London Central Build Blog – Week 40

This week has seen the completion of all major external works, with exception of course given to the generators, some minor armoured barrier installations and general cleaning / painting.

Fencing assembly coming together

Fencing assembly coming together

Gates being assembled

Gates being assembled

A corner of the fencing assembly reaching completion

A corner of the fencing assembly reaching completion

Pedestrian gate installed down roadside of the facility

Pedestrian gate installed down roadside of the facility

Main run of fencing reaching completion

Main run of fencing reaching completion

Main run of fencing complete, excluding razor wire and skip access panel

Main run of fencing complete, excluding razor wire and skip access panel

Spiral fire exit staircase installation underway

Spiral fire exit staircase installation under way

First section of staircase installed

First section of staircase installed

Staircase nearing landing level at first floor data hall fire exit

Staircase nearing landing level at first floor data hall fire exit

Landing platform and hand rail assembly installed

Landing platform and hand rail assembly installed

A look at the staircase as final fixings are made

A look at the staircase as final fixings are made

View from the first floor data hall fire exit onto the new staircase

View from the first floor data hall fire exit onto the new staircase

The completed fire exit staircase

The completed fire exit staircase

The completed fire exit staircase

The completed fire exit staircase

A view of the staircase and other exit routes, along with office-side plant hardware at rear of facility, ahead of fencing in

A view of the staircase and other exit routes, along with office-side plant gear at rear of facility, ahead of fencing in

An additional APC delivery with new cabinets for deployment in first floor data hall

An additional APC delivery with new cabinets for deployment in first floor data hall

Cooling stack frame reaching completion ahead of final ductwork assembly

Cooling stack frame reaching completion ahead of final ductwork assembly