We have now migrated our existing customer base across to the new site, which is a massive milestone for us. As you are probably aware from reading our blog, the site still has some finishing touches to be completed, and lots of system integration work to undertake, however as soon as the site was deemed ready to hold clients, we moved everyone across.
At this moment in time, many clients are still being housed in their Dell racks, as used in Sutton and in the temporary facility in Docklands. These will be swapped over to the new APC cabinets in the coming weeks / months.
This is a monumental milestone in the build project, as the site is now actively handling our live estate at full resilience.