London Central Build Blog – Week 45

This week saw the first of our generators land on site, which is a massive step forwards for us, and allows for the power side of the build project to begin in earnest after Christmas – essentially the final phase ahead of moving existing clients into the new site.

Our Christmas cards for 2014 headed out to their recipients!

Our Christmas cards for 2014 headed out to their recipients!

First two generator sets arriving at site

First two generator sets arriving at site

First two generator sets arriving at site

First two generator sets arriving at site

First set being lifted into place inside of the compound

First set being lifted into place inside of the compound

First and second sets in place inside of compound

First and second sets in place inside of compound

A closer look at the backup generator sets

A closer look at the backup generator sets

A closer look at the backup generator sets

A closer look at the backup generator sets

Final pieces of ductwork being installed to complete cooling system air handling

Final pieces of ductwork being installed to complete cooling system air handling

Final pieces of ductwork being installed to complete cooling system air handling

Final pieces of ductwork being installed to complete cooling system air handling

The arrival of the first generator sets is a big milestone for us as we head towards Christmas for a short period of well earned rest.

Our generators will always run at N+1. When at capacity, we will have 5 identical units inside of our compound, with a new unit added each time additional capacity is required to maintain the level of redundancy that we have specified.