Week 11 has seen further decommissioning of our Sutton site, along with fantastic developments at our new London Central facility. The offices were properly unpacked this week, allowing the Bermondsey site head quarters to come online. There is still a way to go until they are exactly as we want them (those that know our team will know that we take great pride in making our offices as personal / identifiable as possible), but they are well on their way to becoming our new home.

Further decommissioning of data floor in Sutton

Office layout taking shape

NOC area ahead of deep cleaning

Cardboard recycling pile in reception

Customer Lounge starting to take shape

Customer Lounge starting to take shape

Next week will see our first deep clean, which will bring the facility into a new light after the first stage of works.