This week has seen extensive planning for the data floor works to begin in earnest. There have also been finalisations made to the cabling infrastructure feeding the office, as well as preparation works on the core services room ready for cable runs to begin on the network. Because much of the work at the London Central facility has been hidden from view, there are no worthy progress photos for this week, bar one shot showing the flooring in the large ground floor storage area reaching completion.
One area of interest is the secondary team decommissioning the London South (Sutton) facility. The office space has seen a transformation back to its post-refurbished empty state. We took great pride in the building of our Sutton facility, and it is saddening to see it decommissioned, however we are moving on to far bigger and better things in Bermondsey.
We will have some further pictorial updates for you in the coming weeks.