The past few weeks have seen lots of time spent on stabilising the migrated estate, so in terms of build progress there isn’t a huge amount to report. That said, there has of course been progress in a number of areas, as our efforts to bring the site to total completion continue.
First aid kits have been installed in various key locations around the facility
A look at the first aid kit in the first data hall
Large headway has been made in fitting out the remaining doors with their furniture and door closers
A fourth layer of filtration has been added to the cold corridor, which acts as the first filtration point, catching large particulates on their entry to the building
To complete the reception entrance way, we had to raise the level of the entry floor to match the main floor
After raising the level, we could lay our new hard wearing entry mat / carpet
Finishing thresholds fitted to the entry way
A look at the completed entrance