London Central Build Blog – Week 13

Many areas of the new facility are now reaching completion, particularly in the ‘front of house’ expanses of the building. Apart from various finishing touches, more rooms have reached completion this week.

First UPS in place in electrical intake room

Customer kitchen area nearing completion

Customer kitchen area nearing completion

Entertainment centre and lockers in place in customer lounge

One of the 8 large flat screen TVs positioned around the new facility

Temporary systems now in place on ground floor

Flooring laid in reception lobby

Flooring in lobby completed, awaiting final decoration

Progress is very solid as we move towards the Summer. The heavy technical works in the first data hall are ready to commence in earnest, with works under way in the coming weeks to build our state-of-the-art man traps and cable management systems. Our large exterior signage is due for installation in the coming weeks also.