London Central Build Blog – Week 14

Week 14 has seen further progress on technical areas of the facility, including the build room for the first data hall, and the meet-me / core network room. Structural works in the technical side of the facility, such as the construction of the cold plant corridor, will begin very shortly.

Build room for first data hall ready for decoration

Installation of new metal hung ceiling in shower room

Installation of new metal hung ceiling in shower room

Glass pane installation in board room partitioning

Glass pane installation in board room partitioning

Completed board room partitioning

Another look at the completed board room

Finished board room ahead of table lid installations

Delivery of new exterior signage items

Test mount of signage on unfinished backboard without stand-offs

Our exterior sign is over 6 meters across, and is backlit with warm white LEDs. This will really make a bold statement in the local area, making our building stand out to visitors from a healthy distance.