The past few weeks have seen lots of time spent on stabilising the migrated estate, so in terms of build progress there isn’t a huge amount to report. That said, there has of course been progress in a number of areas, as our efforts to bring the site to total completion continue.

Large headway has been made in fitting out the remaining doors with their furniture and door closers

A fourth layer of filtration has been added to the cold corridor, which acts as the first filtration point, catching large particulates on their entry to the building