London Central Build Blog – Week 37

The flooring has taken shape this week, along with completion of the first two pod containment systems. We are now ready for a final deep clean and for racks to begin making their way up to the first floor data hall.

On site construction of the cold aisle containment plenums

On site construction of the cold aisle containment plenums

Completed containment system with test rack in position

Completed containment system with test rack in position

A look across the first floor data hall as final technical flooring is installed

A look across the first floor data hall as final technical flooring is installed

The rack pods will be built out on the black areas of the floor

The rack pods will be built out on the black areas of the floor

The flooring colour scheme aids with visualising the layout of the data hall ahead of total pod population

The flooring colour scheme aids with visualising the layout of the data hall ahead of total pod population

Panorama as flooring around the first pod is completed

Panorama as flooring around the first pod is completed

Second pod flooring completed

Second pod flooring completed

Test rack positioning at end of first containment pod

Test rack positioning at end of first containment pod

Decorating continues in the ground floor facility access areas

Decorating continues in the ground floor facility access areas

Decorating continues in the ground floor facility access areas

Decorating continues in the ground floor facility access areas

As you can see, things are progressing quickly, with many areas of the facility coming together simultaneously. This puts us in very good stead to have all assembly works completed within the next 3 to 4 weeks, leaving just the connections to bring the data centre to life ready for occupancy.