Much like last week, as we reach the closing stages of the project progress is solid in a number of key areas. The cooling system has again taken great strides towards completion, and many rack enclosures are now in the data hall ready for building out the first pods.
Extraction duct work sleeving installed into walls
Fans being installed into extraction duct work
Extraction fan installed into duct work
A look at the highly efficient extraction fans which form part of our intelligent cooling system
A look at one of the custom 3-way duct and actuated louvred panel systems which control the remixing of air inside of the cooling system
Second wetbox cooler fitted atop the first cooling stack minus filter panels
Delivery of our palisade fencing system ready for enclosing the generator plant area
Delivery of our palisade fencing system ready for enclosing the generator plant area
The various gates which form part of our rear compound enclosure
Corner post section being constructed
Gate posts ahead of hanging the first set of main gates
First gate hung in place
Second gate hung, completing the first gate assembly ahead of installing palisades
A view down the main run of compound enclosure posts
Delivery of our specialist APC AR3200 lockable half rack enclosures