London Central Build Blog – Week 41 / 42

This fortnight has seen plenty of progress on various elements of the project which have been in a state of half-completion for a while. With the nature of a project this complex, unfortunately it is not as simple as starting an element of the project, seeing it through to completion and moving onto the next – everything is interconnected and various aspects of the build are in progress at the same time.

As such, the progress of the build ebbs and flows depending on how close to completion various elements of the project are.

The reason for combining two weeks into a single post here is that the number of photos taken of various elements over the course of this period has been limited. This is because whilst works continue, various planning and development meetings have been occurring behind the scenes, which naturally take up lots of management time.

A look at the cooling stack as the top duct and louvred panel assembly is fixed in place

A look at the cooling stack as the top duct and louvred panel assembly is fixed in place

A closer look at the top assembly ahead of connecting ductwork between the fan and coolers

A closer look at the top assembly ahead of connecting ductwork installations between the fan and coolers

An 'up-high' view of the first cooler stack in its final position, ahead of final ducting connections

An ‘up-high’ view of the first cooler stack in its final position, ahead of final ducting connections

A view through the progressing assembly of the second cooling stack

A view through the progressing assembly of the second cooling stack

The second stack's intake fan being installed into the cold corridor enclosure

The second stack’s intake fan being installed into the cold corridor enclosure

A closer look at the intake fan, with the opening for the extraction duct work and fan to the left (for recirculation)

A closer look at the intake fan, with the opening for the extraction duct work and fan to the left (for recirculation)

Second stack nearing completion, with second wet box and primary louvred panel installed

Second stack nearing completion, with second wet box and primary louvred panel installed

Second cooling stack flow control duct chamber installed

Second cooling stack flow control duct chamber installed

Mains water feed and control module for first stack being installed

Mains water feed and control module for first stack being installed

A look at the mains feed being installed along the length of the cold corridor

A look at the mains feed being installed along the length of the cold corridor

Delivery of final cooling system custom-made duct work pieces

Delivery of final cooling system custom-made duct work pieces

Delivery of final cooling system custom-made duct work pieces

Delivery of final cooling system custom-made duct work pieces

Power reinstated to facility loading bay roller shutters

Power reinstated to facility loading bay roller shutters

Power reinstated to facility loading bay roller shutters

Power reinstated to facility loading bay roller shutters

Delivery of further APC racks

Delivery of further APC racks

Delivery of further APC racks

Delivery of further APC racks

Cable pulling to finalise first floor data hall lighting systems

Cable pulling to finalise first floor data hall lighting systems

Some BT termination equipment installed in meet me room for specialist services

Some BT termination equipment installed in meet me room for specialist services

Secondary BT termination equipment installed in meet me room for specialist services

Secondary BT termination equipment installed in meet me room for specialist services

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.