus on more general plans and scheduling.
So here’s an update of photos showing additional work completed since our last update, along with some general site photos to serve as a starting point for the Build Blog in 2021.
The checkerplate is the most obvious visual addition since the last instalment of the Build Blog, covering the walls in all high foot fall customer routes. This gives much-needed protection and a great deal of added visual energy to the space. Custom plates for all high risk doors will also be installed soon.
The reason for having most of the ceiling tiles still in a state of removal is simply for ease of ongoing access. We still need easy accessibility above the grid for cabling overhead services during the build, and as such we will only be installing the tiles once access requirements calm down. This is to ensure the tiles are installed with the least amount of disturbance once in place.
As you can see from the wider facility photo set, the progress made in the last ~8 months is impressive to say the least. As a reminder of where we’ve come from in that time, we’ve included a set of day one photos of the space below.
What our team have managed to achieve in this time is staggering (even more so as this all occurred in the middle of a global pandemic!), and we’re incredibly proud of everyone involved, particularly as we move onto the next phase of energisation, preparing us for launch later this year.
What else has been happening?
We’ve expanded our team!
We’ll be making the official announcement soon, although the hawked eyed among you may have already seen this causing quite a stir online.
We’ve also been going through our first ISO recertification audit, following our initial accreditation to both ISO 9001 and ISO 27001 back in 2017. This will renew our certificates for another three years, with annual surveillance audits covering the 12 month cycles in between. The scope of our certifications will be expanded later this year, to include the new NLE site. This is our first fully remote audit, thanks to the COVID pandemic, which has been an interesting new approach to the audit process.
What’s next?
Planning on the next phase of electrical works will continue, with a number of exciting developments to announce very soon.
We’ll also be continuing with a wide variety of supplementary works, which will includes taking delivery of our first customer enclosure pod; racks, containment, blanks etc, which will allow us to layout our first occupiable colocation space within Data Hall 1.