Massive changes to report this time around, as the walling installation works begin at NLE, zoning the building into its final room layout.
This comes along side a range of other works that have seen a huge, tangible evolution of the site as we head into the final phase of the envelope installation.
Weekly overview
What a three weeks we’ve had on-site here at NLE. The walls have really started to take shape, with the first floor data halls now visible, along with some of the main access corridor and customer breakout / build room. We’ve also had the ground floor to first floor riser access holes cut into the mezzanine floor, ready for our future inter-floor service routes.
Our lift installation is now also underway, with the main vertical runners and lifting mechanism now in place. This will be enclosed by the shaft in the coming weeks, and the platform will be installed.
The ground floor of the facility has also had all fire protection for the mezzanine structure installed, which is another great milestone in terms of having that component of the envelope fully finished.
We now have 25 tonnes of insulated wall panelling on-site, ready for installation. This will be followed by nearly 33 tonnes of raised floor, and several tonnes of hung ceiling flown overhead in each hall.
Those with a keen eye will notice that the current door openings cut into the walls would not be correct when factoring in our raised floor. These are currently temporary cut-outs for positioning and site access, and will have their height increased (along with base boards installed) later.
We’re incredibly excited to see the site reach this stage. Of course we still have quite a way to go, with several weeks remaining on the envelope stage alone, however seeing the rooms take shape on-site is a massive milestone.
What else has been happening?
Our new van is now almost finished, and we’re very excited to show you what she looks like! We’re very impressed with how she’s turned out.
We just have some final finishing touches to make, and we’ll show you how she looks.
What’s next?
We still have a few weeks of walling and fire protection installation works to completed on-site, while also flying overhead containment grids in each Data Hall to allow for above ceiling cable runs. Beyond this, the envelope installation works will continue, moving onto floors, ceilings and access.