This week has seen works under way in the electrical intake room, as well as other power-related areas throughout the site.
Glands being fitted to the top of the main generator breaker cabinet
A look at some of the copper inside of the main generator breaker cabinet
Here we see the generator / backup supply side of the electrical intake room taking shape
A look at the internals of the generator breaker cabinet, as the first two gen-sets are being terminated
A look at the internals of the generator ATS
Current generator feeds as they enter the breaker cabinet
External facials of the generator control and distribution cabinets reaching completion
A look at progress on internal cabling
BT circuit now live inside of the meet me room
Related