This week saw the first of our generators land on site, which is a massive step forwards for us, and allows for the power side of the build project to begin in earnest after Christmas – essentially the final phase ahead of moving existing clients into the new site.
The arrival of the first generator sets is a big milestone for us as we head towards Christmas for a short period of well earned rest.
Our generators will always run at N+1. When at capacity, we will have 5 identical units inside of our compound, with a new unit added each time additional capacity is required to maintain the level of redundancy that we have specified.