We are now rapidly approaching readiness for initial occupation, with this week seeing completion of the power commissioning, and the deployment of the core network.
A completed mains bypass panel, ahead of a final output to the custom distribution boards
Three of the first four custom power distribution panels having their internal components fitted, ahead of wiring
A look at the 16A and 32A commando sockets fitted to our laser cut and painted doors, ready for fitting onto the panels
A look at the upper half of one of the 16A distribution panels ahead of any termination
A look at the upper internals of the distribution panels with termination completed, with just the connections to the sockets left to complete
Earthing connections to the commando sockets installed
A look at the external louvred panels that will allow our dynamic cooling system to ‘breathe’ external air
Our BMS interface in the electrical intake room, which will allow for instant facility status read-outs – there will be many of these around the site
Custom lights fitted to our UPS bypass panels for immediate load status information
Temporary connections in place in the meet me room while one side of our network is configured by our network engineers
Network harnesses in place between our core and the distribution racks in each row